Salmonberry Creek Restoration
|
Mid-Puget Sound Fish Enh Grp; Salmonberry Creek Restoration (#00-1729)
02/01/2004, Attachment #18024, February 4, 2005 INSPECTION PHOTOS
|
|
|
Project Status:  |
Closed Completed since 11/22/2006 |
|
|
Project Type:  |
Acquisition & Restoration |
  |
|
Funding Board:  |
Salmon Recovery Funding Board
|
    Funding |
  |
|
    Links |
  |
|
|
The Salmonberry Creek restoration project will create a side channel that will flow through a series of ponds that mimic beaver pond rearing areas for coho and cutthroat. This channel will help to alleviate the adult stranding that takes place annually due to stream channelization and invasive plant species within this agricultural area. This stranding is occurring before the salmon reach their spawning grounds. The side channel will add approximately 5,000 lineal feet of rearing habitat and ease adult migration through this channelized segment. This project is expected to significantly increase the juvenile coho and cutthroat numbers and survival rates. This area is completely devoid of riparian vegetation, therefore, a riparian buffer will also be re-established for an average of 100 feet wide along the created channel and the area between the new channel and the existing creek. Conservation easements will be secured for long-term protection of the project and the resource.
|
General Area:
|
|
Salmonberry Creek is a tributary to Long Lake and Curley Creek.
|
County:
|
|
Kitsap
|
Legislative District:
|
|
26
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Clovos Passage/Carr Inlet
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kitsap
|
Sections:
|
|
06
|
Township:
|
|
T23NR02E
|
Coordinates:
|
|
47.51202216 -122.59533431
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Salmonberry Creek Restoration (#1)
|
Administrative costs (Acq), Easement, Other restoration activities, Planting (C.5.c.1), Riparian Plant removal / control (C.5.h.1), Standard Incidentals
|
$167,152
|
| Total | $167,152 |
Amounts may not be complete
Worksite Name | | Property Name | | Actual Acquisition Acres | Actual Acquisition Cost |
Salmonberry Creek Restoration (#1)
|
|
Property 1 - Private Landowner
|
|
3.73
|
$44,861
|
Salmonberry Creek Restoration (#1)
|
|
Property 2 - Private Landowner
|
|
2.50
|
$140,695
|
Salmonberry Creek Restoration (#1)
|
|
Property 3 - Private Landowner
|
|
3.49
|
$16,621
|
Salmonberry Creek Restoration (#1)
|
|
Property 4 - Private Landowner
|
|
3.00
|
$17,156
|
Salmonberry Creek Restoration (#1)
|
|
Property 5 - Private Landowner
|
|
3.02
|
$15,880
|
Salmonberry Creek Restoration (#1)
|
|
Property 6 - Private Landowner
|
|
2.36
|
$13,229
|
Salmonberry Creek Restoration (#1)
|
|
|
|
4.17
|
$0
|
| | | Total | 22.27 | $248,442 |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Riparian Habitat Project |
Planting (C.5.c.1) |
|
Acres Planted in riparian (C.5.c.3)
|
17.0
|
Riparian Plant removal / control (C.5.h.1) |
|
Acres of riparian treated for plant removal/control (C.5.h.3)
|
16.9
|
Real Property Acquisition |
Acquisition or lease of land, wetland or estuarine for conservation (C.10.c.1) |
|
Miles Of Streambank Protected By Land or Easement Acquisition (C.10.c.5)
|
0.38
|
Milestone Name | Target Date | Description |
Project Start
|
01/26/2001
|
|
Survey Complete
|
01/15/2002
|
|
Order Appraisal Review(s)
|
02/28/2002
|
|
Bid Awarded
|
03/01/2002
|
|
Monitor/Steward Plan Submitted
|
06/01/2003
|
|
Monitoring Started
|
06/01/2003
|
Includes pre-construction.
|
A&E Plans Submitted
|
06/15/2003
|
|
Construction Started
|
06/15/2003
|
|
RFP Complete
|
07/01/2003
|
Sent to contractors
|
Applied for Permits
|
07/01/2003
|
|
Fencing Complete
|
03/31/2005
|
Livestock exclusion after construction.
|
Construction Complete
|
03/31/2005
|
|
Baseline Docum. Complete
|
07/01/2005
|
|
Purchase Agreement Signed
|
09/30/2005
|
Conservation Easements
|
Acquisition Closing
|
02/28/2006
|
|
Recorded Documents to Mgmt Agy
|
03/31/2006
|
|
Agreement End Date
|
03/31/2006
|
|
Final Docs/Billing to Mgmt Agy
|
08/31/2006
|
|
Monitoring Complete
|
03/31/2008
|
3 years - Standard success monitoring.
|