PRISM Project #00-1762 (Completed)
Barrier Prioritization Surveys - WRIA 15
    Project Details    
Project Status:  Closed Completed since 09/07/2006
 
Project Type:  Planning
Project Sponsor:  Pierce Conservation District
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $70,156
Total RCO Grant: $70,156 (59%)
Sponsor Match: $48,000 (41%)
Total Agreement: $118,156 (100%)
              Links
 

    Project Description    
The Pierce Conservation District is in the process of completing an inventory of fish passage barriers in the andromous zone of East WRIA 15. Over 140 structures have been identified, with 56% of those determined to be barriers to fish passage. The next step is to prioritize those barriers, so higher priority projects can be adressed first. Prioritization is conducted following WDFW protocol as described in the Fish Passage Barrier Assessment and Prioritization Manual, and involves completing a field habitat survey of stream reaches above fish passage barriers to determine the quantity and quality of available habitat. Prioritization also considers species utilization, stock status for species utilizing the stream, and project cost. The result is a Priority Index (PI) score, which can be used to directly compare priorities of proposed projects. PI scores on some culverts identified by the Conservation District identified culverts in the Puyallup watershed have been used to rank projects for the 2000 construction season. After prioritization has been completed, the top ten barrier culverts will be addressed and preliminary design work will be completed. The prioritized list will also be available for Enhancement Groups, Conservation Districts, Cities, Counties, and other entities to use as a project list from which to work.

    Project Contacts    
         
Project Sponsor: Pierce Conservation District Lead Entity: West Sound Partners for Ecosystem Recovery
  Project Contact: Kathryn Mahan

(253) 845-9770 110
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
General Area:   Key Peninsula and Gig Harbor watersheds.
County:   Pierce
Watershed Administrative Unit:   Clovos Passage/Carr Inlet
HUC8:   Puget Sound (17110019)
WRIA:   Kitsap
Sections:   11
Township:   T21NR01W

    Worksites    
Worksite NameScope of WorkActual Planning Cost
Key Peninsula, Gig Harbor Barrier Survey (#1) Instream survey (B.2.c) $118,156
 Total$118,156
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 40.0

Salmonid Habitat Assessment / Inventory
      Instream survey (B.2.c)
Stream Miles Assessed (B.2.c.2) 8.00
Stream miles assessed that contained salmonids (B.2.c.3) 8.00
Stream Miles Assessed That Needed Restoration (B.2.c.4) 8.00
Number of fish passage impediments identified (B.2.c.6) 5

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 02/01/2001
Data Gathering Started 02/01/2001
Draft Rpt Reviewed by Mgmt Agy 01/01/2003
Final Report Completed 02/01/2003 Database/CD ROM
Agreement End Date 09/30/2004
Final Docs/Billing to Mgmt Agy 12/31/2004


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 00-1762 Agreement & General Provisions 03/08/01.pdf 09/10/2007

Back to top Date of last change: 10/04/2023