Dogfish Creek Estuary Restoration
|
Poulsbo City of; Dogfish Creek Estuary Restoration (#01-1272)
09/19/2003, Attachment #5804, Park Sign - Funding project sponsors - IAC etc.
|
|
|
Project Status:  |
Closed Completed since 09/29/2006 |
|
|
Project Type:  |
Acquisition & Restoration |
  |
|
Funding Board:  |
Salmon Recovery Funding Board
|
    Funding |
  |
|
    Links |
  |
|
|
This project will restore 1,200' of estuarine shoreline and 13 acres of adjacent upland habitat along Dogfish Creek estuary. The project is located on Liberty Bay on the west side of central Puget Sound. This project is contiguous to a major 2nd Round SRFB project: removal of a culvert/construction of a bridge to restore over 4 acres of estuarine habitat. This shoreline/estuary complex is listed as critical habitat by NMFS for the recovery of Puget Sound chinook salmon and is a designated shoreline conservancy area by Poulsbo zoning. Dogfish Creek has important runs of chinook, coho, chum, steelhead salmon and searun cutthroat trout. This project is an integral component of the City Parks Department's future Salmon Park and planned Poulsbo Environmental Learning Center.
The project will restore native conifers and complex habitat structure to the shoreline. The land will be designated as passive open space and set aside for habitat restoration. The public will access the property through designated trails to learn about habitat restoration, the ecological interaction between the terrestrial and aquatic (freshwater and estuarine) environments, and observe fish and wildlife.
|
General Area:
|
|
Project is located at the northern tip of Liberty Bay at the mouth of Dogfish Creek.
|
Waterbody:
|
|
Puget Sound/Pacific Ocean
|
County:
|
|
Kitsap
|
Legislative District:
|
|
23
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Liberty-Miller-Appletree
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kitsap
|
Sections:
|
|
15
|
Township:
|
|
T26NR01E
|
Coordinates:
|
|
47.74729141 -122.65323769
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Dogfish Creek Estuary Restoration (#1)
|
Administrative costs (Acq), Channel modification (C.9.c.1), Creation of new estuarine area (C.9.q.1), Estuarine plant removal / control (C.9.j.1), Land, Restored land maintained (C.11.c.1), Standard Incidentals
|
$153,023
|
| Total | $153,023 |
Amounts may not be complete
Worksite Name | | Property Name | | Actual Acquisition Acres | Actual Acquisition Cost |
Dogfish Creek Estuary Restoration (#1)
|
|
Property 1 - Private Landowner
|
|
13.00
|
$979,129
|
| | | Total | 13.00 | $979,129 |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Estuarine / Nearshore Project |
Channel modification (C.9.c.1) |
|
Yards (linear measure) of Channel Modified/Created (C.9.c.2)
|
100
|
|
Acres of Estuary Treated (C.9.c.3)
|
4.0
|
Estuarine plant removal / control (C.9.j.1) |
|
Acres of Estuary Treated for plant removal/control (C.9.j.3)
|
4.0
|
Creation of new estuarine area (C.9.q.1) |
|
Acres of Estuary Created (C.9.q.2)
|
0.3
|
Site Stewardship Project |
Restored land maintained (C.11.c.1) |
|
Acres of restored land maintained (C.11.c.2)
|
8.0
|
Milestone Name | Target Date | Description |
Project Start
|
05/01/2001
|
|
Order Appraisal Review(s)
|
05/15/2002
|
Four parcels/short plat
|
Purchase Agreement Signed
|
06/30/2002
|
|
Environmental Clearance Rec'd
|
07/01/2002
|
|
Acquisition Closing
|
07/01/2002
|
|
Recorded Documents to Mgmt Agy
|
08/01/2002
|
|
Monitor/Steward Plan Submitted
|
03/01/2003
|
|
A&E Plans Submitted
|
09/01/2003
|
|
Monitoring Started
|
06/01/2004
|
|
Applied for Permits
|
05/01/2005
|
|
Construction Started
|
09/01/2005
|
Restoration work
|
Noxious Weed Control Complete
|
09/30/2005
|
|
Construction Complete
|
03/31/2006
|
|
Monitoring Complete
|
03/31/2006
|
On-going
|
Agreement End Date
|
06/30/2006
|
|
Final Docs/Billing to Mgmt Agy
|
09/30/2006
|
|