Sinclair Inlet North Shore Estuary Res.
|
Bremerton Port of; Sinclair Inlet North Shore Estuary Res. (#01-1281)
Attachment #42459, Parametrix Gorst pics 001
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The purpose of this project is to restore to 1942 vintage the western most 1500 feet of the Northern shoreline of Sinclair Inlet and to increase the productive area of existing estuary by 1.7 acres. (See enclosed, photos, mapping, and drawings) Sinclair Inlet along with it's shoreline and estuary is a major passage way and nursery for Chinook, Coho, Chum Steelhead Salmon and Searun Cutthroat trout entering and leaving Gorst Creek. Several miles of the Northern shoreline have been hardened with riprap to accommodate SR 16 and PSNS railroad. The only portion of Northern shoreline between Gorst and Navy Yard City Interchange that can be restored is the subject of this grant request.
This project will include two phases. Both phases together will restore 1,820 feet of shoreline and 4.2 acres of estuary. Phase 1 of the project, the subject of this grant, will effect the cleanup of all 1160 feet of the existing shoreline, restore 620+ feet of shoreline, and create 1.7 acres of additional estuary. Phase two of the project will be the subject of further grant requests and will be completed when additional funding is available. (See enclosed chart for further site information).
The importance of estuarine and shoreline habitat to salmon productivity is well documented. There is a direct correlation between outgoing wild chinook smolt survival from Gorst Creek and the health, and configuration of the shoreline of Sinclair Inlet. Over 1000 wild Chinook spawn in Gorst Creek.
|
General Area:
|
|
Northshore of Sinclair Inlet near mouth of Gorst Creek.
|
Waterbody:
|
|
Puget Sound/Pacific Ocean
|
County:
|
|
Kitsap
|
Legislative District:
|
|
26
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
S Sinclair Inlet
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kitsap
|
Coordinates:
|
|
47.52915069 -122.69392945
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Sinclair Inlet Northshore Restoration (#1)
|
Architectural & Engineering (A&E), Creation of new estuarine area (C.9.q.1), Estuarine plant removal / control (C.9.j.1), Implementation monitoring, Regrading of slope (C.9.i.1), Removal of existing fill material (C.9.g.1), Shoreline armor removal or modification (C.9.k.1)
|
$468,155
|
| Total | $468,155 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Sinclair Inlet Northshore Restoration (#1)
|
|
Property 1 - Property - Worksite #1
|
Local Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Estuarine / Nearshore Project |
Removal of existing fill material (C.9.g.1) |
|
Acres of Estuary Treated through fill material removal (C.9.g.2)
|
1.6
|
Regrading of slope (C.9.i.1) |
|
Acres of Estuary Treated through slope regrading (C.9.i.2)
|
1.6
|
Estuarine plant removal / control (C.9.j.1) |
|
Acres of Estuary Treated for plant removal/control (C.9.j.3)
|
1.6
|
Shoreline armor removal or modification (C.9.k.1) |
|
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
|
0.12
|
|
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
|
1.6
|
Creation of new estuarine area (C.9.q.1) |
|
Acres of Estuary Created (C.9.q.2)
|
1.7
|
Milestone Name | Target Date | Description |
RFP Complete
|
07/15/2001
|
Consultant selected 8/15/01; SRFB funds applied for and awarded in 3rd Round
|
Project Start
|
04/12/2002
|
Landowner willingness accepted and planning started on 6/1/01
|
Applied for Permits
|
07/26/2002
|
JARPA Submission
|
Monitor/Steward Plan Submitted
|
12/01/2002
|
Will work with Suquamish Tribe on monitoring
|
Monitoring Started
|
01/01/2003
|
Beginning of baseline monitoring
|
A&E Plans Submitted
|
11/01/2004
|
Completion of design and "draft" bid package
|
Bid Awarded/Consultant Hired
|
05/01/2005
|
Proposed Summer '03 construction
|
Construction Started
|
05/15/2006
|
Starting with opening of HPA "fish window"
|
Construction Complete
|
09/15/2006
|
|
Monitoring Complete
|
12/01/2006
|
May be extended
|
Agreement End Date
|
12/30/2006
|
|
Final Docs/Billing to Mgmt Agy
|
03/31/2007
|
|