Project Snapshot
PRISM Project #05-1119 (Completed)
Niepoth Iguchi - Cool Cr R3
    Project Details    
Mid-Puget Sound Fish Enh Grp; Niepoth Iguchi - Cool Cr R3 (#05-1119)

05/04/2005, Attachment #15348, NiepothDSculvert1
Mid-Puget Sound Fish Enh Grp; Niepoth Iguchi - Cool Cr R3 (#05-1119) 05/04/2005, Attachment #15348, NiepothDSculvert1

Mid-Puget Sound Fish Enh Grp; Niepoth Iguchi - Cool Cr R3 (#05-1119)

05/04/2005, Attachment #15348, NiepothDSculvert1
Project Status:  Closed Completed since 02/08/2008
 
Project Type:  Restoration
Project Sponsor:  Mid-Puget Sound Fisheries Enhancement Group
Funding Board:  Recreation and Conservation Office
              Funding  
FFFPP Grants: $144,313
Total RCO Grant: $144,313 (96%)
Sponsor Match: $6,500 (4%)
Total Agreement: $150,813 (100%)
              Links
 

    Project Description    
This project will replace a 36-inch CMP culvert on a private driveway serving 5-6 residences on Cool Creek, Kitsap County, WA. The new culvert will be 11 feet in diameter, and will conform to WDFW's no-slope method as recommended by WDFW engineering staff. The existing culvert represents a partial barrier to upstream fish migration. This stream is known to support both coho salmon and resident cuthroat trout. Other native fish species may also be present. Both the upstream and downstream habitat is considered "excellent". This project will provide full, unimpeded fish passage to 0.94 miles of upstream habitat (location of next complete passage barrier). Additionally, this project could provide incentive to correct this upstream barrier, provding fish passage to the remaining 0.61 miles. This would result in a total gain of 1.55 miles of excellent fish habitat. In addition to the FFFPP grant program, Landowners and Mid Sound Fisheries, the Kitsap Conservation District has provided funds for survey and initial design work, and continue to be a project partner.

    Project Contacts    
         
Project Sponsor: Mid-Puget Sound Fisheries Enhancement Group Lead Entity: West Sound Partners for Ecosystem Recovery
  Project Contact: Troy Fields

(206) 529-9467
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Tara Galuska
tara.galuska@rco.wa.gov
   

    Project Location    
General Area:   near Port Orchard
Waterbody:   Unnamed
County:   Kitsap
Legislative District:   26
Congressional District 2022:   06
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Clovos Passage/Carr Inlet
HUC8:   Puget Sound (17110019)
WRIA:   Kitsap
Sections:   07
Township:   T23NR02E
Coordinates:   47.50052841
-122.60706035

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Niepoth (#1) Architectural & Engineering (A&E), Culvert installed or improved (C.2.f.1), Fish passage blockages removed or altered (C.2.c.1), Road-crossing removal (C.2.i.1) $19,623
 Total$19,623
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Niepoth (#1)   Property 1 - Property - Worksite #1 Private
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

Fish Passage Improvement
      Fish passage blockages removed or altered (C.2.c.1)
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2) 1
      Culvert installed or improved (C.2.f.1)
Miles of stream made accessible by culvert installation/repair (C.2.f.3) 0.94
      
Number of blockages / impediments / barriers impeding passage (C.2.b.4) 1

    Project Permits    
Permit TypeApplied
Date
Received
Date
Expiration
Date
Permit Number
Forest Practices Application [Forest & Fish]
Hydraulics Project Approval [HPA]

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/01/2005
30% Design Review/Cost Check 06/21/2006
Applied for Permits 08/01/2006
Bid Awarded/Contractor Hired 08/15/2006
Construction Started 09/01/2006
Construction Complete 09/15/2006
Annual Project Billing Due 07/15/2007
Agreement End Date 12/31/2007
Final Docs/Billing to Mgmt Agy 02/29/2008


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State FFFPP Agreement.pdf 12/09/2010
Agreement - State 05-1119_FFFPP Project Agreement.pdf 07/17/2006
Amendment request Cost Increase Spreadsheet.pdf 10/29/2007
Amendment request Request for Additional Funds Cool Ck FINAL.pdf 10/29/2007
Barrier evaluation form Niepoth_BEF.pdf 05/05/2005
Correspondence hpa revised.pdf 10/09/2007
Correspondence Sept 10, 2007 Pilchuck MEMO.pdf 10/03/2007
Correspondence CoolCreekFaultLetter8 23 2007.pdf 09/20/2007
Correspondence Landowner Agreement.pdf 09/11/2007
Correspondence budget cool creek.pdf 05/02/2007
Correspondence 05-1119_FFFPP Funding ltr 2-10-06.pdf 02/15/2006
Correspondence Niepoth - Cool Ck concept drawing.ppt 06/01/2005
Correspondence Niepoth Cool Ck. cost est.pdf 06/01/2005
Engineer cost estimate Phase 2 Quote.pdf 10/03/2007
Engineer cost estimate Phase 1 Invoice (revised).pdf 10/03/2007
Expanded barrier evaluation form EBEF2005.pdf 09/01/2005
Landowner application Iguchi_application.pdf 11/09/2005
Landowner application FFFPP_initial_tracking_form.pdf 04/06/2005
Landowner application niepoth_application.pdf 04/06/2005
Map: Site Location niepoth_map.pdf 04/06/2005
Photo Niepoth_CoolCr_Rd_2.JPG.jpg 05/23/2022
Photo Niepoth_CoolCr_Rd_1.JPG.jpg 05/23/2022
Photo Niepoth_CoolCr_Outlet_1.JPG.jpg 05/23/2022
Photo Niepoth_CoolCr_Inlet_3.JPG.jpg 05/23/2022
Photo Niepoth_CoolCr_Inlet_2.JPG.jpg 05/23/2022
Photo Niepoth_CoolCr_Inlet_1.JPG.jpg 05/23/2022
Photo Niepoth_CoolCr_DS_1.JPG.jpg 05/23/2022
Photo US Cool at high flow dec 3.jpg 12/11/2007
Photo Cool Cr road erosion.jpg 12/11/2007
Photo Cool Cr DS high flow.jpg 12/11/2007
Photo Andy Pavone and Michael Ahr.jpg 11/05/2007
Photo Bob at Cool Cr.jpg 11/05/2007
Photo Cool Rd Shot.jpg 11/05/2007
Photo Cool Cr US.jpg 11/05/2007
Photo Cool CR DS.jpg 11/05/2007
Photo NiepothOutletAfter1.jpg 11/01/2007
Photo completed project downstream Oct. 31, 2007.jpg 11/01/2007
Photo looking downstream Oct 31 07.jpg 11/01/2007
Photo Cool Cr culvert failure3.jpg 07/03/2007
Photo Cool Cr culvert failure2.jpg 07/03/2007
Photo Cool Cr culvert failure.jpg 07/03/2007
Photo Cool Cr after failure.jpg 07/03/2007
Photo Cool Creek Rd during construction.jpg 07/03/2007
Photo Road leading to culvert.jpg 04/24/2006
Photo NiepothUSchannel.jpg 05/05/2005
Photo NiepothDSchannel.jpg 05/05/2005
Photo NiepothUSculvert2.jpg 05/05/2005
Photo NiepothDSculvert1.jpg 05/05/2005
Site map WDFW 05-1119_Niepoth_site_map.pdf 09/27/2005
Watershed map WDFW 05-1119_Niepoth_wau_map.pdf 09/27/2005

Back to top Date of last change: 01/09/2023