PRISM Project #05-1471 (Completed)
Beaconsfield on the Sound Feasibility
    Project Details    
Project Status:  Closed Completed since 07/08/2008
 
Project Type:  Planning
Project Sponsor:  Forterra NW
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon State Projects: $41,597
Total RCO Grant: $41,597 (85%)
Sponsor Match: $7,340 (15%)
Total Agreement: $48,938 (100%)
              Links
 

    Project Description    
Beaconsfield on the Sound is composed of 33 small ~1/10 acre, independently owned parcels along the marine nearshore of Puget Sound. The area consists of 4 acres of historic feeder bluffs, shallow habitat, tidelands, and over ΒΌ mile of saltwater beach that are critical for sustaining nearshore and habitat forming processes essential for rearing, refuge, foraging, migration and transition to saltwater habitats for all anadromous salmonids. Beaconsfield on the Sound has been listed as a priority action area (NS-11) by the WRIA 9 Salmon Habitat Plan (2005)



In its current state the feeder bluff has been disconnected from the nearshore by a bulkhead at the toe of slope that extends across 80% of the property. This bulkhead impedes sediment inputs into the nearshore system by preventing sediment erosion, drift, and accretion down drift. Disruption of these processes ultimately impacts forage fish habitat and salmonid habitat.



The goals of the Beaconsfield on the Sound feasibility study are two-fold: 1) assess the impacts of removing a 1/4 mile of shoreline armoring from the historic feeder bluff in order to reconnect sediment processes to the Puget Sound nearshore, and 2) assess landowner willingness to participate in this restoration project through acquisition of fee simple or donation to Cascade Land Conservancy. To date three property owners have expressed willingness to transfer their ownership.

    Project Contacts    
         
Project Sponsor: Forterra NW Lead Entity: Green/Duwamish and Central Puget Sound Watershed (WRIA 9) Lead Entity
  Project Contact: Joe Sambataro
jsambataro@tulaliptribes-nsn.gov
(360) 716-4619
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Kate McLaughlin
kate.mclaughlin@rco.wa.gov
(360) 815-0866
   

    Project Location    
General Area:   Normandy Park, King County
Waterbody:   Puget Sound/Pacific Ocean
County:   King
Legislative District:   33
Congressional District 2022:   07
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   S Elliott Bay/E Passage
HUC8:   Puget Sound (17110019)
WRIA:   Duwamish - Green
Coordinates:   47.41499945
-122.34695770

    Worksites    
Worksite NameScope of WorkActual Planning Cost
Beaconsfield on the Sound (#1) Conducting habitat restoration scoping and feasibility studies (B.1.b.8) $48,938
 Total$48,938
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 12.0

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 02/01/2006
Bid Awarded/Consultant Hired 03/01/2006
Data Gathering Started 04/01/2006
Draft Rpt Reviewed by Mgmt Agy 05/01/2007
Proposed Completion Date 06/01/2007
Final Report Completed 07/01/2007
Agreement End Date 07/01/2007
Final Docs/Billing to Mgmt Agy 10/01/2007


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State Full Salmon Agreement.pdf 04/18/2011
Agreement - State Agreement - This is not complete - see 4/18/11 attachment.pdf 05/06/2009
Agreement - State 05-1471_Salmon agreement Pages 1, 2 .pdf 05/09/2006
Amendment - State Name Change Ammendment.pdf 12/08/2011
Application authorization Authorization Memorandum_Beaconsfieldfinal.jpg 09/30/2005
Application authorization CLC Beaconsfield 081805_FINAL.pdf 08/19/2005
Correspondence Beaconsfield Lawsuit Settled 08-29-12.pdf 09/04/2012
Correspondence Beaconsfield Property Owners list.pdf 08/19/2005
Environmental Site Assessment Report Color Feasibility Study 11-22-06.pdf 06/17/2011
Final project report Other Final Report 4/30/08 .pdf 04/18/2011
Inspection Report Compliance Inspection 01-10-12.pptx 01/17/2012
Map beaconsfield feasibility.jpg 08/19/2005
News Article 05-1357_KC Salmon funds.pdf 02/01/2006
News Article 05-1471_KC Salmon funding.pdf 02/01/2006
Photo Property view from air.jpg 09/30/2005
Scope of work Black & White Feasibility Study 11/22/06.pdf 04/18/2011
Stewardship plan draft stewardship plan.pdf 09/30/2005
Visuals Photos.pdf 09/30/2005