Project Snapshot
PRISM Project #05-1591 (Completed)
Entiat Instream Habitat Improvements
    Project Details    
Project Status:  Closed Completed since 06/03/2008
 
Project Type:  Restoration
Project Sponsor:  Chelan County Natural Resources Department
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $231,203
Total RCO Grant: $231,203 (85%)
Sponsor Match: $40,801 (15%)
Total Agreement: $272,004 (100%)
              Links
 

    Project Description    
The Chelan County Natural Resources Department (CCNRD) will implement the Entiat Instream Habitat Improvement Project. This project was identified in the "aquatic habitat recommendations" contained in the Entiat WRIA 46 Management Plan, specifically Entiat Ecosystem Diagnosis and Treatment Analysis (EDT), Alternative Management Scenario 1 and 5 (see attached Plan).

The treatments are to be constructed within two general locations within the mainstem Entiat River: the Milne restoration site and the Hanan-Detwiler restoration site. The treatments in the Entiat Management Plan recommend: 1) construction of cross vanes or other appropriate structures in the lower mainstem Entiat, and 2) installation of "log retention structures" in the upper middle Entiat. The proposed project includes the placement of five (5) midstream boulder clusters, seven (7) rock barbs and six (6) LWD structures on both sides of the river at the Milne restoration site. At the Hanan-Detwiler restoration site, the project includes the installation of a rock cross-vane, a sluice gate, excavation of two pools, the placement of logs and rootwads, and riparian plantings.

The cross vane installation in the lower Entiat is intended to increase the amount of pool habitat and LWD loading, reduce channel confinement, and restore a measure of riparian function. The log structure action in the upper middle Entiat is intended to increase LWD density, backwater pools, high flow refuge habitat, and tail-out habitat and thus habitat diversity. These measures are consistent with the Entiat WRIA 46 Management Plan "diagnoses" for Entiat spring and late-run chinook.

    Project Contacts    
         
Project Sponsor: Chelan County Natural Resources Department Lead Entity: Upper Columbia Salmon Recovery Board Lead Entity
  Project Contact: Paul Heffernan
Paul.Heffernan@co.chelan.wa.us
(509) 667-6346
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
General Area:   From the confluence of the Columbia and Entiat Rivers, travel north up the Entiat River Valley, the proposed project area begins at Slackwater at approximately RM 5, and ends at Preston Creek at approximately RM 27.
Waterbody:   Columbia River, Entiat River
County:   Chelan
Legislative District:   12
Congressional District 2022:   08
Salmon Recovery Regions:   Upper Columbia River
Watershed Administrative Unit:   Lower Entiat
HUC8:   Upper Columbia-Entiat (17020010)
WRIA:   Entiat
Sections:   33
Township:   T26NR20E
Coordinates:   47.70410675
-120.32968651

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Entiat Instream Habitat Improvements (#1) Architectural & Engineering (A&E), Channel structure placement (C.4.d.1), Obtain permits, Planting (C.5.c.1), Streambank stabilization (C.4.e.1) $272,004
 Total$272,004
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Entiat Instream Habitat Improvements (#1)   Property 1 - Milne & Hanan-Detwiler Private
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

Instream Habitat Project
      Channel structure placement (C.4.d.1)
Miles of Stream Treated for channel structure placement (C.4.d.3) 0.22
Acres Of Streambed Treated for channel structure placement (C.4.d.4) 2.0
Pools Created through channel structure placement (C.4.d.5) 26
Number of structures placed in channel (C.4.d.7) 28

Permits
      Obtain permits
Number of permits required for implementation of project 5

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 03/01/2006 BOR analysis
Applied for Permits 03/01/2007 Locations identified
A&E Plans Submitted 04/01/2007 Completed structure design
Bid Awarded/Consultant Hired 07/01/2007 Contract awarded
Construction Started 08/01/2007 Mobilize equipment and materials
Construction Complete 09/30/2007 Instream and bank stabilization
Agreement End Date 11/01/2008
Final Docs/Billing to Mgmt Agy 12/30/2008


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State Salmon project agreement.pdf 05/09/2006
Correspondence 04-07-08 Cost Increase Amendment.pdf 04/10/2008
Design document Rock Weir Design Example.pdf 09/27/2005
Evaluation proposal Entiat Evaluation Proposal.pdf 09/28/2005
Final project report Final Report 4-30-08.pdf 05/29/2008
Final project report Milne Barb Construction Photos.pdf 05/29/2008
Final project report Entiat Instream Final Report 04-08.ppt 05/29/2008
Map Entiat River Map.jpg 09/30/2005
News Article Excavator Placing Boulders.jpg 05/29/2008
Photo Hanan-Detwiler Cross Vane 1.jpg 05/30/2008
Photo Hanan-Detwiler Diversion and Sluice Gate.jpg 05/30/2008
Photo Hanan-Detwiler Entrance to Diversion Ditch at Cross Vane.jpg 05/30/2008
Photo P1010999.jpg 05/30/2008
Photo Hanan-Detwiler LWD Snowy.jpg 05/30/2008
Photo P1020251.jpg 05/30/2008
Photo Hanan-Detwiler Diversion Ditch.jpg 05/30/2008
Photo Hanan-Detwiler LWD.jpg 05/30/2008
Photo Hanan-Detwiler Cross Vane.jpg 05/30/2008
Photo P1020232.jpg 05/30/2008
Photo Milne Barb with Sluicegate and LWD.jpg 05/30/2008
Photo Milne LWD 1.jpg 05/30/2008
Photo Milne Closeup of rootwads and barbs..jpg 05/30/2008
Photo Milne LWD.jpg 05/30/2008
Photo Rootwads#6.jpg 05/30/2008
Photo Rootwads#6#7.jpg 05/30/2008
Photo rootwad&cable.jpg 05/30/2008
Photo rootwad#2A.jpg 05/30/2008
Photo rootwad#2.jpg 05/30/2008
Photo Diversion Barb 2.jpg 05/30/2008
Photo Diversion Barb Construction 1.jpg 05/30/2008
Photo Diversion Barb Construction.jpg 05/30/2008
Photo Snorkler.jpg 05/30/2008
Photo milne 017.jpg 05/29/2008
Photo milne 016.jpg 05/29/2008
Photo milne 011.jpg 05/29/2008
Photo Milne Bank Barb Rock Placement.jpg 05/29/2008
Photo Milne Excavation and Sediment Plume.jpg 05/29/2008
Photo Milne Pool Excavation.jpg 05/29/2008
Photo Milne Barb Construction .jpg 05/29/2008
Photo Diversion Barb Sluice Box.jpg 05/29/2008
Photo Diversion Barb.jpg 05/29/2008
Photo Boulder Cluster #3.jpg 05/29/2008
Photo Excavator Placing Boulder Cluster #2.jpg 05/29/2008
Photo Boulder Cluster #2 in Place.jpg 05/29/2008
Photo Rock8D - RM Comtemplating?.jpg 05/29/2008
Photo Rock#8A - Completed Barb.jpg 05/29/2008
Photo Rock#7 - RM on Barb.jpg 05/29/2008
Photo Rock#6A - RM and Excavator.jpg 05/29/2008
Photo Before Bank Barbs.jpg 05/29/2008
Photo Milne Bank Barb 3.jpg 05/29/2008
Photo Milne Bank Barb 2.jpg 05/29/2008
Photo Milne Bank Barb 1.jpg 05/29/2008
Photo Milne Bank Barb.jpg 05/29/2008
Project presentation Entiat River Photos.pdf 09/30/2005
Project presentation Entiat WRIA 46 Management Plan Ch 9.pdf 09/26/2005
Project presentation Entiat WRIA 46 Management Plan Ch 7.pdf 09/26/2005

Back to top Date of last change: 02/05/2024