PRISM Project #07-1788 (Completed)
Entiat PUD Canal System Conversion Project
    Project Details    
Cascadia Conservation District; Entiat PUD Canal System Conversion Project (#07-1788)

05/01/2007, Attachment #49206, Figure 4. Unlined pond that leaks and will be decommissioned
Cascadia Conservation District; Entiat PUD Canal System Conversion Project (#07-1788) 05/01/2007, Attachment #49206, Figure 4. Unlined pond that leaks and will be decommissioned

Cascadia Conservation District; Entiat PUD Canal System Conversion Project (#07-1788)

05/01/2007, Attachment #49206, Figure 4. Unlined pond that leaks and will be decommissioned Cascadia Conservation District; Entiat PUD Canal System Conversion Project (#07-1788)

05/01/2007, Attachment #49202, Figure 2. Leakage from pipelineCascadia Conservation District; Entiat PUD Canal System Conversion Project (#07-1788)

05/01/2007, Attachment #49204, Figure 3. Pipeline leakageCascadia Conservation District; Entiat PUD Canal System Conversion Project (#07-1788)

01/06/2012, Attachment #131476, Entiat PUD Canal Site Map 01-2012
Project Status:  Closed Completed since 08/30/2012
 
Project Type:  Restoration
Project Sponsor:  Cascadia Conservation District
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $251,308
Total RCO Grant: $251,308 (57%)
Sponsor Match: $188,406 (43%)
Total Agreement: $439,713 (100%)
              Links
 

    Project Description    
Decommissioning the leaking and inefficient PUD irrigation system pipeline and delivery system and converting existing irrigation water users to wells will create water savings of 2.7 - 3.3 cfs between RM 3.45 and 1.7 (pipeline intake and outfall) and improve lower Entiat River instream flow conditions. To create improved off-channel habitat conditions year-round targeted at benefiting adult and juvenile steelhead (spring Chinook juveniles may also benefit), flows in the canal will be reduced 8-9 cfs, resulting in a savings of 8-9 cfs in the mainstem in the 0.15 mile between the canal diversion and outfall.

The Entiat PUD Canal System Conversion Project is located in the lower portion (RM 0.0- RM16.2; Category 2 subwatershed) of the Entiat River in Chelan County. The canal runs along the Entiat River in T25 R20 Sec13 and T25 R21 Sec18 in Chelan County. The canal irrigation water canal diversion and return outfall are located approximately River Mile 3.45 miles and RM 1.49 miles, respectively.

The Entiat PUD Canal System Conversion project will address water quantity and water quality issues, particularly late-season instream flows, help moderate stream temperature extremes and improve water quality in the lower Entiat, and facilitate salmonid access to spawning and rearing habitats. The water savings from this project will be enrolled in or dedicated to the Washington Water Trust program. In addition, it complements the suite of habitat improvement actions implemented instream adjacent to and within the canal last year as part of Phase 1 of the Bridge-to-Bridge project.

    Project Contacts    
         
Project Sponsor: Cascadia Conservation District Lead Entity: Upper Columbia Salmon Recovery Board Lead Entity
  Project Contact: Kurt Hosman

(509) 436-1601
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
General Area:   Lower Entitat. Entiat PUD Canal System
Waterbody:   Columbia River, Entiat River
County:   Chelan
Legislative District:   12
Congressional District 2022:   08
Salmon Recovery Regions:   Upper Columbia River
Watershed Administrative Unit:   Lower Entiat
HUC8:   Upper Columbia-Entiat (17020010)
WRIA:   Entiat
Sections:   13
Township:   T25NR20E
Coordinates:   47.66561914
-120.26732532

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Entiat PUD Canal System (#1) Architectural & Engineering (A&E), Fish screens installed (C.1.c.1), Irrigation practice improvement (C.3.e.1), Obtain permits, Restoration signs $439,713
 Total$439,713
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Entiat PUD Canal System (#1)   Property 1 - Chelan County PUD Canal Local Government
Entiat PUD Canal System (#1)   Property 2 - Douglas R. and Mary K. Grim Private
Entiat PUD Canal System (#1)   Property 3 - Bruce Grim (representing Douglas Grim) Private
Entiat PUD Canal System (#1)   Property 4 - Mike and Roxie Asher Private
Entiat PUD Canal System (#1)   Property 5 - Bill and Loretta Rust Private
Entiat PUD Canal System (#1)   Property 6 - Jack and Rowena Asher Private
Entiat PUD Canal System (#1)   Property 7 - Dale Foreman Private
Entiat PUD Canal System (#1)   Property 8 - John Groff Private
Entiat PUD Canal System (#1)   Property 9 - Brent and Dawn Milne Private
   Total
Amounts may not be complete

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/13/2007
Special Conditions Met 01/29/2008 Compliance with Executive Order 05-05 (cultural resources) was met via the Department of Archaeology & Historic Preservation letter concurring that this project is exempt.
Applied for Permits 03/15/2008
Annual Project Billing Due 07/31/2008
Annual Project Billing Due 07/31/2009
Annual Project Billing Due 07/31/2010
Annual Project Billing Due 07/31/2011
Agreement End Date 05/15/2012
Final Report Due 05/31/2012
Final Billing Due 05/31/2012


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State General Provisions 4.15.02.pdf 07/10/2013
Agreement - State Salmon Agreement.pdf 05/22/2008
Correspondence Cash Advacne 5/30/12.pdf 05/30/2012
Correspondence 09-21-11 Time Extension Request.pdf 10/12/2011
Correspondence Tech Memo TW-1 Test Pump FINAL.pdf 04/28/2010
Correspondence Entiat PUD Canal Current Schedule 08-25-08.pdf 09/09/2008
Correspondence SRFB application.pdf 09/13/2007
Design document Entiat Well Conversion_R1 100419.pdf 04/28/2010
Design document CPUD Entiat TW-2 rev2_Final Screen Design.jpg 04/28/2010
Evaluation proposal Evaluation Proposal.pdf 09/13/2007
Inspection Report Final Inspection Photos 05-22-12.pptx 06/18/2012
Landowner acknowledgement form LWFs.pdf 09/13/2007
Map PUD Canal Landowners & Wells Map.docx 02/01/2012
Map state map.pdf 09/13/2007
Map Ownership & Irrigated Acres Ortho Photo.pdf 09/13/2007
Milestones Updated milestones Dec 2009.pdf 01/05/2010
News Article News Clip 12-21-2007.pdf 02/26/2008
Notice of Long-Term Obligations Cascadia Conservation District 2014 Sponsor Notice.pdf 12/15/2014
Photo Entiat_PUD_Canal_PhaseII_Final_11_5_2015_Collaborator_Sign.jpg 12/02/2015
Photo Entiat PUD Canal Site Map 01-2012.jpg 01/11/2012
Photo Figure 4. Unlined pond that leaks and will be decommissioned.jpg 09/13/2007
Photo Figure 3. Pipeline leakage.jpg 09/13/2007
Photo Figure 2. Leakage from pipeline.jpg 09/13/2007
Project partnership form Chelan PUD Contribution Form.pdf 09/13/2007
SRFB Review Panel Comment Form Project Review Form.pdf 12/28/2007
SRFB Review Panel Comment Form Project Comment Form 7/7/07.pdf 09/13/2007
Visuals Ground Photos.pdf 09/13/2007