Below the Keystone Bridge - Riparian Planting
|
Cascadia Conservation District; Below the Keystone Bridge - Riparian Planting (#08-2186)
04/06/2011, Attachment #131194, Mike & Phylisha Caring
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The project will upgrade the existing Keystone Diversion and improve Entiat River salmon habitat diversity by replacing an instream push up dam that is reconstructed each year with a rock wing dam that directs water into a sluiceway. The rock structure will also serve as a grade control and create a large scour pool. Large woody debris will be added in the Entiat river to increase habitat diversity (pools/cover) for juvenile and adult salmonids in the form of two LWD structures comprised of five logs each and one ELJ constructed of about 30 logs. Five boulder cluster structures comprised of five four foot diameter boulders each will also be placed instream. The wing dam, LWD structures, ELJ, and boulder clusters will significantly improve habitat diversity (main limiting factor on lower Entiat River). The diversion fish screen and bypass on the diversion will be upgraded to comply with ESA standards to ensure safe juvenile salmonid passage.
Native trees and shrubs will be planted and underplanted in the riparian area (conifers, deciduous trees/livestakes, and shrubs) will be planted in the floodplain riparian area to enhance the existing riparian zone and also to establish a long-term source of LWD to the Entiat River. Enhanced riparian vegetation will also help moderate the high and low stream water temperatures that adversely affect juvenile salmonids. The project is located on the right and left banks of the Entiat River between RM 1.0 and RM 1.45.
|
General Area:
|
|
Near Keystone in Lower Entiat River
|
Waterbody:
|
|
Columbia River, Entiat River
|
County:
|
|
Chelan
|
Legislative District:
|
|
12
|
Congressional District 2022:
|
|
08
|
Salmon Recovery Regions:
|
|
Upper Columbia River
|
Watershed Administrative Unit:
|
|
Lower Entiat
|
HUC8:
|
|
Upper Columbia-Entiat (17020010)
|
WRIA:
|
|
Entiat
|
Sections:
|
|
18
|
Township:
|
|
T25NR21E
|
Coordinates:
|
|
47.66343195 -120.24536967
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Riparian Planting and Maintenance (#1)
|
Architectural & Engineering (A&E), Channel structure placement (C.4.d.1), Other restoration activities, Planting (C.5.c.1), Riparian Plant removal / control (C.5.h.1)
|
$50,122
|
| Total | $50,122 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Riparian Planting and Maintenance (#1)
|
|
Property 1 - Keystone Ranch
|
Private
|
Riparian Planting and Maintenance (#1)
|
|
Property 2 - WDFW
|
State Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Instream Habitat Project |
Channel structure placement (C.4.d.1) |
|
Miles of Stream Treated for channel structure placement (C.4.d.3)
|
0.05
|
|
Pools Created through channel structure placement (C.4.d.5)
|
6
|
|
Number of structures placed in channel (C.4.d.7)
|
10
|
Riparian Habitat Project |
Planting (C.5.c.1) |
|
Acres Planted in riparian (C.5.c.3)
|
5.5
|
Milestone Name | Target Date | Description |
Project Start
|
01/15/2009
|
|
A&E Plans Submitted
|
02/01/2009
|
|
Applied for Permits
|
02/15/2009
|
|
RFP Complete
|
05/01/2009
|
|
Monitor/Steward Plan Submitted
|
05/15/2009
|
|
Bid Awarded/Consultant Hired
|
06/01/2009
|
|
Cultural Resources Complete
|
07/01/2009
|
Compliance with EO 05-05 must be met prior to commencing construction
|
Construction Started
|
07/01/2009
|
may begin in 2010 depending on landowner MOU and permit windows
|
Progress Report Due
|
07/31/2009
|
|
Annual Project Billing Due
|
07/31/2009
|
Due to the delay in setting up this contract, the sponsor may need more time to submit their annual billing
|
Annual Project Billing Due
|
07/31/2010
|
|
Annual Project Billing Due
|
07/31/2011
|
|
Construction Complete
|
12/31/2011
|
planting maintenance complete
|
Agreement End Date
|
01/31/2012
|
|
Final Docs/Billing to Mgmt Agy
|
03/31/2012
|
|