Project Snapshot
PRISM Project #09-1390 (Completed)
Lower Quinault Major Tributaries Knotweed Control
    Project Details    
Project Status:  Closed Completed since 03/27/2014
 
Project Type:  Restoration
Project Sponsor:  Quinault Indian Nation
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $287,808
Total RCO Grant: $287,808 (85%)
Sponsor Match: $51,000 (15%)
Total Agreement: $338,808 (100%)
              Links
 

    Project Description    
Lower Quinault Major Tributaries Knotweed Control

Riparian habitat is crucial to the life cycle of salmon species resident in the Quinault Watershed. Invasive plants, such as knotweed, alter and damage that habitat and if not controlled have severe impacts on salmon. The goal of this project is to remove knotweed in the watersheds of the major tributaries of the lower Quinault as part of an ongoing strategy to rid the whole watershed of this invasive plant. This project targets approximately 68,635 acres covering 9 sub-watersheds. This 3 year project is expected to remove knotweed from these areas streams (321 miles) and roads (195 miles) in these tributaries. The community of the reservation is involved through the Land and Natural Resource Committee of the QIN. This is the second phase, Prairie Creek sub-watershed is currently receiving its 3rd year of successful treatment. After these tributaries are treated the Quinault main stem and floodplains will follow. The QIN has been coordinating efforts with Grays Harbor County, Olympic National Park and the USFS to treat the lands in the entire Quinault Watershed.

    Project Contacts    
         
Project Sponsor: Quinault Indian Nation Lead Entity: Quinault Indian Nation Lead Entity
  Project Contact: Jim Plampin
jplampin@quinault.org
(360) 580-0601 Ext 7290
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Teresa Miskovic
teresa.miskovic@rco.wa.gov
(360) 622-1659
   

    Project Location    
General Area:   tributaries to the Quinault River downstream of Lake Quinault
Waterbody:   , Quinault River
County:   Grays Harbor
Legislative District:   24
Congressional District 2022:   06
Salmon Recovery Regions:   Washington Coast
Watershed Administrative Unit:   Lower Quinault River
HUC8:   Queets-Quinault (17100102)
WRIA:   Queets - Quinault
Sections:   25
Township:   T23NR10W
Coordinates:   47.45692527
-123.89153969

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Lower Quinault major tributaries (#1) Architectural & Engineering (A&E), Implementation monitoring, Obtain permits, Plant removal/control (C.4.g.1), Planting (C.5.c.1), Riparian Plant removal / control (C.5.h.1) $350,320
 Total$350,320
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Lower Quinault major tributaries (#1)   Property 1 - Lower Quinault major tributaries Tribal Government
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

Instream Habitat Project
      Plant removal/control (C.4.g.1)
Miles of Stream Treated for plant removal/control (C.4.g.3) 42.00

Riparian Habitat Project
      Planting (C.5.c.1)
Acres Planted in riparian (C.5.c.3) 1.0
      Riparian Plant removal / control (C.5.h.1)
Acres of riparian treated for plant removal/control (C.5.h.3) 92.4

Permits
      Obtain permits
Number of permits required for implementation of project 4

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/10/2009 begin planning and RFP preparation
RFP Complete 05/31/2010 RFP and bid packets in mail for survey treat summer 2010
Applied for Permits 06/30/2010 QIN FPA/HPA and state NPDES permit applications completed and turned in
Progress Report Due 06/30/2010
Cultural Resources Complete 06/30/2010 N/A no ground disturbance - only herbicide application
Bid Awarded/Consultant Hired 07/01/2010 Contractor selected and contracts signed
Construction Started 07/15/2010 Field work begins by now. Survey and treat lower Quinault Tribs.
Annual Project Billing Due 07/31/2010
Progress Report Due 12/30/2010 Season one - year end reporting - results
Progress Report Due 06/30/2011
Annual Project Billing Due 07/31/2011
Progress Report Due 11/30/2011 Season two - year end reporting - results
Progress Report Due 06/30/2012
Annual Project Billing Due 07/31/2012
Progress Report Due 12/31/2012 Season three - year end reporting - results
Progress Report Due 06/30/2013
Annual Project Billing Due 07/31/2013
Construction Complete 10/31/2013 Finish fourth year of treatment
Agreement End Date 12/31/2013
Monitoring Complete 12/31/2013
Progress Report Due 12/31/2013 Season four - year end reporting - results
Final Docs/Billing to Mgmt Agy 03/31/2014
Final Report Due 03/31/2014


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State Agreement 3-25-10.pdf 04/15/2010
Application Document Resolution 2-23-10.pdf 10/10/2014
Final project report Final Report 03/27/2014.pdf 03/27/2014
Inspection Report Inspection Report, #143 (Submitted 03/27/14 13:19:39).pdf 03/27/2014
Map SRFB 09-1390 Final Map.jpg 11/20/2013
Map 09grantKnotlocHUCaddstreamsMPrism.pdf 08/07/2009
Map Knotweed Tributaries Watershed Map.pdf 06/01/2009
Map: Restoration Worksite 09-1390 F15 boat launch spruce planting.jpg 04/02/2014
Permit Rayonier Agreement 2010 - Special Use Permit 6-21-10.pdf 12/09/2010
Photo Recovery and knotweed.jpg 03/25/2014
Photo South Boulder Cr after.jpg 03/25/2014
Photo Neilton before.jpg 03/25/2014
Photo Neilton before (3).jpg 03/25/2014
Photo Neilton before (2).jpg 03/25/2014
Photo Neilton after treatment2.jpg 03/25/2014
Photo Neilton after treatment.jpg 03/25/2014
Photo Lower Quinault Trib before.jpg 03/25/2014
Photo Lower Quinault Trib after3.jpg 03/25/2014
Photo Lower Quinault trib after2.jpg 03/25/2014
Photo Lower Quinault Trib after treatment.jpg 03/25/2014
Progress report Progress Report 11/27/2013.pdf 11/27/2013
Progress report Progress Report 11/27/2013.pdf 11/27/2013
Progress report Progress Report 12/21/2012.pdf 12/21/2012
Progress report Progress Report 06/13/2012.pdf 06/13/2012
Progress report Progress Report 12/22/2011.pdf 12/22/2011
Progress report Progress Report 06/17/2011.pdf 06/17/2011
Progress report Progress Report SRFB Combined Quarterly 060110.doc 07/23/2010
Scope of work LowerQINtributary Budget.pdf 08/17/2009
Scope of work SRFB2009 grantApplication.pdf 08/17/2009
SRFB Review Panel Comment Form Post Application Individual Project Comments 10-30-09.pdf 12/11/2009
SRFB Review Panel Comment Form Response to SRFBtechreview 7-29-09.pdf 08/06/2009

Back to top Date of last change: 07/30/2024