PRISM Project #09-1656 (Completed)
Entiat National Fish Hatchery Floodplain Connectio
    Project Details    
Cascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

03/30/2012, Attachment #148774, Levee Removal Restoration
Cascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656) 03/30/2012, Attachment #148774, Levee Removal Restoration

Cascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

03/30/2012, Attachment #148774, Levee Removal Restoration Cascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

04/06/2011, Attachment #117470, Levee Removal Area with LWD PlacementCascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

04/06/2011, Attachment #117473, LWD Placement on Levee Removal AreaCascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

04/06/2011, Attachment #117476, Floodplain Reconnection AreaCascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)
, Progress Report: 11/21/2011
09/13/2011, Attachment #129438, ENFH Fall 2011 planting 1Cascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)
, Progress Report: 11/21/2011
09/16/2011, Attachment #129439, ENFH Fall 2011 planting 2Cascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

03/30/2012, Attachment #148771, Trout Pond on Floodplain TerraceCascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

03/30/2012, Attachment #148772, Levee Removal AreaCascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

03/30/2012, Attachment #148773, Pine Tree Planting with MulchCascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

03/30/2012, Attachment #148775, Closeup of Pine PlantingCascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

03/30/2012, Attachment #148776, Wetland Creation & Floodplain RevegetationCascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

03/30/2012, Attachment #148777, Floodplain/Riparian RevegetationCascadia Conservation District; Entiat National Fish Hatchery Floodplain Connectio (#09-1656)

03/30/2012, Attachment #148778, River Trail Sign
Project Status:  Closed Completed since 07/09/2012
 
Project Type:  Restoration
Project Sponsor:  Cascadia Conservation District
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $87,673
Total RCO Grant: $87,673 (84%)
Sponsor Match: $16,950 (16%)
Total Agreement: $104,623 (100%)
              Links
 

    Project Description    
This project is located on the mainstem Entiat River at approximately RM 6.8 to 7.1. Following European settlement, human activities have greatly altered the lower Entiat River, though only qualitative or anecdotal information exists with which to compare present-day conditions. Localized channelization, removal of riparian vegetation, floodplain development, and dam building have perhaps been the most impactful anthropogenic activities in this reach. This project affords a rare opportunity to address these issues over a significant length of river by attempting to return those missing elements of river function. A levee on the upstream portion of the property has disconnected the river from its right-bank floodplain, while large wood and natural, off-channel habitat are all but missing from the lower river. This project aims to reactivate the Entiat National Fish Hatchery (ENFH) floodplain (or at least promote a trajectory for improvement in the future) by removing much of this levee. Future project phases will increase the amount of off-channel habitat and construct multiple LWD jams to further reactivate the ENFH floodplain. It is important to demonstrate the need and benefits of reach-scale, ecological process-driven restoration to Entiat landowners who have generally not embraced levee removal or LWD as a desirable technique for salmon recovery. In doing so, we hope to show the compatibility of floodplain infrastructure with floodplain restoration.

    Project Contacts    
         
Project Sponsor: Cascadia Conservation District Lead Entity: Upper Columbia Salmon Recovery Board Lead Entity
  Project Contact: Kurt Hosman

(509) 436-1601
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
General Area:   Appx. 6 miles west of Entiat, WA.
Waterbody:   Columbia River, Entiat River
County:   Chelan
Legislative District:   12
Congressional District 2022:   08
Salmon Recovery Regions:   Upper Columbia River
Watershed Administrative Unit:   Lower Entiat
HUC8:   Upper Columbia-Entiat (17020010)
WRIA:   Entiat
Sections:   03
Township:   T25NR20E
Coordinates:   47.70062580
-120.32042111

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Entiat National Fish Hatchery floodplain (#1) Architectural & Engineering (A&E), Channel reconfiguration and connectivity (C.4.c.1), Cultural resources, Obtain permits, Other restoration activities, Planting (C.5.c.1), Streambank stabilization (C.4.e.1) $107,767
 Total$107,767
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Entiat National Fish Hatchery floodplain (#1)   Property 1 - Entiat National Fish Hatchery Federal Government
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

Instream Habitat Project
      Channel reconfiguration and connectivity (C.4.c.1)
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3) 0.20

Riparian Habitat Project
      Planting (C.5.c.1)
Acres Planted in riparian (C.5.c.3) 3.7

Permits
      Obtain permits
Number of permits required for implementation of project 2

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/10/2009
Applied for Permits 01/31/2010
Cultural Resources Complete 04/30/2010 USFWS will complete - project takes place on Federal Property
Progress Report Due 06/30/2010
Annual Project Billing Due 07/31/2010
Progress Report Due 12/01/2010
Progress Report Due 06/30/2011
Annual Project Billing Due 07/31/2011
Progress Report Due 12/01/2011
Progress Report Due 06/30/2012
Annual Project Billing Due 07/31/2012
Agreement End Date 09/30/2012
Final Billing Due 12/31/2012
Final Report Due 12/31/2012
Landowner Agreement to RCO 12/31/2012


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State Agreement.pdf 04/21/2010
Certification of Applicant Match ENFH_SRFB-TRIB_fund_mod_11_03_09.pdf 11/05/2009
Correspondence Post Application Individual Project Comments.pdf 12/11/2009
Correspondence ENFH Final_Proposal_Ammendment_10_23_09.pdf 11/03/2009
Design document Design Drawings 4-2-2010.pdf 04/15/2010
Design document 1D flood map showing 100-year flood extent, current cond's.pdf 11/06/2009
Final project report Final Report 07/09/2012.pdf 07/09/2012
Inspection Report 03-30-12 Final Inspection Photos.pptx 05/03/2012
Inspection Report 04-06-11 Interim Inspection.pptx 05/11/2011
Map ENFH expanded planting 05-2011.pdf 06/01/2011
Notice of Long-Term Obligations Cascadia Conservation District 2014 Sponsor Notice.pdf 12/15/2014
Photo River Trail Sign.jpg 07/30/2012
Photo Floodplain/Riparian Revegetation.jpg 07/30/2012
Photo Wetland Creation & Floodplain Revegetation.jpg 07/30/2012
Photo Closeup of Pine Planting.jpg 07/30/2012
Photo Levee Removal Restoration.jpg 07/30/2012
Photo Pine Tree Planting with Mulch.jpg 07/30/2012
Photo Levee Removal Area.jpg 07/30/2012
Photo Trout Pond on Floodplain Terrace.jpg 07/30/2012
Photo ENFH Fall 2011 planting 2.jpg 11/21/2011
Photo ENFH Fall 2011 planting 1.jpg 11/21/2011
Photo Floodplain Reconnection Area.jpg 05/11/2011
Photo LWD Placement on Levee Removal Area.jpg 05/11/2011
Photo Levee Removal Area with LWD Placement.jpg 05/11/2011
Progress report Progress Report 06/18/2012.pdf 06/18/2012
Progress report Progress Report 11/30/2011.pdf 11/30/2011
Progress report Progress Report 08/01/2011.pdf 08/01/2011
Scope of work ENFH_final_SRFB_proposal.pdf 09/21/2009
Scope of work SRFB-TRIB PreProposal_2009.pdf 06/16/2009
Sponsor final report Final Report for HCP Trib. Comm 06-2012.pdf 07/03/2012
Visuals Levee historic photos.pdf 05/05/2010