Cornet Bay Shoreline Areas 4, 6, and 7 Restoration
|
    Funding |
  |
|
    Links |
  |
|
|
The project area is the shoreline area beginning about 320 feet southwest from the Marine Maintenance Facility Dock stretching to about 50 feet north of the boat launch at Cornet Bay in Deception Pass State Park. The total linear feet of beach treated is 820. The project activities include removing the creosote wood bulkhead and associated fill and restoring the beach’s natural grade and composition. The south side of the entrance of the boat launch will require replacement of the existing bulkhead with shorter concrete bulkhead to address infrastructure protection. The rest of the project area will be restored to a natural beach profile, with riparian planting and strategic placement of large woody debris to increase habitat value. Please see the project map and photos attached to the project record in PRISM. This project will expand upper beach habitat, remove creosote contamination, as well as improve forage fish and salmon habitat.
Engineering will be completed by Whidbey Island Conservation District staff. Permitting is already underway with the assistance of State Parks staff and staff from the U.S. Fish and Wildlife Service.
Please see the attached project description for a more detailed project description.
|
General Area:
|
|
Deception Pass State Park, Whidbey Island
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Whidbey Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Island
|
Coordinates:
|
|
48.39750836 -122.63510016
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Cornet Bay Shoreline Areas 4, 6, 7 (#1)
|
Architectural & Engineering (A&E), Beach nourishment (C.9.l.1), Implementation monitoring, Obtain permits, Planting (C.5.c.1), Regrading of slope (C.9.i.1), Removal of existing fill material (C.9.g.1), Shoreline armor removal or modification (C.9.k.1)
|
$349,247
|
| Total | $349,247 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Cornet Bay Shoreline Areas 4, 6, 7 (#1)
|
|
Property 1 - Deception Pass State Park
|
State Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Riparian Habitat Project |
Planting (C.5.c.1) |
|
Acres Planted in riparian (C.5.c.3)
|
0.6
|
Estuarine / Nearshore Project |
Removal of existing fill material (C.9.g.1) |
|
Acres of Estuary Treated through fill material removal (C.9.g.2)
|
0.6
|
Regrading of slope (C.9.i.1) |
|
Acres of Estuary Treated through slope regrading (C.9.i.2)
|
1.2
|
Shoreline armor removal or modification (C.9.k.1) |
|
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
|
0.16
|
|
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
|
1.2
|
Beach nourishment (C.9.l.1) |
|
Cubic Yards Of Beach Substrate Placed (C.9.l.2)
|
890
|
|
Miles of Shoreline Treated for beach nourishment (C.9.l.3)
|
0.16
|
|
Acres Treated for beach nourishment (C.9.l.4)
|
0.6
|
Permits |
Obtain permits |
|
Number of permits required for implementation of project
|
6
|
Milestone Name | Target Date | Description |
Cultural Resources Complete
|
06/01/2010
|
On-going, anticipate completion April 30,2011
|
Applied for Permits
|
09/10/2010
|
On-going, anticipate completion April 30,2011
|
Project Start
|
12/01/2010
|
|
Progress Report Due
|
01/01/2011
|
|
RFP Complete
|
03/01/2011
|
Tentative RFP for construction
|
Monitor/Steward Plan Submitted
|
05/15/2011
|
|
A&E Plans Submitted
|
06/01/2011
|
|
Progress Report Due
|
06/01/2011
|
|
Bid Awarded/Consultant Hired
|
06/30/2011
|
|
Annual Project Billing Due
|
07/31/2011
|
|
Progress Report Due
|
08/31/2012
|
|
Construction Started
|
09/30/2012
|
Construction begins after the 2012 fish window opens
|
Construction Complete
|
11/30/2012
|
Major construction completed. Planting to be completed by 4/27/2013.
|
Progress Report Due
|
01/31/2013
|
|
Special Conditions Met
|
12/31/2013
|
Conditions from Review Panel
|
Agreement End Date
|
12/31/2013
|
|
Monitoring Complete
|
12/31/2013
|
|
Final Docs/Billing to Mgmt Agy
|
03/31/2014
|
|