Gorst Creek Habitat Enhancement
|
Mid-Puget Sound Fish Enh Grp; Gorst Creek Habitat Enhancement (#11-1470)
Attachment #117514, Gorst Pictures 2
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The Gorst Creek project is a restoration project that will have a direct benefit to Steelhead, Chinook and Coho salmon. Due to channelization, road encroachment and fragmentation of the riparian corridor, Gorst has lost a lot of its quality spawning habitat. This grant will finish the project permitting submission, make any necessary edits to designs and construct a project that will restore riparian and in-stream habitat of 1200 linear feet of creek. The project is at lat/long 47.528082/-122.707479 and just downstream of Jarstad Park on W. Belfair Valley Road. Both spawning and rearing habitat will be created, and current spawning habitat will be protected. There is little rearing habitat, but what is present will be protected. The project will as designed includes bioengineered bank stabilization and LWD installation, riparian plantings to compliment the already existing site conditions, and sloping back banks where possible to initiate re-connection with the already existing floodplain. Root wads will be strategically placed to protect high erosion areas and create fish rearing habitat and places of refuge. Root wads and other LWD will also be used to create much needed stream complexities by producing points of decreased water velocity and creating pools and eddies (see uploaded design document). This project is on the lead entity 3 Year Work Plan implementation list and has had SRFB review.
|
General Area:
|
|
Kitsap County just South of Gorst, Washington
|
County:
|
|
Kitsap
|
Legislative District:
|
|
26
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
S Sinclair Inlet
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kitsap
|
Sections:
|
|
32
|
Township:
|
|
T24NR01E
|
Coordinates:
|
|
47.52738591 -122.70612685
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Dalton (#1)
|
Architectural & Engineering (A&E), Channel structure placement (C.4.d.1), Implementation monitoring, Obtain permits, Planting (C.5.c.1), Streambank stabilization (C.4.e.1)
|
$98,002
|
| Total | $98,002 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Dalton (#1)
|
|
Property 1 - Dalton
|
Private
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Instream Habitat Project |
Channel structure placement (C.4.d.1) |
|
Miles of Stream Treated for channel structure placement (C.4.d.3)
|
0.12
|
|
Acres Of Streambed Treated for channel structure placement (C.4.d.4)
|
0.2
|
|
Pools Created through channel structure placement (C.4.d.5)
|
6
|
|
Number of structures placed in channel (C.4.d.7)
|
35
|
Streambank stabilization (C.4.e.1) |
|
Miles of Streambank Stabilized (C.4.e.3)
|
0.23
|
Riparian Habitat Project |
Planting (C.5.c.1) |
|
Acres Planted in riparian (C.5.c.3)
|
0.2
|
Permits |
Obtain permits |
|
Number of permits required for implementation of project
|
3
|
Milestone Name | Target Date | Description |
Project Start
|
12/08/2011
|
|
Landowner Agreement to RCO
|
02/29/2012
|
Attachment 15.
|
Progress Report Due
|
05/31/2012
|
|
Applied for Permits
|
06/15/2012
|
|
Annual Project Billing Due
|
12/07/2012
|
|
Permits Complete
|
12/31/2012
|
|
Progress Report Due
|
12/31/2012
|
|
Cultural Resources Complete
|
03/01/2013
|
USACOE permit attached in PRISM
|
Progress Report Due
|
05/15/2013
|
|
Final Design to RCO
|
06/15/2013
|
Final Stamped Design needs to be to RCO prior to construction
|
Bid Awarded/Contractor Hired
|
06/30/2013
|
|
Annual Project Billing Due
|
07/31/2013
|
|
Restoration Started
|
08/15/2013
|
|
Progress Report Due
|
12/31/2013
|
|
Restoration Complete
|
05/15/2015
|
|
RCO Final Inspection
|
05/31/2015
|
|
Special Conditions Met
|
06/15/2015
|
As-Builts showing any changes that occured during construction
|
Agreement End Date
|
06/15/2015
|
|
Final Report Due
|
07/15/2015
|
|
Final Billing Due
|
07/15/2015
|
|