PRISM Project #11-1505 (Completed)
Powel Shoreline Restoration Implementation
    Project Details    
Project Status:  Closed Completed since 10/28/2015
 
Project Type:  Restoration
Project Sponsor:  Bainbridge Island Land Trust
Funding Board:  Salmon Recovery Funding Board
              Funding  
Puget Sound Acq. & Restoration: $293,910
Total RCO Grant: $293,910 (85%)
Sponsor Match: $51,850 (15%)
Total Agreement: $345,760 (100%)
              Links
 

    Project Description    
The Powel Shoreline Restoration Implementation Project will restore over 1544 lineal feet of privately owned shoreline in Port Madison, Bainbridge Island by removing shoreline armoring. The project will result in increases in various habitats on the property, including an overall increase of 163 percent in current intertidal habitat area, almost tripling the amount of salt marsh habitat over time, and enhancing 32,795 square feet of marine riparian habitat. This project addresses lost salt marsh, intertidal habitats, and marine riparian habitat typically associated with armoring and focuses on recreating shallow intertidal habitat important to juvenile salmonids, particularly ESA-listed Chinook, for migration, feeding, refuge and physiological transition. The nearshore environment associated with this property is home to documented juvenile salmon and forage fish, as identified in Westsound Watersheds Council’s 3 Year Salmon Recovery Plan Implementation List. This is a showcase project to other private shoreline landowners to increase awareness of the importance and option of restoring nearshore habitats in Puget Sound. This project is Phase II of a two phased project and implements Phase I, the Powel Shoreline Restoration Design Project, SRFB project #09-1961N, which resulted in a final design approved by the landowner, and other stakeholders (WDFW, Suquamish Tribe, City of BI, USACE). Phase II has not been previously funded by SRFB but builds off of and continues the work done in Phase I.

    Project Contacts    
         
Project Sponsor: Bainbridge Island Land Trust Lead Entity: West Sound Partners for Ecosystem Recovery
  Project Contact: Brenda Padgham
brenda@bi-landtrust.org
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
General Area:   Port Madison on Bainbridge Island, Kitsap County
County:   Kitsap
Legislative District:   23
Congressional District 2022:   06
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Bainbridge Island
HUC8:   Puget Sound (17110019)
WRIA:   Kitsap
Sections:   34
Township:   T26NR02E
Coordinates:   47.70083896
-122.53175476

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Powel Property (#1) Architectural & Engineering (A&E), Cultural resources, Debris removal (C.9.n.1), Fish screens installed (C.1.c.1), Implementation monitoring, Obtain permits, Planting (C.5.c.1), Removal of existing fill material (C.9.g.1), Restoration signs, Restored land maintained (C.11.c.1), Riparian Plant removal / control (C.5.h.1), Shoreline armor removal or modification (C.9.k.1), Utility relocation / reconnection $349,964
 Total$349,964
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Powel Property (#1)   Property 1 - Powel Private
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

Fish Screening Project
      Fish screens installed (C.1.c.1)
Number Of Fish Screens Installed (C.1.c.2) 1
The Flow Rate Of Screened Water (C.1.c.3) 300.00

Riparian Habitat Project
      Planting (C.5.c.1)
Acres Planted in riparian (C.5.c.3) 0.9
      Riparian Plant removal / control (C.5.h.1)
Acres of riparian treated for plant removal/control (C.5.h.3) 0.9

Estuarine / Nearshore Project
      Removal of existing fill material (C.9.g.1)
Acres of Estuary Treated through fill material removal (C.9.g.2) 0.5
      Shoreline armor removal or modification (C.9.k.1)
Miles of Shoreline Treated for armor modification/removal (C.9.k.2) 0.29
Acres of Shoreline Treated for armor modification/removal (C.9.k.3) 0.2
      Debris removal (C.9.n.1)
Acres Treated for debris removal (C.9.n.2) 0.2

Site Stewardship Project
      Restored land maintained (C.11.c.1)
Acres of restored land maintained (C.11.c.2) 1.9

Permits
      Obtain permits
Number of permits required for implementation of project 3

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/08/2011
Applied for Permits 02/10/2012
Final Design to RCO 06/11/2012 Must have final design attached in PRISM before construction activities begin (attachment #18)
Annual Project Billing Due 07/31/2012
Cultural Resources Complete 08/03/2012 Cultural Resources Survey Completed 2011. Attach any documents related to cultural resources in PRISM
Permits Complete 08/03/2012
Bid Awarded/Contractor Hired 08/10/2012
Landowner Agreement to RCO 08/27/2012
Restoration Started 08/27/2012
Progress Report Due 09/30/2012
Restoration Complete 12/01/2012 Armor Removal ended 9/19/12 and reveg planting ended 12/31/12
Progress Report Due 12/15/2012
Progress Report Due 06/30/2013
Annual Project Billing Due 07/31/2013
Progress Report Due 12/15/2013
Progress Report Due 06/30/2014
Annual Project Billing Due 07/31/2014
Progress Report Due 12/15/2014
Stewardship Plan to RCO 03/06/2015 In landowner agreement
RCO Final Inspection 05/30/2015
Final Report Due 05/30/2015
Agreement End Date 06/30/2015
Final Billing Due 09/30/2015


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State Agreement.pdf 03/30/2012
Amendment - State 11-1505 Amend #2 A&E-Admin Limit Change.pdf 06/29/2015
Correspondence Bainbridge Nearshore_EffectiveAction_FactSheet_Dec2015.pdf 07/19/2017
Correspondence Bainbridge Nearshore_Effective Action_Background Narrative_J.pdf 07/19/2017
Cost Estimate powel_update_Budget_PRISM.xls 08/26/2011
Design document Final_Engineering_Design_Oct4_FINALpdf.pdf 02/14/2012
Design document Powel_Shoreline_Final_Report_and_Design_Document_.pdf 08/26/2011
Design document Appendix 5 - Final engineering drawing sheet set.pdf 05/11/2011
Design document Powel_Vegetation_Restoration_Plan.pdf 05/09/2011
Design document (as built) Powel Vegitation Monitoring Report Final.pdf 10/28/2015
Design document (as built) As build engineering report.pdf 11/20/2013
Final project report Final Report 10/28/2015.pdf 10/28/2015
Final project report Final Report Pictorial Correct Version.pdf 10/28/2015
Final project report Final Report Narrative - same as PRIMS but with formatting.docx 10/23/2015
Final project report Final Report Supplemental Materials.pdf 10/23/2015
Inspection Photos 11-0505 Powell Compliance Site Visit.pptx.pptx 02/13/2023
Inspection Report Inspection Report, #3461 (Accepted 02/13/23 21:28:31).pdf 02/13/2023
Inspection Report Inspection Report, #1126 (Submitted 07/14/17 10:42:03).pdf 07/14/2017
Map Powel_Parcels.pdf 05/09/2011
Map Powel_Proximity_Map.pdf 05/09/2011
News Article Sea Grant Sea Star Newsletter Summer 2013.pdf 01/17/2014
Photo Beach gravels and shoreline vegetation.JPG.jpg 02/13/2023
Photo armored v unarmored beach.JPG.jpg 02/13/2023
Photo shoreline vegetation.JPG.jpg 02/13/2023
Photo Fish Screen.jpg 11/20/2013
Photo Fish Screen Installation 1_9_2013.jpg 11/20/2013
Photo Sea Grant and BeachWatcher Monitors.jpg 11/20/2013
Photo Sample amror at Powel.jpg 08/27/2011
Progress report Progress Report 01/21/2015.pdf 01/21/2015
Progress report PrePostPhotoDoc12_2014.pdf 12/15/2014
Progress report Progress Report 07/03/2014.pdf 07/03/2014
Progress report Progress Report 01/24/2014.pdf 01/24/2014
Progress report Progress Report 11/20/2013.pdf 11/20/2013
Progress report Progress Report 01/10/2013.pdf 01/10/2013
Progress report Powel Shoreline Restoration Implementation ProjectReport1_9_.pdf 01/09/2013
Progress report Progress Report 09/14/2012.pdf 09/14/2012
Progress report Progress report - PRISM.docx 09/14/2012
Project presentation Powel Project Poster.pdf 11/20/2013
Project Support / Concern Documents Land Trust Camp Proposal.pdf 01/17/2014
Project Support / Concern Documents Photos of Existing Shoreline Conditions on the Powel Propert.pdf 08/26/2011
Salmon Project Proposal Project Proposal.doc 08/27/2011
Salmon Project Proposal response_to_srfb_review_panel_powel.pdf 06/29/2011
SRFB Review Panel Comment Form Final Comment Form.doc 12/21/2011
Stewardship plan Powel 2013 Annual Veg report - stewardship plan material.pdf 06/23/2014
Visuals Powel Shoreline Restoration Project Brochure.pdf 01/17/2014
Visuals One Year Anniversary _Powelinvite.pdf 12/16/2013
Visuals 1303_BILT_Powel VIP invite_final.pdf 12/16/2013
Visuals Powel Shoreline Restoration Aug 2012.pptx 10/16/2012
Visuals Fish present at project site.doc 08/26/2011

Back to top Date of last change: 10/04/2023