Milestone Name | Target Date | Description |
Acquisition Closing
|
11/30/2012
|
Parcel 1 (Lindner), 2 (Bicknell), and 7 (Burgess Parcels) - Waiver 12-1535
|
Project Start
|
07/01/2013
|
|
Recorded Acq Documents to RCO
|
12/19/2013
|
Parcel 1 (Lindner), 2 (Bicknell), and 7 (Burgess Parcels) - Waiver 12-1535
|
Order Appraisal(s)
|
01/31/2014
|
Parcels 3, A-1
|
Order Appraisal Review(s)
|
02/15/2014
|
3, A-1
|
Order Appraisal(s)
|
03/31/2014
|
Parcels 4, 6, 7, A2, A3, A4, A5, A6
|
Order Appraisal Review(s)
|
04/15/2014
|
Parcel 4,6, 7, A2, A3, A4, A5, A6
|
Purchase Agreement Signed
|
05/31/2014
|
Parcels 3, A1
|
Order Appraisal(s)
|
05/31/2014
|
Parcels 5-7
|
Order Appraisal(s)
|
05/31/2014
|
Parcel 5
|
Order Appraisal Review(s)
|
06/15/2014
|
Parcel 5
|
Environmental Audit Complete
|
06/15/2014
|
Parcel 3, A1 - The entire Fort Casey area has been declared a "superfund site". Currently working EPA to determine the true boundaries of designation.
|
Progress Report Due
|
06/30/2014
|
|
Order Appraisal Review(s)
|
06/30/2014
|
Parcels 5-7
|
Purchase Agreement Signed
|
06/30/2014
|
|
Cultural Resources Complete
|
10/15/2014
|
All applicable parcels with planned ground disturbance
|
Environmental Audit Complete
|
05/31/2015
|
Parcels 4, 6, 7, A2, A3, A4, A5, A6
|
Progress Report Due
|
06/01/2015
|
|
Annual Project Billing Due
|
07/31/2015
|
Bill #1 for Lindner and Bicknell land costs, incidentals and admin reviewed and accepted. Also - SPU incidentals and admin
|
Environmental Audit Complete
|
07/31/2015
|
Parcel 5
|
Acquisition Closing
|
09/30/2015
|
Parcel 3, A1
|
Recorded Acq Documents to RCO
|
09/30/2015
|
Parcels 3, A1
|
Progress Report Due
|
12/31/2015
|
|
Purchase Agreement Signed
|
04/30/2016
|
Parcel 5
|
Progress Report Due
|
12/31/2016
|
|
Acquisition Closing
|
01/31/2017
|
Parcels 4, 6, 7, A2, A3, A4, A5, A6
|
Acquisition Closing
|
01/31/2017
|
Parcel 5
|
Stewardship Plan to RCO
|
03/01/2017
|
All applicable parcels
|
Recorded Acq Documents to RCO
|
03/31/2017
|
Parcels 4, 6, 7, A2, A3, A4, A5, A6
|
Recorded Acq Documents to RCO
|
03/31/2017
|
Parcel 5
|
Fencing Complete
|
06/15/2017
|
All applicable parcels
|
Progress Report Due
|
06/30/2017
|
|
Recorded Land Survey to RCO
|
11/30/2017
|
All applicable parcels
|
Noxious Weed Control Complete
|
11/30/2017
|
|
Funding Acknowl Sign Posted
|
11/30/2017
|
|
RCO Final Inspection
|
12/15/2017
|
|
Final Report Due
|
12/31/2017
|
|
Agreement End Date
|
12/31/2017
|
Per RCFB Approved Resolution 2017-01
|
Final Billing Due
|
12/31/2017
|
|