Phase II Entiat PUD Canal Conversion
|
Cascadia Conservation District; Phase II Entiat PUD Canal Conversion (#12-1646)
05/22/2012, Attachment #151970, PUD Canal Diversion
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
Chelan County PUD owns and operates a surface water irrigation system which delivers water to seven landowners through a pipeline and open channel system (circa 1909) located between Entiat River Miles (RM) 1.49 and 3.45. The system diverts 4.52 cfs in the mainstream Entiat River, while actual water need has been established at 2.24 cfs. Additionally, 8-9 cfs savings will be realized along the 0.15 mile long diversion structure. Objectives of this project are to decommission the PUD irrigation pipeline and delivery system, upgrade to modern and efficient delivery systems located closer to the point of use (creating water savings), improve lower Entiat River instream flow conditions, enhance off-channel habitat conditions, and prevent juvenile fish entrainment. The project addresses water quantity and water quality issues, particularly late-season instream flows; helps to moderate stream temperature extremes and improves water quality in the lower Entiat; and facilitates salmon access to spawning and rearing habitats. Water savings from this project will be enrolled in or dedicated to the Washington Water Trust program. This is the continuation of a SRFB project number 07-1788 that began in 2008. The original project assumption was that drilled irrigation wells, one for each property owner, would achieve the project goals. Wells have been drilled, and only three of the seven properties will have their irrigation water needs met by wells.
|
General Area:
|
|
Lower Entiat, near Kwanzut hut
|
County:
|
|
Chelan
|
Legislative District:
|
|
12
|
Congressional District 2022:
|
|
08
|
Salmon Recovery Regions:
|
|
Upper Columbia River
|
Watershed Administrative Unit:
|
|
Lower Entiat
|
HUC8:
|
|
Upper Columbia-Entiat (17020010)
|
WRIA:
|
|
Entiat
|
Sections:
|
|
13
|
Township:
|
|
T25NR20E
|
Coordinates:
|
|
47.66763852 -120.28164963
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Entiat PUD Canal (#1)
|
Architectural & Engineering (A&E), Irrigation practice improvement (C.3.e.1), Utility relocation / reconnection
|
$291,663
|
| Total | $291,663 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Entiat PUD Canal (#1)
|
|
Property 1 - Chelan County PUD Canal
|
Local Government
|
Entiat PUD Canal (#1)
|
|
Property 2 - Douglas R. and Mary K. Grim
|
Private
|
Entiat PUD Canal (#1)
|
|
Property 3 - McMahon
|
Private
|
Entiat PUD Canal (#1)
|
|
Property 4 - Dale Foreman
|
Private
|
Entiat PUD Canal (#1)
|
|
Property 5 - Klineman
|
Private
|
Entiat PUD Canal (#1)
|
|
Property 6 - Brent and Dawn Milne
|
Private
|
Entiat PUD Canal (#1)
|
|
Property 7 - Mike and Roxie Asher
|
Private
|
Entiat PUD Canal (#1)
|
|
Property 8 - Bill and Loretta Rust
|
Private
|
Entiat PUD Canal (#1)
|
|
Property 9 - Jack and Rowena Asher
|
Private
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Instream Flow Project |
Irrigation practice improvement (C.3.e.1) |
|
Acre Feet Of Water Conserved (C.3.e.2)
|
478
|
|
Cfs (Cubic Feet Per Second) Of Water Conserved (C.3.e.3)
|
1
|
Milestone Name | Target Date | Description |
Project Start
|
12/06/2012
|
|
Landowner Agreement to RCO
|
03/31/2013
|
|
Preliminary Design to RCO
|
06/30/2013
|
Well Pumps/Outfitting for four existing wells.
|
Annual Project Billing Due
|
07/31/2013
|
|
Progress Report Due
|
07/31/2013
|
|
Bid Awarded/Contractor Hired
|
08/31/2013
|
Well pumps, outfitting for 4 existing wells.
|
Applied for Permits
|
09/30/2013
|
|
Cultural Resources Complete
|
10/31/2013
|
|
Preliminary Design to RCO
|
01/31/2014
|
Shared river intake.
|
Progress Report Due
|
01/31/2014
|
|
Annual Project Billing Due
|
07/31/2014
|
|
Progress Report Due
|
07/31/2014
|
|
Permits Complete
|
09/30/2014
|
|
Preliminary Design to RCO
|
09/30/2014
|
Milne intake reconfiguration.
|
Bid Awarded/Contractor Hired
|
09/30/2014
|
Milne intake reconfiguration
|
Restoration Complete
|
10/31/2014
|
Drilling and development of additional well.
|
Progress Report Due
|
01/31/2015
|
|
Restoration Started
|
03/31/2015
|
|
Funding Acknowl Sign Posted
|
04/30/2015
|
|
Progress Report Due
|
07/31/2015
|
|
Restoration Complete
|
09/30/2015
|
|
Stewardship Plan to RCO
|
09/30/2015
|
|
Annual Project Billing Due
|
10/30/2015
|
|
Agreement End Date
|
11/30/2015
|
|
RCO Final Inspection
|
12/31/2015
|
|
Final Report Due
|
02/28/2016
|
|
Final Design to RCO
|
02/28/2016
|
|
Final Billing Due
|
02/28/2016
|
|