This project provides funding to monitor an ELJ project in the Upper Entiat. The ELJ project is to construct 5 Engineered Log Jams (ELJ) in the Upper Entiat River (Figures 8, and 10-15). Each ELJ structure will consist of 25-50 conifer trees with and without root wads. The logs range in size from 14-36 inches in diameter and vary in length from 12-60 feet. There will be 2 types of log jams: bank oriented/deflector and mid-channel/bar apex. Each structure is sited in a specific location to achieve maximum biological benefit and is largely based on a detailed USFWS geomorphic analysis (USFWS, unpublished data). ELJ designs are based on a 2010 USFWS survey of natural log jams in the White River (USFWS, 2011). This funding will allow for:
- Quarterly site visits by two staff for photo documentation - Staff time to reduce survey data and produce drawings - Staff visits during high glow events to monitor structures and identify downstream impacts - Site visits with emergency responders (one year post-construction) for evaluation of any changes
|
General Area:
|
|
Entiat River
|
County:
|
|
Chelan
|
Legislative District:
|
|
12
|
Congressional District 2022:
|
|
08
|
Salmon Recovery Regions:
|
|
Upper Columbia River
|
Watershed Administrative Unit:
|
|
Lower Entiat
|
WRIA:
|
|
Entiat
|
Coordinates:
|
|
47.71739567 -120.34041834
|
|
|
Worksite Name | Scope of Work | Actual Monitoring Cost |
Dillwater (#1)
|
Intensively monitored watershed (E.1.c.15)
|
$5,999
|
| Total | $5,999 |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Monitoring |
Intensively monitored watershed (E.1.c.15) |
|
# acres (to nearest 0.1 acre) Intensively monitored watershed (E.1.c.15.c)
|
20.0
|
|
# miles (to nearest 0.01 mile) Intensively monitored watershed (E.1.c.15.a)
|
2.60
|
Milestone Name | Target Date | Description |
Project Start
|
08/01/2012
|
|
Progress Report Due
|
01/31/2013
|
|
Progress Report Due
|
07/30/2013
|
|
Agreement End Date
|
09/30/2013
|
|
Final Billing Due
|
10/31/2013
|
|
Final Report
|
10/31/2013
|
started 6/16/14
|