Myers- Trib to Blackjack Creek R11
|
Kitsap Conservation District; Myers- Trib to Blackjack Creek R11 (#12-1945)
Attachment #157686, Myers_BlackjackCr_Outlet
|
|
|
    Funding |
  |
FFFPP Grants:
|
$122,193
|
|
Total RCO Grant:
|
$122,193
|
(100%)
|
Total Agreement:
|
$122,193
|
(100%)
|
|
    Links |
  |
|
|
The KitsapConservation District will sponsorthis bridge replacement project which is a high priority fish passage barrier on a tributary to Blackjack Creek in Kitsap county. The crossing currently consists of avery small and low bridge over a very flashy stream that builds up with streambed materials and blocks passage of fish. The structure is too small for the system and will be replaced with a larger structure that allows for proper hydraulic function andwillallow unimpeded fish passage. Correction of this barrier would improve access to 2.19 miles of habitat for coho, chum, steelhead and searun cutthroat trout.
|
General Area:
|
|
Kitsap County
|
Waterbody:
|
|
Blackjack Creek, Un-named
|
County:
|
|
Kitsap
|
Legislative District:
|
|
35
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
S Sinclair Inlet
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kitsap
|
Sections:
|
|
22
|
Township:
|
|
T23NR01E
|
Coordinates:
|
|
47.46952041 -122.65341427
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Myers Fish Barrier (#1)
|
Architectural & Engineering (A&E), Bridge installed or improved (C.2.g.1)
|
$122,193
|
| Total | $122,193 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Myers Fish Barrier (#1)
|
|
Property 1 - Myers
|
Private
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Fish Passage Improvement |
Bridge installed or improved (C.2.g.1) |
|
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
|
2.19
|
|
Number of bridges (C.2.g.2)
|
1
|
|
|
Number of blockages / impediments / barriers impeding passage (C.2.b.4)
|
1
|
Milestone Name | Target Date | Description |
Project Start
|
09/01/2013
|
|
Preliminary Design to RCO
|
03/14/2014
|
|
Landowner Agreement to RCO
|
04/05/2014
|
|
Final Design to RCO
|
04/15/2014
|
|
Applied for Permits
|
04/15/2014
|
|
Progress Report Due
|
05/12/2014
|
|
Permits Complete
|
05/15/2014
|
|
Bid Awarded/Contractor Hired
|
05/31/2014
|
|
Cultural Resources Complete
|
06/30/2014
|
|
Annual Project Billing Due
|
07/31/2014
|
|
Restoration Started
|
09/17/2014
|
|
Progress Report Due
|
10/01/2014
|
|
Restoration Complete
|
10/30/2014
|
|
RCO Final Inspection
|
12/24/2014
|
|
Agreement End Date
|
01/31/2015
|
|
Final Report Due
|
02/16/2015
|
|
Final Billing Due
|
02/28/2015
|
|