Project Snapshot
PRISM Project #13-1137 (Completed)
Milwaukee Dock Eelgrass Restoration
    Project Details    
Suquamish Tribe; Milwaukee Dock Eelgrass Restoration (#13-1137)

Attachment #159772, Milwaukee Dock Aerial Photo Showing Depressional Area
Suquamish Tribe; Milwaukee Dock Eelgrass Restoration (#13-1137) Attachment #159772, Milwaukee Dock Aerial Photo Showing Depressional Area

Suquamish Tribe; Milwaukee Dock Eelgrass Restoration (#13-1137)

Attachment #159772, Milwaukee Dock Aerial Photo Showing Depressional Area Suquamish Tribe; Milwaukee Dock Eelgrass Restoration (#13-1137)

Attachment #159774, Milwaukee Dock Historic Aerial
Project Status:  Closed Completed since 01/12/2017
 
Project Type:  Restoration
Project Sponsor:  Suquamish Tribe
Funding Board:  Salmon Recovery Funding Board
              Funding  
PSAR Large Capital Projects: $1,731,325
Total RCO Grant: $1,731,325 (94%)
Sponsor Match: $116,077 (6%)
Total Agreement: $1,847,403 (100%)
              Links
 

    Project Description    
The Suquamish Tribe with the Elliott Bay Trustee Council will complete eelgrass restoration at Milwaukee Dock, located approximately 200 feet from the beach at Pritchard Park near Eagle Harbor, Bainbridge Island. The overall project entails filling 2 sub-tidal, artificial depressions covering an area of approximately 3 acres at a depth up to -25 feet (MLLW) to replant with eelgrass. An extensive and dense eelgrass meadow surrounds the area of the former Dock, but channels were dredged through meadow to access the dock. Sparse eelgrass exists in the depressions only to depths between -12 and -14 feet (MLLW). The dredged channels are no longer needed. This proposal will fund restoration of the north depression. The Trustees completed overall restoration design and permitting. The first phase of restoration initiated in 2012 and completed in 2013 was funded by the Trustees and entailed 1) placing fill to return south depression elevations to approximate pre-dredge conditions; and 2) transplanting eelgrass propagated at Pacific Northwest National Laboratory (PNNL) Marine Science Lab. The habitat that was destroyed by the dredging will be returned to approximate pre-disturbance elevation and vegetation community to benefit ESA listed Chinook salmon, as well as coho, steelhead, bull trout, and forage fish such as herring.

    Project Contacts    
         
Project Sponsor: Suquamish Tribe Lead Entity: West Sound Partners for Ecosystem Recovery
  Project Contact: Tom Ostrom

   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
General Area:   Eagle Harbor Bainbridge Island
County:   Kitsap
Legislative District:   23
Congressional District 2022:   06
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Bainbridge Island
HUC8:   Puget Sound (17110019)
WRIA:   Kitsap
Coordinates:   47.61714743
-122.49923231

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Milwaukee Dock (#1) Architectural & Engineering (A&E), Beach nourishment (C.9.l.1), Estuarine planting or native plant establishment (C.9.r.1) $1,854,133
 Total$1,854,133
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Milwaukee Dock (#1)   Property 1 - South Depression State Government
Milwaukee Dock (#1)   Property 2 - North Depression State Government
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

Estuarine / Nearshore Project
      Beach nourishment (C.9.l.1)
Cubic Yards Of Beach Substrate Placed (C.9.l.2) 21000
Miles of Shoreline Treated for beach nourishment (C.9.l.3) 0.01
Acres Treated for beach nourishment (C.9.l.4) 1.6

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/05/2013
Landowner Agreement to RCO 12/05/2013 PRISM Attach. 1 (incls stewardship plan)
Preliminary Design to RCO 12/05/2013 PRISM Attach. 14
Cultural Resources Complete 12/05/2013 Section 106 completed in 2008. THPO and SHPO concurrence letters PRISM Attach 18.
Applied for Permits 12/05/2013
Permits Complete 01/31/2014 Secure extensions to existing permits.
Progress Report Due 06/04/2014
Final Design to RCO 06/30/2014 Bid docs
Bid Awarded/Contractor Hired 08/15/2014
Annual Project Billing Due 12/03/2014
Progress Report Due 12/04/2014
Restoration Started 12/05/2014
Progress Report Due 06/04/2015
Progress Report Due 10/31/2015
Final Design to RCO 04/30/2016 Planting plan with memo before planting begins
Progress Report Due 04/30/2016
Progress Report Due 09/30/2016
Restoration Complete 10/31/2016
Final Report Due 10/31/2016
RCO Final Inspection 11/30/2016
Final Design to RCO 11/30/2016 As Built as described in appendix D-4
Agreement End Date 12/31/2016 Project closing: All expenditures must be incurred prior to this date.
Final Billing Due 01/31/2017


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 13-1137 Project Agreement.pdf 04/10/2014
Agreements - Special DNR Aquatic Lands Agreement Amendment.pdf 08/03/2017
Amendment - State 13-1137 Amend #1 Time Ext.pdf 08/03/2017
Correspondence 12C0038 Contract Award for fill of south depression.pdf 04/22/2013
Correspondence Site Visit, Milwaukee Dock Eelgrass Restoration 13-1137.pdf 03/29/2013
Correspondence WRIA 15 Milwaukee Dock Eelgrass Restoration Project.pdf 03/29/2013
Cost Estimate milwaukee dock.xlsx 08/30/2013
Cost Estimate Milwaukee Dock Budget - Justifications added 4-22-2013.pdf 04/22/2013
Cost Estimate Milwaukee Dock Budget.pdf 03/28/2013
Cultural Resources: DAHP Response SPHO and THPO 106 responses Mil Dock.pdf 08/09/2013
Design document Milwaukee Dock Planting Plan.pdf 04/26/2016
Design document Design Plans (includes north depression as option).pdf 08/06/2013
Design document (as built) Milwaukee Eelgrass northern depression As-Built.pdf 09/27/2016
Final project report Final Report, 13-1137 (accepted 04/04/17 08:35:12).pdf 04/04/2017
Final project report Final Report 01/12/2017.pdf 01/12/2017
Inspection Report Inspection Report, #901 (Submitted 12/14/16 08:01:16).pdf 12/14/2016
Landowner acknowledgement form Landowner Acknowledgement Form - Milwaukee Dock.pdf 08/09/2013
Landowner agreement Executed Amendment to ROE 23-086389[1].pdf 03/28/2013
Landowner agreement Executed Aquatic Lands Final Right of Entry-Eelgrass Restora.pdf 03/28/2013
Map: Restoration Worksite WRIA 15 Milwaukee Dock Eelgrass Restoration Project Location.pdf 03/29/2013
News Article Milwaukee Dock eelgrass article.pdf 08/09/2013
Photo Milwaukee Dock Historic Aerial.jpg 03/29/2013
Photo Milwaukee Dock Photo Showing Placement of Fill from Barge.jpg 03/29/2013
Photo Milwaukee Dock Aerial Photo Showing Depressional Area.jpg 03/29/2013
Plans and Bid Specifications Milwuakee Dock Eelgrass - 21 JULY 2014 New.pdf 09/15/2014
Progress report Progress Report 09/27/2016.pdf 09/27/2016
Progress report Progress Report 04/29/2016.pdf 04/29/2016
Progress report Progress Report 10/29/2015.pdf 10/29/2015
Progress report Progress Report 04/10/2015.pdf 04/10/2015
Progress report Progress Report 01/21/2015.pdf 01/21/2015
Progress report Progress Report 06/18/2014.pdf 06/18/2014
Project Application Report Application Report, 13-1137R (submitted 08/30/13).pdf 08/30/2013
Project Application Report Application Report, 13-1137R (submitted 08/09/13).pdf 08/09/2013
Project Support / Concern Documents Milwaukee Dock 401 extension.pdf 01/06/2014
Project Support / Concern Documents Milwaukee Dock NWP27 extension.pdf 01/06/2014
Project Support / Concern Documents Milwaukee Dock HPA extension.pdf 12/05/2013
Project Support / Concern Documents Appendix G-1 (MD).pdf 08/30/2013
Salmon Project Proposal Project_Proposal_Milwaukee_Dock_Rev1.1.doc 08/09/2013
Salmon Project Proposal Project_Proposal_Milwaukee_Dock.doc 03/28/2013
Scope of work PNNL Proposed SOW Budget for South Depression.pdf 04/22/2013
Visuals Milwaukee Dock Eelgrass PSP update 2015.ppt 10/28/2015
Visuals WSWC TAG 13-OCT-15 - Milwaukee Dock.pptx 10/23/2015
Visuals Milwaukee Eelgrass 2015-02-05 PostConstSurvey.pdf 06/15/2015

Back to top Date of last change: 10/04/2023