Milwaukee Dock Eelgrass Restoration
|
Suquamish Tribe; Milwaukee Dock Eelgrass Restoration (#13-1137)
Attachment #159772, Milwaukee Dock Aerial Photo Showing Depressional Area
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The Suquamish Tribe with the Elliott Bay Trustee Council will complete eelgrass restoration at Milwaukee Dock, located approximately 200 feet from the beach at Pritchard Park near Eagle Harbor, Bainbridge Island. The overall project entails filling 2 sub-tidal, artificial depressions covering an area of approximately 3 acres at a depth up to -25 feet (MLLW) to replant with eelgrass. An extensive and dense eelgrass meadow surrounds the area of the former Dock, but channels were dredged through meadow to access the dock. Sparse eelgrass exists in the depressions only to depths between -12 and -14 feet (MLLW). The dredged channels are no longer needed. This proposal will fund restoration of the north depression. The Trustees completed overall restoration design and permitting. The first phase of restoration initiated in 2012 and completed in 2013 was funded by the Trustees and entailed 1) placing fill to return south depression elevations to approximate pre-dredge conditions; and 2) transplanting eelgrass propagated at Pacific Northwest National Laboratory (PNNL) Marine Science Lab. The habitat that was destroyed by the dredging will be returned to approximate pre-disturbance elevation and vegetation community to benefit ESA listed Chinook salmon, as well as coho, steelhead, bull trout, and forage fish such as herring.
|
General Area:
|
|
Eagle Harbor Bainbridge Island
|
County:
|
|
Kitsap
|
Legislative District:
|
|
23
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Bainbridge Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kitsap
|
Coordinates:
|
|
47.61714743 -122.49923231
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Milwaukee Dock (#1)
|
Architectural & Engineering (A&E), Beach nourishment (C.9.l.1), Estuarine planting or native plant establishment (C.9.r.1)
|
$1,854,133
|
| Total | $1,854,133 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Milwaukee Dock (#1)
|
|
Property 1 - South Depression
|
State Government
|
Milwaukee Dock (#1)
|
|
Property 2 - North Depression
|
State Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Estuarine / Nearshore Project |
Beach nourishment (C.9.l.1) |
|
Cubic Yards Of Beach Substrate Placed (C.9.l.2)
|
21000
|
|
Miles of Shoreline Treated for beach nourishment (C.9.l.3)
|
0.01
|
|
Acres Treated for beach nourishment (C.9.l.4)
|
1.6
|
Milestone Name | Target Date | Description |
Project Start
|
12/05/2013
|
|
Landowner Agreement to RCO
|
12/05/2013
|
PRISM Attach. 1 (incls stewardship plan)
|
Preliminary Design to RCO
|
12/05/2013
|
PRISM Attach. 14
|
Cultural Resources Complete
|
12/05/2013
|
Section 106 completed in 2008. THPO and SHPO concurrence letters PRISM Attach 18.
|
Applied for Permits
|
12/05/2013
|
|
Permits Complete
|
01/31/2014
|
Secure extensions to existing permits.
|
Progress Report Due
|
06/04/2014
|
|
Final Design to RCO
|
06/30/2014
|
Bid docs
|
Bid Awarded/Contractor Hired
|
08/15/2014
|
|
Annual Project Billing Due
|
12/03/2014
|
|
Progress Report Due
|
12/04/2014
|
|
Restoration Started
|
12/05/2014
|
|
Progress Report Due
|
06/04/2015
|
|
Progress Report Due
|
10/31/2015
|
|
Final Design to RCO
|
04/30/2016
|
Planting plan with memo before planting begins
|
Progress Report Due
|
04/30/2016
|
|
Progress Report Due
|
09/30/2016
|
|
Restoration Complete
|
10/31/2016
|
|
Final Report Due
|
10/31/2016
|
|
RCO Final Inspection
|
11/30/2016
|
|
Final Design to RCO
|
11/30/2016
|
As Built as described in appendix D-4
|
Agreement End Date
|
12/31/2016
|
Project closing: All expenditures must be incurred prior to this date.
|
Final Billing Due
|
01/31/2017
|
|