Badger Mtn ID Riverstation screens
|
Badger Mtn Irrigation District; Badger Mtn ID Riverstation screens (#14-1348)
Attachment #268872, All screens are installed
|
|
|
    Funding |
  |
|
    Links |
|
  |
|
|
Badger Mountain Irrigation District (BMID) proposes to install six new, belt-driven fish exclusion screens at BMID’s existing water diversion intake from the Yakima River. The screens will replace five 38-year old screens that are nearing the end of their service life and one screen that is now absent. The screens are located on the Yakima River in the proximity of 540 Columbia Park trail, Richland, WA. Species protected by the screens include juvenile steelhead, juvenile summer and fall Chinook, and juvenile Coho.
The new traveling screens will be sized to match the old screens and housed in the existing river station. Removal and installation of the screens will be done by a boom truck lifting the units vertically up and out of each individual chambered pocket within the existing concrete structure. Upgrading the screens will promote more consist running time and more effective debris clearing of the screens, making for a positive barrier between our intake diversions and the juvenile fish species present at this site in the lower Yakima River.
|
General Area:
|
|
lower Yakima River
|
County:
|
|
Benton
|
Legislative District:
|
|
08
|
Congressional District 2022:
|
|
04
|
Salmon Recovery Regions:
|
|
Middle Columbia River
|
Watershed Administrative Unit:
|
|
Cold Creek Agricultural Lands
|
HUC8:
|
|
Lower Yakima (17030003)
|
WRIA:
|
|
Lower Yakima
|
Sections:
|
|
23
|
Township:
|
|
T09NR28E
|
Coordinates:
|
|
46.24513480 -119.26936298
|
|
|
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Badger Mtn Irrigation Dist Fish Screens (#1)
|
|
Property 1 - U.S. Corps of Engineers
|
Federal Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Permits |
Obtain permits |
|
Number of permits required for implementation of project
|
4
|
Fish Screening Project |
Fish screens replaced or modified (C.1.d.1) |
|
The Flow Rate Of Screened Water (C.1.d.3)
|
99.00
|
|
Number Of Fish Screens Replaced Or Modified (C.1.d.2)
|
6
|
Milestone Name | Target Date | Description |
Project Start
|
12/03/2014
|
|
Progress Report Due
|
06/30/2015
|
|
Cultural Resources Complete
|
07/01/2015
|
no ground disturbance is planned; if that changes, please notify RCO immediately
|
Bid Awarded/Contractor Hired
|
07/31/2015
|
|
Applied for Permits
|
08/15/2015
|
|
Landowner Agreement to RCO
|
10/01/2015
|
from Army Corps of Engineers, also attach screen operation and maintenance plan to PRISM
|
Permits Complete
|
11/01/2015
|
|
Restoration Started
|
11/30/2015
|
|
Final Design to RCO
|
11/30/2015
|
BMID will submit all engineering and specifications of materials
|
Progress Report Due
|
11/30/2015
|
|
Funding Acknowl Sign Posted
|
01/31/2016
|
RCO has small metal signs available for use upon request
|
RCO Final Inspection
|
05/31/2016
|
|
Restoration Complete
|
06/15/2016
|
|
Agreement End Date
|
06/15/2016
|
PROJECT CLOSING. All expenditures must be prior to this date.
|
Final Design to RCO
|
06/15/2016
|
As-built documentation, if constructed project differs from final design
|
Final Report Due
|
07/31/2016
|
|
Annual Project Billing Due
|
07/31/2016
|
|
Final Billing Due
|
08/15/2016
|
|