Cornet Bay Moorage Facility Replacement - BFP
|
    Funding |
  |
|
    Links |
  |
|
|
the Washington State Parks and Recreation Commission will use this grant to improve and expand the marina facilities at the Cornet Bay Marine Area of Deception Pass State Park in Island County. Project scope includes replacement of the existing pedestrian access pier, gangway ramp, pilings and moorage floats, and development of approximately 384 linear feet of new moorage. The primary recreation opportunity provided by this project is motorized boating.
|
General Area:
|
|
Deception Pass State Park.
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Coordinates:
|
|
48.40055041 -122.62428950
|
|
|
Worksite Name | Scope of Work | Actual Development Cost |
Cornet Bay Marine Area (#1)
|
Architectural & Engineering (A&E), Boarding float installation, Cultural resources, Gangway installation, General site preparation, Install pilings, Install power utilities, Obtain permits, Transient moorage
|
$1,664,000
|
| Total | $1,664,000 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Cornet Bay Marine Area (#1)
|
|
Property 1 - Cornet Bay Marine Area
|
State Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Permits |
Obtain permits |
|
Number of permits required for implementation of project
|
6
|
Boating Infrastructure |
Boarding float installation |
|
Linear feet of the boarding floats
|
32
|
Transient moorage |
|
Linear feet of fixed pier
|
235
|
|
Linear feet of moorage
|
384
|
|
Number of fixed piers
|
New: 1, Renov: 0
|
Site Preparation |
General site preparation |
|
Acres of site preparation
|
1.00
|
Milestone Name | Target Date | Description |
Project Start
|
11/01/2015
|
|
Design Initiated
|
01/01/2016
|
|
Progress Report Due
|
03/31/2016
|
|
60% Plans to RCO
|
06/01/2016
|
|
Annual Project Billing Due
|
07/31/2016
|
|
Progress Report Due
|
09/30/2016
|
|
Cultural Resources Complete
|
12/31/2016
|
Evidence of compliance with Executive Order 05-05 and/or Section 106 required, see special condition #1.
|
Applied for Permits
|
12/31/2016
|
|
SEPA/NEPA Completed
|
12/31/2016
|
|
Progress Report Due
|
03/31/2017
|
|
Annual Project Billing Due
|
07/31/2017
|
|
Progress Report Due
|
09/30/2017
|
|
Progress Report Due
|
03/31/2018
|
|
Progress Report Due
|
02/28/2019
|
|
Annual Project Billing Due
|
04/30/2019
|
|
Progress Report Due
|
10/31/2019
|
|
Progress Report Due
|
05/05/2020
|
|
Annual Project Billing Due
|
07/31/2020
|
|
Progress Report Due
|
09/30/2020
|
|
Progress Report Due
|
03/31/2021
|
|
All Bid Docs/Plans to RCO
|
04/30/2021
|
|
Bid Awarded/Contractor Hired
|
07/01/2021
|
|
Annual Project Billing Due
|
07/31/2021
|
|
Construction Started
|
08/31/2021
|
|
Progress Report Due
|
11/09/2021
|
|
RCO Interim Inspection
|
12/31/2021
|
|
50% Construction Complete
|
12/31/2021
|
|
Progress Report Due
|
01/31/2022
|
|
90% Construction Complete
|
02/28/2022
|
|
Construction Complete
|
02/28/2022
|
|
Funding Acknowl Sign Posted
|
04/30/2022
|
|
RCO Final Inspection
|
05/31/2022
|
|
Final Billing Due
|
05/31/2022
|
|
Final Report Due
|
06/15/2022
|
|
Agreement End Date
|
06/30/2022
|
Approved via RCFB Resolution #2019-12 (to 6/30/2021) and RCFB Resolution #2021-05 (to 6/30/2022).
|
Attachment Type | Attachment Title | Attach Date |
Agreement - State
|
14-1641 Project Agreement.pdf
|
10/20/2015
|
Amendment - State
|
14-1641 Amendment #4 - Time Extension.pdf
|
05/20/2021
|
Amendment - State
|
14-1641-Amend1-TimeExtension.pdf
|
06/28/2019
|
Amendment - State
|
14-1641-Amend3-TimeExtension.pdf
|
06/28/2019
|
Amendment - State
|
Amend 2-Cost Change.pdf
|
11/29/2018
|
Applicant Resolution/Authorizations
|
2014 Boating Infrastructure-AppAuth.pdf
|
06/17/2014
|
Application Review Report
|
Application Review Report, 14-1641D(compl 08/29/14 09:02:34).pdf
|
08/29/2014
|
Application Review Report
|
Application Review Report, 14-1641D(rtnd 08/04/14 11:57:55).pdf
|
08/04/2014
|
Billing forms
|
Distribution of Payroll Oct-Dec 2021.xlsx.xlsx
|
01/24/2022
|
Billing forms
|
Distribution of Payroll Apr-Jun2021.xls.xls
|
07/15/2021
|
Billing forms
|
Distribution of Payroll Jul-Sep 2020.xls.xls
|
10/23/2020
|
Billing forms
|
Distribution of Payroll Apr-Jun2020.xls.xls
|
07/24/2020
|
Billing forms
|
Distribution of Payroll Jan-Mar2020.xls.xls
|
04/17/2020
|
Billing forms
|
Distribution of Payroll Oct-Dec2019.xls.xls
|
01/17/2020
|
Billing forms
|
Distribution of Payroll Jul-Sep2019.xls.xls
|
10/17/2019
|
Billing forms
|
Distribution of Payroll Oct-Dec2018.xls.xls
|
01/16/2019
|
Billing forms
|
Distribution of Payroll Jul-Sep2018.xls.xls
|
11/09/2018
|
Billing forms
|
Distribution of Payroll Apr-Jun2018.xls.xls
|
07/17/2018
|
Billing forms
|
WWA BI Jan-Mar2018 Distribution of Payroll and Related Costs.xls
|
04/16/2018
|
Billing forms
|
HRMS BI Report Oct-Dec2017.xls.xls
|
01/16/2018
|
Billing forms
|
HRMS BI Report Jul-Sep2017.xls.xls
|
10/16/2017
|
Billing forms
|
HRMS BI Report Apr-Jun2017.xls.xls
|
07/17/2017
|
Billing forms
|
HRMS BI Report Oct2016-Mar2017.xls.xls
|
04/17/2017
|
Billing forms
|
HRMS BI Report Jul-Sep2016.xls
|
10/20/2016
|
Billing forms
|
HRMS BI Report Apr-Jun2016.xls
|
07/19/2016
|
Billing forms
|
HRMS BI Report Jan-Mar2016.xls
|
04/15/2016
|
Control & Tenure Documentation
|
Cornet Bay deed.jpg
|
06/23/2014
|
Evaluation: Project presentation - Final
|
14-1641 State Parks-Dec Pass-Cornet Bay Moorage.ppt
|
09/23/2014
|
Final project report
|
Final Report, 14-1641 (accepted 06/24/22 09:41:39).pdf
|
06/24/2022
|
Map: Regional Location
|
Cornet Bay Location.jpg
|
06/17/2014
|
Milestones
|
Milestones 16-1641D CB moorage.docx
|
07/14/2015
|
Permit
|
2018_06-14_CornetBayPier_WCR-2017-7601.pdf
|
03/03/2024
|
Permit
|
01EWFW00-2018-F-1399 - Initiation Letter (2).pdf
|
10/03/2018
|
Photo
|
Existing Moorage Pier_ Gangway.jpg
|
06/17/2014
|
Plans and Bid Specifications
|
20210708 NW-C3714 D Pass-Cornet Bay Moorage-Drawings.pdf
|
07/13/2021
|
Plans and Bid Specifications
|
20210708 NW-C3714 D Pass-Cornet Bay Moorage-Specs Book2.pdf
|
07/13/2021
|
Plans and Bid Specifications
|
20210708 NW-C3714 D Pass-Cornet Bay Moorage-Specs Book1.pdf
|
07/13/2021
|
Plans and Bid Specifications
|
Cornet Bay Construction Dwgs (5-6-21) Signed.pdf.pdf
|
07/01/2021
|
Progress report
|
Progress Report, 14-1641 (accepted 11/09/21 12:15:34).pdf
|
11/09/2021
|
Progress report
|
Progress Report, 14-1641 (accepted 02/08/21 18:07:58).pdf
|
02/08/2021
|
Progress report
|
Progress Report, 14-1641 (accepted 05/05/20 17:44:21).pdf
|
05/05/2020
|
Progress report
|
Progress Report, 14-1641 (accepted 01/08/20 11:45:25).pdf
|
01/08/2020
|
Progress report
|
Progress Report, 14-1641 (accepted 04/30/19 14:19:17).pdf
|
04/30/2019
|
Progress report
|
Progress Report, 14-1641 (accepted 03/02/18 16:26:49).pdf
|
03/02/2018
|
Progress report
|
Progress Report, 14-1641 (accepted 09/08/17 11:40:51).pdf
|
09/08/2017
|
Progress report
|
Progress Report, 14-1641 (accepted 04/26/17 11:34:07).pdf
|
04/26/2017
|
Progress report
|
Progress Report 09/01/2016.pdf
|
09/01/2016
|
Progress report
|
Progress Report 03/03/2016.pdf
|
03/03/2016
|
Project Application Report
|
Application Report, 14-1641D (submitted 08/28/14 12:35:11).pdf
|
08/28/2014
|
Project Application Report
|
Application Report, 14-1641D (submitted 06/23/14 13:53:15).pdf
|
06/23/2014
|
Site Plan: Development site plan
|
Preliminary Layout 1.pdf
|
06/17/2014
|