The Whidbey Camano Land Trust will use this grant to acquire 59 acres of nearshore habitat located on the southeast side of Whidbey Island along Saratoga Passage. The project area consists of four parcels that total 33 acres of uplands, 2,000 feet of feeder bluff, 2 streams, and 26 acres of tidelands. Eelgrass, Dungeness crab, pandalid shrimp, and geoduck are found on the project area’s tidelands and outmigrating juvenile salmon use the shoreline as a travel corridor. The primary purpose of this project is to conserve high-priority, Puget Sound marine shoreline habitats.
|
General Area:
|
|
Clinton, South Whidbey Island
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Whidbey Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Island
|
Sections:
|
|
13
|
Township:
|
|
T29NR03E
|
Coordinates:
|
|
47.99668244 -122.37328440
|
|
|
Worksite Name | Scope of Work |
Waterman Nearshore (#1)
|
Administrative costs (Acq), Appraisal, Appraisal Review, Closing, Recording, Taxes, Title, Environmental Audits, Fencing (Acq), Land, Noxious weed control, Signs (Acq), Stewardship plan, Survey (Acq)
|
| |
Amounts may not be complete
Worksite Name | | Property Name | | Actual Acquisition Acres | Actual Acquisition Cost |
Waterman Nearshore (#1)
|
|
Property 1 - Private Landowner
|
|
58.94
|
$1,634,913
|
| | | Total | 58.94 | $1,634,913 |
Amounts may not be complete
Milestone Name | Target Date | Description |
Project Start
|
09/03/2014
|
|
Progress Report Due
|
12/31/2014
|
|
Order Appraisal(s)
|
02/28/2015
|
|
Order Appraisal Review(s)
|
02/28/2015
|
|
Progress Report Due
|
03/31/2015
|
Not necessary since agreement was just signed
|
Progress Report Due
|
06/30/2015
|
|
Annual Project Billing Due
|
07/31/2015
|
|
RCO Interim Inspection
|
08/14/2015
|
|
Purchase Agreement Signed
|
08/15/2015
|
|
Environmental Audit Complete
|
09/15/2015
|
|
Cultural Resources Complete
|
09/15/2015
|
|
Acquisition Closing
|
10/31/2015
|
|
Funding Acknowl Sign Posted
|
11/30/2015
|
|
Recorded Acq Documents to RCO
|
12/31/2015
|
|
Recorded Land Survey to RCO
|
12/31/2015
|
|
RCO Final Inspection
|
06/15/2016
|
|
Special Conditions Met
|
06/30/2016
|
|
Noxious Weed Control Complete
|
06/30/2016
|
|
Stewardship Plan to RCO
|
08/31/2016
|
|
Final Report Due
|
08/31/2016
|
|
Agreement End Date
|
08/31/2016
|
|
Final Billing Due
|