Feeder Bluff and Armor Removal Assessment Project
|
    Funding |
  |
|
    Links |
  |
|
|
This project will populate the PSNERP/ESRP projects portfolio with feeder bluff restoration projects aimed at restoring the sources of degradation and sediment supply to shoreline process units in Island and East Jefferson Counties. This is a pilot project employing a three-phase approach to achieve a list of ‘ready to proceed’ feeder bluff restoration projects. First will be a technical analysis of existing data on feeder bluff parcels designed to identify and prioritize bluff restoration sites with the highest potential to restore processes. These sites will be sorted by restoration priority and by landowner (public, commercial, or private). Phase two will implement project development activities designed to reach out to landowners in high priority areas to increase awareness of coastal processes and encourage the consideration of alternatives to armoring to establish landowner willingness for armor removal. The third and final phase will be the production of 3-4 conceptual designs for feeder bluff restoration projects in high priority areas that will restore sediment supply to shoreline process units and have landowner willingness. These projects will be ready for final design and implementation. Additionally, the project will produce a longer list of potential projects to restore sediment supply ready for entry into the PSNERP project portfolio.
|
General Area:
|
|
Island County
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Whidbey Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Island
|
Sections:
|
|
24
|
Township:
|
|
T33NR01E
|
Coordinates:
|
|
48.33873541 -122.61645649
|
|
|
Worksite Name | Scope of Work | Actual Planning Cost |
East Jefferson County and Island County (#1)
|
Conducting habitat restoration scoping and feasibility studies (B.1.b.8), Preliminary design (B.1.b.11.a RCO)
|
$295,535
|
| Total | $295,535 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
East Jefferson County and Island County (#1)
|
|
Property 1 - Seahorse Siesta
|
Private
|
East Jefferson County and Island County (#1)
|
|
Property 2 - Maylors Point
|
Federal Government
|
East Jefferson County and Island County (#1)
|
|
Property 3 - Waterman
|
Private
|
East Jefferson County and Island County (#1)
|
|
Property 4 - Beckett Point
|
Private
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
|
|
|
Area Encompassed (acres) (B.0.b.1)
|
0.7
|
|
Miles of Stream and/or Shoreline Affected (B.0.b.2)
|
0.42
|
Milestone Name | Target Date | Description |
Project Start
|
01/01/2013
|
Eligible pre-agreement expenditures
|
Data Gathering Started
|
01/01/2013
|
Eligible pre-agreement expenditures
|
RFP Complete/Consultant Hired
|
09/22/2014
|
|
Progress Report Due
|
12/31/2014
|
|
Progress Report Due
|
06/30/2015
|
|
Annual Project Billing Due
|
07/31/2015
|
|
Progress Report Due
|
12/31/2015
|
|
Progress Report Due
|
06/30/2016
|
|
Annual Project Billing Due
|
07/31/2016
|
|
Progress Report Due
|
12/31/2016
|
|
Final Plan to RCO
|
03/31/2017
|
Plan will include feasibility assessments of a number of parcels identified for armor removal
|
Progress Report Due
|
03/31/2017
|
|
Draft Design to RCO
|
06/01/2017
|
Deliverables include draft preliminary armor removal designs for at least three feeder bluff parcels
|
Draft Plan to RCO
|
06/01/2017
|
Plan will include draft feasibility assessments of a number of parcels identified for armor removal
|
Preliminary Design to RCO
|
06/30/2017
|
Deliverables include preliminary armor removal designs for at least three feeder bluff parcels
|
Special Conditions Met
|
05/31/2018
|
Consistent with Statement of Work
|
Agreement End Date
|
05/31/2018
|
|
Final Report Due
|
06/30/2018
|
|
Final Billing Due
|
06/30/2018
|
|