PRISM Project #14-2196 (Completed)
Feeder Bluff and Armor Removal Assessment Project
    Project Details    
Project Status:  Closed Completed since 09/17/2018
 
Project Type:  Planning
Project Sponsor:  Northwest Straits Marine Conservation Foundation
Funding Board:  Recreation and Conservation Office
              Funding  
Estuary & Salmon Restoration: $194,969
Total RCO Grant: $194,969 (75%)
Sponsor Match: $63,528 (25%)
Total Agreement: $258,497 (100%)
              Links
 

    Project Description    
This project will populate the PSNERP/ESRP projects portfolio with feeder bluff restoration projects aimed at restoring the sources of degradation and sediment supply to shoreline process units in Island and East Jefferson Counties. This is a pilot project employing a three-phase approach to achieve a list of ‘ready to proceed’ feeder bluff restoration projects. First will be a technical analysis of existing data on feeder bluff parcels designed to identify and prioritize bluff restoration sites with the highest potential to restore processes. These sites will be sorted by restoration priority and by landowner (public, commercial, or private). Phase two will implement project development activities designed to reach out to landowners in high priority areas to increase awareness of coastal processes and encourage the consideration of alternatives to armoring to establish landowner willingness for armor removal. The third and final phase will be the production of 3-4 conceptual designs for feeder bluff restoration projects in high priority areas that will restore sediment supply to shoreline process units and have landowner willingness. These projects will be ready for final design and implementation. Additionally, the project will produce a longer list of potential projects to restore sediment supply ready for entry into the PSNERP project portfolio.

    Project Contacts    
         
Project Sponsor: Northwest Straits Marine Conservation Foundation Lead Entity: Island County Lead Entity
  Project Contact: Lisa Kaufman
kaufman@nwstraitsfoundation.org
(360) 393-6948
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Kay Caromile
kay.caromile@rco.wa.gov
(360) 867-8532
   

    Project Location    
General Area:   Island County
County:   Island
Legislative District:   10
Congressional District 2022:   02
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Whidbey Island
HUC8:   Puget Sound (17110019)
WRIA:   Island
Sections:   24
Township:   T33NR01E
Coordinates:   48.33873541
-122.61645649

    Worksites    
Worksite NameScope of WorkActual Planning Cost
East Jefferson County and Island County (#1) Conducting habitat restoration scoping and feasibility studies (B.1.b.8), Preliminary design (B.1.b.11.a RCO) $295,535
 Total$295,535
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
East Jefferson County and Island County (#1)   Property 1 - Seahorse Siesta Private
East Jefferson County and Island County (#1)   Property 2 - Maylors Point Federal Government
East Jefferson County and Island County (#1)   Property 3 - Waterman Private
East Jefferson County and Island County (#1)   Property 4 - Beckett Point Private
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 0.7
Miles of Stream and/or Shoreline Affected (B.0.b.2) 0.42

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 01/01/2013 Eligible pre-agreement expenditures
Data Gathering Started 01/01/2013 Eligible pre-agreement expenditures
RFP Complete/Consultant Hired 09/22/2014
Progress Report Due 12/31/2014
Progress Report Due 06/30/2015
Annual Project Billing Due 07/31/2015
Progress Report Due 12/31/2015
Progress Report Due 06/30/2016
Annual Project Billing Due 07/31/2016
Progress Report Due 12/31/2016
Final Plan to RCO 03/31/2017 Plan will include feasibility assessments of a number of parcels identified for armor removal
Progress Report Due 03/31/2017
Draft Design to RCO 06/01/2017 Deliverables include draft preliminary armor removal designs for at least three feeder bluff parcels
Draft Plan to RCO 06/01/2017 Plan will include draft feasibility assessments of a number of parcels identified for armor removal
Preliminary Design to RCO 06/30/2017 Deliverables include preliminary armor removal designs for at least three feeder bluff parcels
Special Conditions Met 05/31/2018 Consistent with Statement of Work
Agreement End Date 05/31/2018
Final Report Due 06/30/2018
Final Billing Due 06/30/2018


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 14-2196 Project Agreement.pdf 10/07/2014
Amendment - State 14-2196 Amend #5 Time Ext.pdf 01/30/2018
Amendment - State 14-2196 Amend #3 Cost Change.pdf 01/22/2018
Amendment - State 14-2196 Amend #4 Time Ext.pdf 12/19/2017
Amendment - State 14-2196 Amend #2 Time Ext.pdf 10/17/2017
Amendment - State 14-2196 Amend #1 Time Extension.pdf 06/09/2015
Amendment request 2 Month Time Extension Request.txt 01/26/2018
Application Review Report Application Review Report, 14-2196P(compl 09/06/14 17:44:35).pdf 09/06/2014
Billing Expanded Documentation 14-3-2196 Mar2016-June2016 Allocations of Office NWSF.pdf 09/06/2016
Billing Expanded Documentation 14-2196 Oct2015-Feb2016 Allocations of Office NWSF.pdf 04/06/2016
Billing Expanded Documentation July-Sept 2015 Allocations of Office NWSF.pdf 10/09/2015
Billing Expanded Documentation June 2015 Allocations of Office NWSF.pdf 07/14/2015
Billing Expanded Documentation Mar,April,May 2015 Allocations of Office NWSF.pdf 06/09/2015
Billing forms match WA Dept Ecology.pdf 08/27/2015
Budget Worksheet ESRP cost estimate 082114.pdf 08/18/2014
Design document FEEDERBLUFF-DraftDesignPortfolioBeckettPt-Task8.2-12282015.pdf 12/28/2015
Design document FEEDERBLUFF-DraftDesignPortfolioWaterman-Task 802-12282015.pdf 12/28/2015
Design document FEEDERBLUFF-DraftDesignPortfolioMaylorsPt-Task 8.2-12282015.pdf 12/28/2015
Design document FEEDERBLUFF-DraftDesignPortfolioSeahorseSiesta-Task 8.2-1228.pdf 12/28/2015
Design document FEEDERBLUFF-SeahorseSiesta_Memo&DesignAlts-06252015.pdf 07/01/2015
Final project report Final Report, 14-2196 (accepted 09/14/18 09:33:51).pdf 09/14/2018
Final project report FEEDERBLUFF-FINAL REPORT-05302017.pdf.pdf 05/31/2017
Milestones Planning Milestone Worksheet ESRP14_2196 091014.doc 09/10/2014
Monitoring activity FEEDERBLUFF-monitoringlog-112014.pdf 11/21/2014
Photo Waterman-Before & After.jpg 03/31/2017
Photo Maylor Point Tire Wall.jpg 03/31/2017
Photo SiestaSeahrs.NEcorner.bulkhd.03.14.16.JPG.jpg 03/31/2017
Photo Beckett Point Pile Wall.jpg 03/31/2017
Photo Jim-crowd-feederbluff.jpg 04/01/2015
Photo Feeder Bluff.jpg 08/17/2014
Progress report Progress Report, 14-2196 (accepted 05/09/17 10:34:09).pdf 05/09/2017
Progress report Progress Report 01/10/2017.pdf 01/10/2017
Progress report Progress Report 01/04/2016.pdf 01/04/2016
Progress report FEEDERBLUFF-progressreport-12312015.pdf 12/28/2015
Progress report Progress Report 07/09/2015.pdf 07/09/2015
Progress report FEEDERBLUFF-progressreport-06302015.pdf 07/02/2015
Progress report FEEDERBLUFF-progressreport-033115.pdf 04/02/2015
Project Application Report Application Report, 14-2196P (submitted 08/18/14 01:14:01).pdf 08/18/2014
Project Deliverables Final_FBAR_Presentation_05182018.pdf.pdf 08/21/2018
Project Deliverables FEEDERBLUFF-Appendix A-SiteVisitReports.pdf.pdf 05/30/2017
Project Deliverables FEEDERBLUFF-Ranked Project Sites Map-12192016.pdf 12/19/2016
Project Deliverables FEEDERBLUFF-Groundtruthed Data-12192016.xlsx 12/19/2016
Project Deliverables FEEDERBLUFF-propertytrackingupdate-12282015.pdf 12/28/2015
Project Deliverables FEEDERBLUFF-fall 2015 workshop attendance-12282015.pdf 12/28/2015
Project Deliverables FEEDERBLUFF-Schaetti-Maxwelton-Site-Assess-May2015.pdf 07/02/2015
Project Deliverables FEEDERBLUFF-Workshop deliverables_Whidbey&Seattle-Spring2015.pdf 07/02/2015
Project Deliverables FEEDERBLUFF-propertytrackinglog-06302015.xlsx 07/02/2015
Project Deliverables FEEDERBLUFF-Navy-MaylorPt-site-Assess-Memo-05212015.pdf 07/01/2015
Project Deliverables FEEDERBLUFF-Chetzemoka-Park Site visit memo-04152015.pdf 07/01/2015
Project Deliverables FEEDERBLUFF-Beckett-Pt Site Memo-04152015.pdf 07/01/2015
Project Deliverables FEEDERBLUFF-IslandCtyWorkshopRegistrationSurvey-April2015.pdf 07/01/2015
Project Deliverables FEEDERBluff-SignInSheet_IslandCo_Spring2015.pdf 07/01/2015
Project Deliverables FEEDERBLUFF-FINALrestorationassessment-March2015.pdf 07/01/2015
Project Deliverables FEEDERBLUFF-monitoringlog-DEC2014.pdf 07/01/2015
Project Deliverables propertytrackinglog-033115.xlsx 04/02/2015
Project Deliverables FEEDERBLUFF-workshopadv_and_signin-033115.pdf 04/02/2015
Project Deliverables FEEDERBLUFF-workshoppresentation-March2015.pdf 04/01/2015
Project Deliverables FEEDERBLUFF-interim results analysis report-121914.pdf 03/30/2015
Project Deliverables CGS_NWSF_FB_rest_assessmt_InterimResultsAnalysis12.19.14.pdf 03/30/2015
Scope of work FEEDERBLUFF-projectplan-1121014.pdf 11/21/2014
Visual Scope of Work PS_Armor Removal Assessment.pdf 08/17/2014