Camano Is State Park Tidal Marsh Feasibility
|
Skagit River Sys Cooperative; Camano Is State Park Tidal Marsh Feasibility (#15-1048)
Attachment #180167, DOE_Oblique_CISP_060708_07004
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
This project intends to evaluate potential actions and design alternatives for restoring natural hydrological processes to the unique shoreline land form located at Camano Island State Park. This project's goal will determine the feasibility of restoring natural processes to the site given modern land use constraints. If an action is deemed feasible, we will develop a preliminary design in a manner consistent with natural habitat processes, and the recreational and educational uses of the park envisioned by Washington State Parks staff and citizen user groups. Any restoration outcome would target feeding and rearing habitat improvements for out-migrating juvenile Chinook salmon.
|
General Area:
|
|
Camano Island
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Camano Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Island
|
Sections:
|
|
36
|
Township:
|
|
T31NR02E
|
Coordinates:
|
|
48.12419143 -122.49425543
|
|
|
Worksite Name | Scope of Work | Actual Planning Cost |
Camano Island State Park (#1)
|
Conducting habitat restoration scoping and feasibility studies (B.1.b.8), Cultural resources
|
$74,795
|
| Total | $74,795 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Camano Island State Park (#1)
|
|
Property 1 - Camano Island State Park
|
State Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
|
|
|
Area Encompassed (acres) (B.0.b.1)
|
4.4
|
|
Miles of Stream and/or Shoreline Affected (B.0.b.2)
|
0.10
|
Milestone Name | Target Date | Description |
Project Start
|
12/09/2015
|
|
Progress Report Due
|
06/30/2016
|
|
Annual Project Billing Due
|
07/31/2016
|
|
Progress Report Due
|
12/31/2016
|
|
Data Gathering Started
|
01/31/2017
|
Topography, sediment cores, wetlands, utilities, and infrastructure surveys.
|
Cultural Resources Complete
|
02/28/2017
|
|
RFP Complete/Consultant Hired
|
02/28/2017
|
Coastal Engineer
|
Progress Report Due
|
07/31/2017
|
|
RFP Complete/Consultant Hired
|
10/02/2017
|
Public Outreach/Facilitation
|
Draft Design to RCO
|
03/29/2019
|
Draft feasibility with check in stages of assessment
|
Applied for Permits
|
03/29/2019
|
Permitting agencies will be consulted during feasibility process.
|
Agreement End Date
|
06/30/2019
|
|
Final Design to RCO
|
09/30/2019
|
Final Conceptual Design, as described in RCO-SRFB Manual #18, Appendix D-1.
|
Final Report Due
|
09/30/2019
|
|
Final Billing Due
|
09/30/2019
|
|