Project Snapshot
PRISM Project #15-1049 (Completed)
Iverson Preserve Stakeholder Integration
    Project Details    
Island Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049)

Attachment #179758, iverson site map
Island Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049) Attachment #179758, iverson site map

Island Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049)

Attachment #179758, iverson site map Island Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049)

Attachment #180275, IMG_1742Island Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049)

Attachment #329154, 02-07-18 Interim InspectionIsland Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049)

Attachment #329155, 02-07-18 Interim Inspection 4Island Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049)

Attachment #329156, 02-07-18 Interim Inspection 1Island Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049)

Attachment #329157, 02-07-18 Interim Inspection 3Island Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049)

Attachment #329158, 02-07-18 Interim Inspection 5Island Co. Dept. Natural Res.; Iverson Preserve Stakeholder Integration (#15-1049)

Attachment #329159, 02-07-18 Interim Inspection 2
Project Status:  Closed Completed since 11/19/2018
 
Project Type:  Planning
Project Sponsor:  Island County Department of Natural Resources
Funding Board:  Salmon Recovery Funding Board
              Funding  
Puget Sound Acq. & Restoration: $104,805
Total RCO Grant: $104,805 (85%)
Sponsor Match: $18,495 (15%)
Total Agreement: $123,300 (100%)
              Links
 

    Project Description    
This project will build upon the two previous feasibility studies for the Iverson Marsh (Phillip Williams and Associates, 2001 and Sheldon & Associates, 2001) to further address the feasibility of restoring inter-tidal marsh at Iverson Marsh. The project area is approximately 120 acres and consists of 3,200 linear feet of shoreline with one hundred acres currently diked, drained and farmed for hay. It is located on the western edge of Livingston Bay on Camano Island, and in WRIA 6 High Priority Geographic Area 1 (ICSRP 2005, p. 27).

The 2001 feasibility studies included restoration alternatives and recommended that additional studies ensue to evaluate potential flood hazard risks to neighboring properties from proposed restoration actions. The main goal of this project is to integrate the stakeholder’s concerns into an acceptable restoration alternative. Island County is interested in balancing the community’s concerns with improving habitat for listed species and water quality. Staff will facilitate neighborhood/stakeholder meetings to work with existing plans and information from feasibility studies to inform the landowners to reach a consensus on alternatives to model and evaluate risks, and to explain the site restoration benefits to advance habitat restoration actions at Iverson Preserve.

The completed restoration project would improve feeding and rearing habitat for out-migrating juvenile salmon.

    Project Contacts    
         
Project Sponsor: Island County Department of Natural Resources Lead Entity: Island County Lead Entity
  Project Contact: Lori Clark
l.clark@islandcountywa.gov
(360) 679-7352
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
General Area:   Whidbey Island
County:   Island
Legislative District:   10
Congressional District 2022:   02
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Camano Island
HUC8:   Puget Sound (17110019)
WRIA:   Island
Coordinates:   48.21276243
-122.44746746

    Worksites    
Worksite NameScope of WorkActual Planning Cost
Iverson Marsh (#1) Conducting habitat restoration scoping and feasibility studies (B.1.b.8) $126,327
 Total$126,327
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 120.0
Miles of Stream and/or Shoreline Affected (B.0.b.2) 0.01

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/09/2015
Data Gathering Started 12/09/2015
RFP Complete/Consultant Hired 04/15/2016
Progress Report Due 04/30/2016
Progress Report Due 10/31/2016
Annual Project Billing Due 12/30/2016
Progress Report Due 03/31/2017
Draft Plan to RCO 05/31/2018 Draft Reports, See Manual #18, Appendix D-1, Conceptual Design Deliverables.
Agreement End Date 06/29/2018
Final Plan to RCO 10/31/2018 Final Narrative Report
Final Report Due 10/31/2018
Final Billing Due 10/31/2018


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 15-1049 Project Agreement.pdf 02/22/2016
Agreement attachment Coastal Geologic Contract 07-2016.pdf 10/03/2016
Amendment - State 15-1049 Amend #3 Time Ext.pdf 12/21/2017
Amendment - State 15-1049 Amend #1 Time Ext.pdf 10/06/2016
Applicant Resolution/Authorizations Application Authorization 01-19-16.pdf 01/21/2016
Application Review Report Application Review Report, 15-1049P(compl 08/26/15 14:12:48).pdf 08/26/2015
Billing forms IC 2018 Rates.tif.tif 11/06/2018
Board memo Iverson Newsletter July 2016 Final.pdf 10/03/2016
Cost Estimate SRFB Share Project Budget 01-29-16.xls 01/29/2016
Cost Estimate Iverson Budget_revised 05-05-2014 Corr.docx 11/06/2015
Environmental Site Assessment Report Iverson Preserve Site Mgmt Plan 12-06-11.pdf 04/28/2014
Environmental Site Assessment Report Iverson Study sheldon.pdf 03/18/2014
Environmental Site Assessment Report Flood Study for Restoration Alts 10-15-01.pdf 03/18/2014
Environmental Site Assessment Report Appendix 111201 (2).pdf 03/18/2014
Final project report Final Report, 15-1049 (accepted 11/05/18 10:02:11).pdf 11/05/2018
Final project report Iverson Final Report September 2018.pdf 10/03/2018
Inspection Report Iverson 02-07-18 Interim Inspection Photos.pptx 02/21/2018
Landowner acknowledgement form Landowner Acknowledgement Form _Iverson005.pdf 03/06/2014
Map: Area of Potential Effect (APE) Iverson TSheet.docx 03/17/2014
Map: Planning Area iverson site map.jpg 03/06/2014
Photo 02-07-18 Interim Inspection 2.jpg 02/21/2018
Photo 02-07-18 Interim Inspection 5.jpg 02/21/2018
Photo 02-07-18 Interim Inspection 3.jpg 02/21/2018
Photo 02-07-18 Interim Inspection 1.jpg 02/21/2018
Photo 02-07-18 Interim Inspection 4.jpg 02/21/2018
Photo 02-07-18 Interim Inspection.jpg 02/21/2018
Photo IMG_1742.jpg 03/18/2014
Progress report Progress Report, 15-1049 (accepted 12/21/17 11:02:12).pdf 12/21/2017
Progress report Progress Report, (accepted 03/16/17 08:54:55).pdf 03/16/2017
Progress report Progress Report 10/04/2016.pdf 10/04/2016
Progress report Progress Report 04/01/2016.pdf 04/01/2016
Project Application Report Application Report, 15-1049P (submitted 08/18/15 16:28:41).pdf 08/18/2015
Project Application Report Application Report, 15-1049P (submitted 03/18/15 00:32:51).pdf 03/18/2015
Project Deliverables Iverson-Sed-CGS-Report-AppendicesA-E.pdf.pdf 10/03/2018
Project Deliverables Iverson-Sed-CGS-Report-FINAL-12-15-17.pdf 10/03/2018
Project Deliverables Iverson-Sed-CGS-Report-Figures1-21.pdf.pdf 10/03/2018
Project Deliverables Livingston Bay Report Skillings 12-15-17.pdf 10/03/2018
Project plan document Iverson Task Force Recommendations.docx.docx 12/14/2017
Salmon Project Proposal 2015 Iverson_SRFB Proposal 031715 RCO New_revised 20150604.docx 06/04/2015
SRFB Review Panel Comment Form 15-1049 SRFB RP Comment Form 09-23-15.pdf 11/17/2015
SRFB Review Panel Comment Form 14-1076 SRFB RP Comment Form 10-22-14.pdf 12/22/2014

Back to top Date of last change: 12/05/2024