Project Status:  Closed Completed since 01/09/2018
 
Project Type:  Planning
Project Sponsor:  Kitsap County
Funding Board:  Salmon Recovery Funding Board
              Funding  
Puget Sound Acq. & Restoration: $290,000
Salmon Federal Projects: $50,000
Total RCO Grant: $340,000 (85%)
Sponsor Match: $60,000 (15%)
Total Agreement: $400,000 (100%)
              Links
 

    Project Description    
The proposed project will complete final designs for a road crossing located within Harper Estuary, a pocket estuary in the vicinity of the Harper-Southworth area on the west shores of central Puget Sound. Kitsap County proposes to complete final design for a bridge to replace an undersized culvert under Olympiad Drive, a road crossing intersecting Harper Estuary. The overall goal of this project is to complete a final bridge design that will allow optimal tidal inundation to the south of the estuary and restore ecological functions of the estuarine area. Pocket estuaries are documented to be a vital element in the life cycle of juvenile salmonids including Chum, Coho, and Chinook salmon for rearing, feeding, and protection from predators.

The Washington DOE received funds from the ASARCO settlement for natural resource damage to restore Harper Estuary. The WA Department of Fish and Wildlife is leading the estuary restoration/cleanup component of the project while Kitsap County is leading the design and construction of a bridge to replace the undersized culvert under SE Olympiad Drive. A Type, Size, and Location (TS&L) Report is attached in PRISM. The final designs will align to Manual 18 Appendix D-3, as well as adhere to Kitsap County road standards, and meet WA State Department of Transportation bridge design manual (as adopted by Kitsap County).

    Project Contacts    
         
Project Sponsor: Kitsap County Lead Entity: West Sound Partners for Ecosystem Recovery
 

   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
General Area:   Harper Estuary
County:   Kitsap
Legislative District:   26
Congressional District 2022:   06
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Clovos Passage/Carr Inlet
HUC8:   Puget Sound (17110019)
WRIA:   Kitsap
Coordinates:   47.51680943
-122.51603428

    Worksites    
Worksite NameScope of WorkActual Planning Cost
Harper Estuary (#1) Final design and permitting (B.1.b.11.a RCO) $454,461
 Total$454,461
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Harper Estuary (#1)   Property 1 - SE Olympiad Drive - Kitsap County R/W Local Government
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 9.1

    Project Milestones    
Milestone NameTarget DateDescription
Data Gathering Started 06/30/2015
Project Start 12/09/2015
Cultural Resources Complete 12/31/2015 Assessment Completed
RFP Complete/Consultant Hired 03/30/2016
Progress Report Due 06/30/2016
Preliminary Design to RCO 06/30/2016 Preliminary Design Deliverables per Manual 18 Appendix D-2
Special Conditions Met 06/30/2016 Presentation to the TAG and other stakeholders, incorporate design review comments into the final design report
Applied for Permits 10/01/2016
Progress Report Due 02/01/2017 New PRISM module implemented 1/27/17
Annual Project Billing Due 06/30/2017 Delay in billing from contractor.
Progress Report Due 06/30/2017
Final Design to RCO 12/01/2017 Final Design Deliverables per Manual 18 Appendix D-3--current design at 90%. Waiting to incorporate WDFW changes.
Annual Project Billing Due 12/01/2017 Changed to reflect billing at end of January 2017
Final Report Due 12/31/2017
Agreement End Date 12/31/2017
Final Billing Due 02/28/2018


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 15-1075 Project Agreement.pdf 05/20/2016
Applicant Resolution/Authorizations application authorization 15-1075.pdf 05/12/2016
Application Review Report Application Review Report, 15-1075P(compl 08/24/15 16:51:25).pdf 08/24/2015
Correspondence Harper_Olympiad Drive SKFR correspondence.pdf 08/13/2015
Cost Estimate SE Olympiad Harper Estuary 100perc Cost Estimate.pdf.pdf 12/01/2017
Cost Estimate Cost_Estimate_2.xlsx 08/13/2015
Cost Estimate Cost_Estimate.xlsx 04/01/2015
Design document 01_Harper Estuary Preliminary Geotechnical Report.pdf.pdf 12/01/2017
Design document 02_Harper Estuary Geotechnical Report Addendum for Final Des.pdf 12/01/2017
Design document SE_Olympiad_Bridge_Contract Provisions Kitsap County_100Perc.pdf 12/01/2017
Design document SEOlympiad_100perc_Plan_17_0630.pdf.pdf 12/01/2017
Design document Harper Estuary Preliminary Bridge Design Report_15_1223.pdf 03/01/2016
Easement 15_0630_HarperAltAnalysisMemo.pdf 08/13/2015
Final project report Final Report, 15-1075 (accepted 12/20/17 09:26:16).pdf 12/20/2017
Inspection Report Harper Site Visit 4.21.2015.pptx 04/24/2015
Map: Area of Potential Effect (APE) Harper Estuary Restoration Final Design Project-APE Map.pdf 03/31/2015
Map: Planning Area Harper Ownershiip Exhibit 2015.pdf 08/12/2015
Map: Planning Area Harper Vicinity Map 3.pdf 03/16/2015
Note to file Memo Olympiad Drive.docx 08/13/2015
Note to file Harper_Estuary_MWD_07_23_2015_ver3.pdf 08/12/2015
Photo Eastern shoreline.jpg 03/31/2015
Photo View of Olympiad Drive from south.jpg 03/31/2015
Photo Culvert.jpg 03/31/2015
Photo Brick Pile.jpg 03/31/2015
Photo Harper Aerial.jpg 03/16/2015
Progress report Progress Report, 15-1075 (accepted 06/27/17 16:21:36).pdf 06/27/2017
Progress report Progress Report, 15-1075 (accepted 03/29/17 11:04:08).pdf 03/29/2017
Progress report Progress Report 01/19/2017.pdf 01/19/2017
Project Application Report Application Report, 15-1075P (submitted 08/13/15 16:15:00).pdf 08/13/2015
Salmon Project Proposal Project Proposal 2.docx 08/13/2015
Scope of work Preliminary Design Scope of Work.pdf 05/13/2015
SRFB Review Panel Comment Form 15-1075 Harpers Estuary Restoration Review Panel Comments.pdf 01/29/2016
Visuals Harper Estuary Presentation 5-12-15 Final.pptx 05/13/2015