Crescent Creek Culvert Feasibility Study
|
    Funding |
  |
|
    Links |
  |
|
|
South Puget Sound Salmon Enhancement Group will complete a feasibility study to replace the culvert at Crescent Creek, a direct tributary to Puget Sound flowing approximately three miles from Crescent Lake to Gig Harbor. Crescent Creek enters Puget Sound in the northeast corner of Gig Harbor through an undersized culvert under 96th Street NW/Vernhardson Street. Crescent Creek supports fall Chinook salmon, winter steelhead, fall chum and Coho. The culvert restricts tidal flow, inhibits fish passage at some tidal elevations, and fragments the estuary. This project would complete a feasibility study to evaluate fish passage, tidal hydrology, and estuarine function to prescribe a design for a new structure to restore fish passage and tidal hydrology. This project was identified as a priority by the WRIA 15 Prioritization and Development project (06-2271) and would build upon restoration work recently complete on the other side of the Harbor on Donkey Creek.
|
General Area:
|
|
Gig Harbor
|
County:
|
|
Pierce
|
Legislative District:
|
|
26
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Clovos Passage/Carr Inlet
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kitsap
|
Sections:
|
|
32
|
Township:
|
|
T22NR02E
|
Coordinates:
|
|
47.34548342 -122.58297924
|
|
|
Worksite Name | Scope of Work | Actual Planning Cost |
Crescent Creek Estuary (#1)
|
Conducting habitat restoration scoping and feasibility studies (B.1.b.8), Cultural resources
|
$50,571
|
| Total | $50,571 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Crescent Creek Estuary (#1)
|
|
Property 1 - Crecent Creek Park
|
Local Government
|
Crescent Creek Estuary (#1)
|
|
Property 2 - DNR State Owned Aquatic Lands
|
State Government
|
Crescent Creek Estuary (#1)
|
|
Property 3 - 96th Street NW Gig Harbor
|
Local Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
|
|
|
Area Encompassed (acres) (B.0.b.1)
|
2.5
|
|
Miles of Stream and/or Shoreline Affected (B.0.b.2)
|
0.10
|
Milestone Name | Target Date | Description |
Project Start
|
12/09/2015
|
|
Data Gathering Started
|
04/01/2016
|
|
RFP Complete/Consultant Hired
|
06/30/2016
|
|
Progress Report Due
|
06/30/2016
|
|
Annual Project Billing Due
|
07/31/2016
|
|
Cultural Resources Complete
|
11/01/2016
|
Monitoring required of GDA as described in PRISM attachments
|
Progress Report Due
|
12/01/2016
|
|
Draft Plan to RCO
|
06/05/2017
|
Alternatives Assessment
|
Progress Report Due
|
06/05/2017
|
|
Draft Design to RCO
|
06/05/2017
|
Conceptual Designs
|
Annual Project Billing Due
|
07/31/2017
|
|
Progress Report Due
|
01/24/2018
|
|
Progress Report Due
|
03/31/2018
|
|
Special Conditions Met
|
06/15/2018
|
DNR Coordination on Reviewing Alternatives; Progress has been delayed due to staff changes and a lack of match. We will seek this approval.
|
Final Plan to RCO
|
07/31/2018
|
Feasiblity Study per Manual 18 Appendix D-1 + Conceptual Designs for preferred alternative
|
Final Report Due
|
07/31/2018
|
|
Agreement End Date
|
07/31/2018
|
All expenses must be incurred by this date.
|
Final Billing Due
|
08/31/2018
|
|