Lower Quinault River Invasive Plant Control Phase4
|
Quinault Indian Nation; Lower Quinault River Invasive Plant Control Phase4 (#15-1103)
Attachment #218309, RCG and knotweed[1]
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The Quinault Indian Nation Division of Natural Resources will conduct a one year of survey and treatment of invasive knotweed plant species in the lower Quinault River floodplain. The project area is located in the lower Quinault River floodplain from river mile 18.0 to 20.3 (2.3 miles). The restoration funding will allow the sponsor to continue its invasive plant treatment and control program in the lower Quinault River watershed. The priority Quinault River salmon species benefitting from improved floodplain forest conditions and aquatic habitats include Chinook, Chum, Coho, Sockeye, Steelhead, and Cutthroat.
|
General Area:
|
|
Lower Quinault River, Grays Harbor County, WA
|
County:
|
|
Grays Harbor
|
Legislative District:
|
|
24
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Washington Coast
|
Watershed Administrative Unit:
|
|
Cook-Elk
|
HUC8:
|
|
Queets-Quinault (17100102)
|
WRIA:
|
|
Queets - Quinault
|
Sections:
|
|
23
|
Township:
|
|
T22NR11W
|
Coordinates:
|
|
47.37685125 -124.05162624
|
|
|
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Lower Quinault River Floodplain (#1)
|
|
Property 1 - Quinault Indian Reservation
|
Tribal Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Riparian Habitat Project |
Riparian Plant removal / control (C.5.h.1) |
|
Acres of riparian treated for plant removal/control (C.5.h.3)
|
462.5
|
|
Miles of streambank treated for plant removal/control (C.5.h.4)
|
3.50
|
Milestone Name | Target Date | Description |
Project Start
|
12/09/2015
|
|
Preliminary Design to RCO
|
12/09/2015
|
|
Landowner Agreement to RCO
|
01/30/2016
|
in the form of basic entry permission form. QIN will keep signed forms on file.
|
Bid Awarded/Contractor Hired
|
02/22/2016
|
|
Applied for Permits
|
03/15/2016
|
|
Permits Complete
|
04/15/2016
|
|
Progress Report Due
|
06/01/2016
|
|
Restoration Started
|
06/01/2016
|
|
Annual Project Billing Due
|
06/30/2016
|
|
Restoration Complete
|
09/30/2016
|
|
Progress Report Due
|
09/30/2016
|
|
Stewardship Plan to RCO
|
12/01/2016
|
|
Final Billing Due
|
12/01/2016
|
|
Final Report Due
|
12/31/2016
|
|
Agreement End Date
|
12/31/2016
|
|