Maylor Pt Armoring Removal
|
NW Straits Marine Cons Found; Maylor Pt Armoring Removal (#16-1307)
Attachment #253100, Maylor Point_Tires and Posts
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
Remove 1,500 feet of varied shore armor treatments from the toe of a high feeder bluff at Maylor's Point, Naval Air Station Whidbey in Island County. The armor includes 185 treated posts, 165 plank, and 1300 tires, 10,000 square feet of concrete bags, and over 16,000 square feet of angular rock.
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Whidbey Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Island
|
Coordinates:
|
|
48.26844341 -122.62745147
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Maylor Point NAS Whidbey (#1)
|
Agency Indirect, Architectural & Engineering (A&E), Shoreline armor removal or modification (C.9.k.1)
|
$127,977
|
| Total | $127,977 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Maylor Point NAS Whidbey (#1)
|
|
Property 1 - NAS Whidbey
|
Federal Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Estuarine / Nearshore Project |
Shoreline armor removal or modification (C.9.k.1) |
|
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
|
0.31
|
|
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
|
1.3
|
Milestone Name | Target Date | Description |
Project Start
|
01/19/2018
|
|
Cultural Resources Complete
|
06/01/2018
|
|
Bid Awarded/Contractor Hired
|
07/01/2018
|
|
Annual Project Billing Due
|
07/31/2018
|
|
Restoration Started
|
09/01/2018
|
|
Progress Report Due
|
10/31/2018
|
|
Landowner Agreement to RCO
|
12/03/2018
|
|
Restoration Complete
|
12/31/2018
|
|
Final Design to RCO
|
03/30/2019
|
As-built drawings, per Manual 18, Appendix D-4.
|
Agreement End Date
|
06/30/2020
|
|
RCO Final Inspection
|
09/30/2020
|
|
Final Report Due
|
09/30/2020
|
|
Final Billing Due
|
09/30/2020
|
|