Skip to main content
Save as PDF
Washington State Recreation and Conservation Office
Project Snapshot
PRISM Project #16-1428 (Completed)
Cornet Bay Riparian Planting Stewardship
    Project Details    
NW Straits Marine Cons Found; Cornet Bay Riparian Planting Stewardship (#16-1428)

Attachment #253244, CB1_Post-construction_planting area_12092015
NW Straits Marine Cons Found; Cornet Bay Riparian Planting Stewardship (#16-1428) Attachment #253244, CB1_Post-construction_planting area_12092015

NW Straits Marine Cons Found; Cornet Bay Riparian Planting Stewardship (#16-1428)

Attachment #253244, CB1_Post-construction_planting area_12092015 NW Straits Marine Cons Found; Cornet Bay Riparian Planting Stewardship (#16-1428)

Attachment #253245, Area 4_toward shelter_02172015 (2)NW Straits Marine Cons Found; Cornet Bay Riparian Planting Stewardship (#16-1428)

Attachment #279411, 04-06-16 Early Application Site VisitNW Straits Marine Cons Found; Cornet Bay Riparian Planting Stewardship (#16-1428)

Attachment #279412, 04-07-16 Early Application Site Visit 1NW Straits Marine Cons Found; Cornet Bay Riparian Planting Stewardship (#16-1428)

Attachment #279413, 04-07-16 Early Application Site Visit 2NW Straits Marine Cons Found; Cornet Bay Riparian Planting Stewardship (#16-1428)

Attachment #279414, 04-07-16 Early Application Site Visit 3NW Straits Marine Cons Found; Cornet Bay Riparian Planting Stewardship (#16-1428)

Attachment #279415, 04-07-16 Early Application Site Visit 4
Project Status:  Closed Completed since 10/14/2021
 
Project Type:  Restoration
Project Sponsor:  Northwest Straits Marine Conservation Foundation
Funding Board:  Salmon Recovery Funding Board
              Funding  
Puget Sound Acq. & Restoration: $25,756
Total RCO Grant: $25,756 (83%)
Sponsor Match: $5,355 (17%)
Total Agreement: $31,111 (100%)
              Links
 

    Project Description    
Continue stewardship of riparian plantings throughout all areas of the restoration site. Maintenance will include periodic weeding, replacement of unsuccessful plants where needed, in-filling with additional plants, as well as providing browse protection to reduce mortality rates of new plants. Summer watering will be included for most recent planting locations. Volunteers and contractors will monitor success of plants and will report on completed activities. Cost estimate covers two years of planting, maintenance, and monitoring.

    Project Contacts    
         
Project Sponsor: Northwest Straits Marine Conservation Foundation Lead Entity: Island County Lead Entity
  Project Contact: Lisa Kaufman
kaufman@nwstraitsfoundation.org
(360) 393-6948
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
County:   Island
Legislative District:   10
Congressional District 2022:   02
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Whidbey Island
HUC8:   Puget Sound (17110019)
WRIA:   Island
Coordinates:   48.39744241
-122.62740950

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Cornet Bay Day Use Area (#1) Agency Indirect, Architectural & Engineering (A&E), Estuarine planting or native plant establishment (C.9.r.1) $31,361
 Total$31,361
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Cornet Bay Day Use Area (#1)   Property 1 - Cornet Bay Day Use Area - Deception Pass State Government
   Total
Amounts may not be complete

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 01/19/2018
Cultural Resources Complete 01/19/2018 Exempt per RCO-DAHP programmatic agreement - restoring previously disturbed habitat area.
Bid Awarded/Contractor Hired 06/04/2018
Restoration Started 06/11/2018
Annual Project Billing Due 07/31/2018
Progress Report Due 07/31/2018
Landowner Agreement to RCO 08/30/2018
Progress Report Due 01/31/2019
Annual Project Billing Due 07/31/2019
Progress Report Due 07/31/2019
Progress Report Due 01/31/2020
Progress Report Due 07/31/2020
Annual Project Billing Due 01/31/2021
Progress Report Due 01/31/2021
Restoration Complete 06/01/2021
RCO Final Inspection 06/15/2021
Agreement End Date 06/30/2021
Final Report Due 08/31/2021
Final Design to RCO 08/31/2021 Final planting plan.
Final Billing Due 08/31/2021


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 16-1428 Agreement.pdf 03/22/2018
Applicant Resolution/Authorizations Appendix_J_Application_Auth_Form_Cornet Bay_16-1428.pdf 03/15/2016
Application Review Report Application Review Report, 16-1428R(compl 08/09/16 11:37:53).pdf 08/09/2016
Billing forms 201908 P&L PSARCB.xlsx.xlsx 10/12/2019
Cost Estimate SRFB_Cost_Estimate_CornetBay_16-1428_FINAL.xlsx 06/02/2016
Design document Cornet Bay_Planting Plans.pdf 06/02/2016
Design document planting plan sheet with gravel path.pdf 03/15/2016
Final project report Final Report, 16-1428 (accepted 09/09/21 10:06:34).pdf 09/09/2021
Inspection Report Inspection Report, #836 (Submitted 09/16/16 09:05:49).pdf 09/16/2016
Map: Restoration Worksite Cornet Bay_16-1428_Workplan Map.pdf 06/02/2016
Map: Restoration Worksite CB_Site Map.pdf 03/15/2016
Monitoring activity Veg Monitoring Report_2015.pdf 03/15/2016
Photo Area4_June2019.jpg.jpg 09/08/2021
Photo Area1_June2019.jpg.jpg 09/08/2021
Photo 52362A67-EB49-42E3-9E11-1157B3982D5E.jpeg.jpeg 09/08/2021
Photo AE943084-4BD7-4C65-9298-1356D5BDF729.jpeg.jpeg 09/08/2021
Photo IMG_20191019_114734833_HDR.jpg.jpg 09/08/2021
Photo IMG_20191019_114813892_HDR.jpg.jpg 09/08/2021
Photo IMG_20191019_092820738_HDR.jpg.jpg 09/08/2021
Photo Area1_06112019.jpg.jpg 10/14/2019
Photo 04-07-16 Early Application Site Visit 4.jpg 09/16/2016
Photo 04-07-16 Early Application Site Visit 3.jpg 09/16/2016
Photo 04-07-16 Early Application Site Visit 2.jpg 09/16/2016
Photo 04-07-16 Early Application Site Visit 1.jpg 09/16/2016
Photo 04-06-16 Early Application Site Visit.jpg 09/16/2016
Photo Area 4_toward shelter_02172015 (2).jpg 03/15/2016
Photo CB1_Post-construction_planting area_12092015.jpg 03/15/2016
Progress report Progress Report, 16-1428 (accepted 01/05/21 10:00:34).pdf 01/05/2021
Progress report Progress Report, 16-1428 (accepted 07/08/20 07:38:12).pdf 07/08/2020
Progress report Progress Report, 16-1428 (accepted 01/07/20 15:14:23).pdf 01/07/2020
Progress report Progress Report, 16-1428 (accepted 10/14/19 16:18:05).pdf 10/14/2019
Progress report Progress Report, 16-1428 (accepted 01/03/19 18:16:49).pdf 01/03/2019
Progress report Progress Report, 16-1428 (accepted 08/03/18 08:16:11).pdf 08/03/2018
Project Application Report Application Report, 16-1428R (submitted 03/15/16 13:20:57).pdf 03/15/2016
Salmon Project Proposal Appendix_C_RestAcqCombProposal_CB Planting_FINAL.pdf 06/02/2016
SRFB Review Panel Comment Form Final SRFB Review Panel Comment Form.pdf 11/01/2016

Back to top Date of last change: 12/05/2024