Wild Fish Conservancy; Gig Harbor Peninsula Watertype Assessment (#16-1599)
Attachment #265294, Pierce_proposal extent
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
Wild Fish Conservancy (WFC) will groundtruth, and correct water type classifications, in a minimum of six watersheds (approx. 90 mi) that drain the Gig Harbor Peninsula - including four with Critical Habitat for Puget Sound Steelhead (NOAA 2016) - using state-established protocols. Watersheds include Purdy, Crescent, North, McCormick, Goodnough, and Artondale Creeks. The assessment will provide data to ensure informed and responsible management of these watersheds. Additionally, WFC will fill critical data gaps on ESA-listed fish species composition and distribution via field observations and use of environmental DNA (eDNA) in watersheds prioritized with assistance from the West Sound Lead Entity Technical Advisory Group. WFC will identify and describe the five highest priority habitat restoration projects encountered during the assessment, and work with project sponsors to develop and implement identified projects in subsequent SRFB rounds. WFC will also provide the water typing results in an interactive web map, and coordinate with cities and counties to ensure the updated fish distribution information is incorporated in their planning processes.
|
General Area:
|
|
Gig Harbor Peninsula
|
County:
|
|
Pierce
|
Legislative District:
|
|
26
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Clovos Passage/Carr Inlet
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kitsap
|
Sections:
|
|
24
|
Township:
|
|
T21NR01E
|
Coordinates:
|
|
47.30066142 -122.61909123
|
|
|
Worksite Name | Scope of Work | Actual Planning Cost |
Gig Harbor Peninsula (#1)
|
Agency Indirect, Habitat surveys (B.2.d), Instream survey (B.2.c)
|
$195,000
|
| Total | $195,000 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Gig Harbor Peninsula (#1)
|
|
Property 1 - Purdy Creek watershed
|
Private
|
Gig Harbor Peninsula (#1)
|
|
Property 2 - Crescent Creek watershed
|
Private
|
Gig Harbor Peninsula (#1)
|
|
Property 3 - North Creek watershed
|
Private
|
Gig Harbor Peninsula (#1)
|
|
Property 4 - McCormick Creek watershed
|
Private
|
Gig Harbor Peninsula (#1)
|
|
Property 5 - Goodnough Creek watershed
|
Private
|
Gig Harbor Peninsula (#1)
|
|
Property 6 - Artondale Creek watershed
|
Private
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
|
|
|
Area Encompassed (acres) (B.0.b.1)
|
66.0
|
Salmonid Habitat Assessment / Inventory |
Habitat surveys (B.2.d) |
|
Acres of habitat assessed (B.2.d.2)
|
66.0
|
Instream survey (B.2.c) |
|
Stream Miles Assessed (B.2.c.2)
|
14.00
|
|
Stream miles assessed that contained salmonids (B.2.c.3)
|
13.00
|
|
Stream Miles Assessed That Needed Restoration (B.2.c.4)
|
5.00
|
|
Stream Miles Assessed For Regulatory Actions (B.2.c.5)
|
14.00
|
|
Number of fish passage impediments identified (B.2.c.6)
|
163
|
|
|
|
Miles of Stream and/or Shoreline Affected (B.0.b.2)
|
110.00
|
Milestone Name | Target Date | Description |
Project Start
|
12/08/2016
|
|
Data Gathering Started
|
12/08/2016
|
Eligible pre-agreement cost per Manual 5
|
Applied for Permits
|
01/30/2017
|
WDFW Science Collection Permit
|
Special Conditions Met
|
03/27/2017
|
No special conditions for this project.
|
Cultural Resources Complete
|
03/27/2017
|
Will complete if ground disturbing work occurs.
|
Progress Report Due
|
04/03/2017
|
|
RFP Complete/Consultant Hired
|
06/30/2017
|
|
Annual Project Billing Due
|
06/30/2017
|
|
Draft Design to RCO
|
07/31/2017
|
|
Draft Plan to RCO
|
07/31/2017
|
|
Preliminary Design to RCO
|
07/31/2017
|
Not applicable
|
Progress Report Due
|
10/02/2017
|
|
Annual Project Billing Due
|
10/31/2017
|
|
Permits Complete
|
01/31/2018
|
Attach to PRISM when complete.
|
Progress Report Due
|
04/02/2018
|
|
Annual Project Billing Due
|
06/30/2018
|
|
Progress Report Due
|
10/01/2018
|
|
Annual Project Billing Due
|
10/31/2018
|
|
Progress Report Due
|
04/30/2019
|
|
Annual Project Billing Due
|
06/30/2019
|
|
Progress Report Due
|
10/01/2019
|
|
Final Plan to RCO
|
03/31/2020
|
Provide summary of completed work and identify & describe 5 highest priority habitat restoration and protection projects encountered during the assessment.
|
Final Report Due
|
03/31/2020
|
|
Agreement End Date
|
03/31/2020
|
Project CLOSING. All expenditures must be prior to this date.
|
Final Billing Due
|
05/15/2020
|
Provide your final invoice and report within 60 days of Agreement End Date.
|