Barnum Point Phase 1 - East Tract Acquisition
|
Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition (#16-2316)
Attachment #252746, Barnum Point Core Bluffs
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The Whidbey Camano Land Trust will acquire 37 acres (17 of riparian/upland and 20 of tidelands), known as the East Tract Phase 1, at Barnum Point, on Camano Island. This initial phase is part of a three phase acquisition to acquire and protect the entire Barnum Point complex, totaling 102 acres. After acquisition and stewardship activies, the property will be transfered to Island County to expand their existing Barnum Point county park. The land trust and the county are pursuing multiple grant applications for Phases 2 and 3 within the Recreation and Conservation Office (RCO). This East Tract Phase 1 agreement is separated from the original three phase "parent" SRFB grant application (#16-1429) for administrative purposes. As the land trust and county secure additional grant funds for the next two phases, then said funds will be amended into this agreement with the additional parcels, or amended into one of the other RCO applications being pursued (ALEA, WWRP or LWCF).
|
General Area:
|
|
West Camano Island
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Camano Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Island
|
Sections:
|
|
05
|
Township:
|
|
T31NR03E
|
Coordinates:
|
|
48.19778343 -122.45458845
|
|
|
Worksite Name | Scope of Work |
Barnum Point (#1)
|
Appraisal, Appraisal Review, Closing, Recording, Taxes, Title, Demolition, Land, Stewardship plan
|
| |
Amounts may not be complete
Worksite Name | | Property Name | | Actual Acquisition Acres | Actual Acquisition Cost |
Barnum Point (#1)
|
|
Property 1 - Private Landowner
|
|
37.00
|
$967,007
|
| | | Total | 37.00 | $967,007 |
Amounts may not be complete
Milestone Name | Target Date | Description |
Order Appraisal(s)
|
03/03/2016
|
|
Order Appraisal Review(s)
|
07/29/2016
|
|
Purchase Agreement Signed
|
08/04/2016
|
|
Project Start
|
08/11/2016
|
|
Environmental Assess Complete
|
10/01/2016
|
|
Acquisition Closing
|
10/14/2016
|
|
Progress Report Due
|
01/15/2017
|
|
Cultural Resources Complete
|
02/15/2017
|
|
Recorded Acq Documents to RCO
|
03/01/2017
|
|
Demolition Complete
|
06/01/2017
|
|
Progress Report Due
|
07/15/2017
|
|
Annual Project Billing Due
|
07/31/2017
|
|
Progress Report Due
|
01/15/2018
|
|
Recorded Land Survey to RCO
|
02/28/2018
|
|
Noxious Weed Control Complete
|
04/01/2018
|
|
Fencing Complete
|
04/01/2018
|
|
Funding Acknowl Sign Posted
|
04/01/2018
|
|
Stewardship Plan to RCO
|
04/01/2018
|
|
Agreement End Date
|
06/30/2018
|
|
RCO Final Inspection
|
07/01/2018
|
|
Final Report Due
|
09/30/2018
|
|
Final Billing Due
|
09/30/2018
|
|