PRISM Project #16-2316 (Completed)
Barnum Point Phase 1 - East Tract Acquisition
    Project Details    
Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #252746, Barnum Point Core Bluffs
Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition (#16-2316) Attachment #252746, Barnum Point Core Bluffs

Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #252746, Barnum Point Core Bluffs Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #252748, Barnum Point West Mouth of Triangle CoveWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #252749, Barnum Point WestWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #252751, Barnum Point West and Core TidelandsWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #252753, Barnum Point East TidelandsWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #252754, Barnum Point East BluffsWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #266552, East Tract BluffsWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #266553, Est Tract - Mouth of Triangle CoveWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #266554, Core and West Tract BluffsWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #279355, 04-07-16 Early Application Site VisitWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #279356, 04-07-16 Early Application Site Visit 1Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #279357, 04-07-16 Early Application Site Visit 2Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #279358, 04-07-16 Early Application Site Visit 3Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

03/21/2017, Attachment #298229, Barnum East Tract House - Barge_ClintonWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

03/21/2017, Attachment #298230, Barnum East Tract house on the barge-looking through foundatWhidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #375167, Barnum House 03-03-18Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #375168, Recycling House Materials 03-03-18Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #375169, View from Barnum 03-03-18Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #375170, Wetland Boardwalk 03-03-18Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #375171, Forest Canopy 03-03-18Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #375172, Barnum Ridge View 03-03-18Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #375173, Barnum Overlook Platform 03-03-18Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #375174, House Demo 1 03-03-18Whidbey Camano Land Trust; Barnum Point Phase 1 - East Tract Acquisition  (#16-2316)

Attachment #375175, House Demo 03-03-18
Project Status:  Closed Completed since 05/17/2018
 
Project Type:  Acquisition
Project Sponsor:  Whidbey Camano Land Trust
Funding Board:  Salmon Recovery Funding Board
              Funding  
Puget Sound Acq. & Restoration: $646,536
Salmon State Projects: $175,144
Total RCO Grant: $821,680 (85%)
Sponsor Match: $145,004 (15%)
Total Agreement: $966,684 (100%)
              Links
 

    Project Description    
The Whidbey Camano Land Trust will acquire 37 acres (17 of riparian/upland and 20 of tidelands), known as the East Tract Phase 1, at Barnum Point, on Camano Island. This initial phase is part of a three phase acquisition to acquire and protect the entire Barnum Point complex, totaling 102 acres. After acquisition and stewardship activies, the property will be transfered to Island County to expand their existing Barnum Point county park.
The land trust and the county are pursuing multiple grant applications for Phases 2 and 3 within the Recreation and Conservation Office (RCO). This East Tract Phase 1 agreement is separated from the original three phase "parent" SRFB grant application (#16-1429) for administrative purposes. As the land trust and county secure additional grant funds for the next two phases, then said funds will be amended into this agreement with the additional parcels, or amended into one of the other RCO applications being pursued (ALEA, WWRP or LWCF).

    Project Contacts    
         
Project Sponsor: Whidbey Camano Land Trust Lead Entity: Island County Lead Entity
  Project Contact: Ryan Elting
ryan@wclt.org
(360) 222-3272
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
General Area:   West Camano Island
County:   Island
Legislative District:   10
Congressional District 2022:   02
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Camano Island
HUC8:   Puget Sound (17110019)
WRIA:   Island
Sections:   05
Township:   T31NR03E
Coordinates:   48.19778343
-122.45458845

    Worksites    
Worksite NameScope of Work
Barnum Point (#1) Appraisal, Appraisal Review, Closing, Recording, Taxes, Title, Demolition, Land, Stewardship plan
  
Amounts may not be complete

    Properties    
Worksite Name Property Name Actual Acquisition
Acres
Actual Acquisition
Cost
Barnum Point (#1)   Property 1 - Private Landowner 37.00 $967,007
   Total37.00$967,007
Amounts may not be complete

    Project Milestones    
Milestone NameTarget DateDescription
Order Appraisal(s) 03/03/2016
Order Appraisal Review(s) 07/29/2016
Purchase Agreement Signed 08/04/2016
Project Start 08/11/2016
Environmental Assess Complete 10/01/2016
Acquisition Closing 10/14/2016
Progress Report Due 01/15/2017
Cultural Resources Complete 02/15/2017
Recorded Acq Documents to RCO 03/01/2017
Demolition Complete 06/01/2017
Progress Report Due 07/15/2017
Annual Project Billing Due 07/31/2017
Progress Report Due 01/15/2018
Recorded Land Survey to RCO 02/28/2018
Noxious Weed Control Complete 04/01/2018
Fencing Complete 04/01/2018
Funding Acknowl Sign Posted 04/01/2018
Stewardship Plan to RCO 04/01/2018
Agreement End Date 06/30/2018
RCO Final Inspection 07/01/2018
Final Report Due 09/30/2018
Final Billing Due 09/30/2018


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 16-2316 Project Agreement.pdf 09/27/2016
Amendment - State 16-2316 Amend #5 Cost Change.pdf 02/20/2018
Amendment - State 16-2316 Amend #4 Project Sponsor Change.pdf 08/22/2017
Amendment - State 16-2316 Amend #3 Cost Change.pdf 05/17/2017
Amendment - State 16-2316 Amend #2 Cost Change.pdf 05/03/2017
Amendment - State 16-2316 Amend #1 Cost Change.pdf 01/25/2017
Applicant Resolution/Authorizations Barnum Point SRFB Resolution.pdf 03/14/2016
Application Review Report Application Review Report, 16-2316A(compl 09/13/16 10:20:55).pdf 09/13/2016
Assignment of rights Barnum Point Recorded AOR 03-28-13.pdf 09/28/2016
Cost Estimate Cost Estimate_7-11-16_Barnum 16-1429 FINAL.xls 07/11/2016
Deed EastTract Deed to Island County 01-31-18.pdf 05/17/2018
Deed Barnum Pt East SWD 10-17-16.pdf 01/19/2017
Deed of right Recorded_Salmon DOR 01-30-18.pdf 02/06/2018
Easement Barnum Point Assignment of Easem 02-28-13.pdf 09/28/2016
Easement BARNUM PT- Recorded CE 08-30-2012.pdf 09/28/2016
Environmental Site Assessment Report Port Susan Beach Seine Final June 2009.pdf 04/11/2016
Final project report Final Report, 16-2316 (accepted 05/17/18 19:51:54).pdf 05/17/2018
Hazardous Substance Certification Form Hazard Subst Certifi Form 05-17-18.pdf 05/17/2018
Hazardous Substance Certification Form REPORT - Phase I ESA for Stay Property Camano Island - Copy.pdf 09/29/2016
Inspection Report Inspection Report, #1671 (Accepted 01/03/19 10:18:53).pdf 01/03/2019
Inspection Report Inspection Report, #846 (Submitted 10/07/16 10:53:32).pdf 10/07/2016
Map: Parcel map Barnum_Parcels.pdf 04/29/2016
Photo House Demo 03-03-18.jpg 01/03/2019
Photo House Demo 1 03-03-18.jpg 01/03/2019
Photo Barnum Overlook Platform 03-03-18.jpg 01/03/2019
Photo Barnum Ridge View 03-03-18.jpg 01/03/2019
Photo Forest Canopy 03-03-18.jpg 01/03/2019
Photo Wetland Boardwalk 03-03-18.jpg 01/03/2019
Photo View from Barnum 03-03-18.jpg 01/03/2019
Photo Recycling House Materials 03-03-18.jpg 01/03/2019
Photo Barnum House 03-03-18.jpg 01/03/2019
Photo Barnum East Tract house on the barge-looking through foundat.jpg 03/22/2017
Photo Barnum East Tract House - Barge_Clinton.jpg 03/22/2017
Photo 04-07-16 Early Application Site Visit 3.jpg 09/16/2016
Photo 04-07-16 Early Application Site Visit 2.jpg 09/16/2016
Photo 04-07-16 Early Application Site Visit 1.jpg 09/16/2016
Photo 04-07-16 Early Application Site Visit.jpg 09/16/2016
Photo Core and West Tract Bluffs.jpg 06/02/2016
Photo Est Tract - Mouth of Triangle Cove.jpg 06/02/2016
Photo East Tract Bluffs.jpg 06/02/2016
Photo Barnum Point East Bluffs.jpg 03/09/2016
Photo Barnum Point East Tidelands.jpg 03/09/2016
Photo Barnum Point West and Core Tidelands.jpg 03/09/2016
Photo Barnum Point West.jpg 03/09/2016
Photo Barnum Point West Mouth of Triangle Cove.jpg 03/09/2016
Photo Barnum Point Core Bluffs.jpg 03/09/2016
Progress report Progress Report, 16-2316 (accepted 01/29/18 10:22:32).pdf 01/29/2018
Progress report Progress Report, 16-2316 (accepted 07/27/17 13:43:54).pdf 07/27/2017
Progress report Progress Report 01/18/2017.pdf 01/18/2017
Project Application Report Application Report, 16-2316A (submitted 09/13/16 10:19:55).pdf 09/13/2016
Salmon Project Proposal Barnum Point_AcqProposal_FINAL.docx 06/02/2016
SRFB Review Panel Comment Form Final SRFB Review Panel Comment Form.pdf 02/15/2018
Stewardship plan Barnum Point Management Plan_1.24.18.pdf.pdf 05/17/2018