Skip to main content
Save as PDF
Washington State Recreation and Conservation Office
Project Snapshot
PRISM Project #18-1378 (Other)
E Camano Rd (#1300) Fish Passage Prelim Design
    Project Details    
Project Status:  Merged since 07/24/2019
 
Project Type:  Planning
Project Sponsor:  Island County
Funding Board:  Salmon Recovery Funding Board
              Funding  
Puget Sound Acq. & Restoration: $56,309
Total RCO Grant: $56,309 (85%)
Sponsor Match: $9,937 (15%)
Total Agreement: $66,246 (100%)
              Links
 

    Project Description    
Island County Public Works proposes to use grant funding for preliminary design for the correction of the fish passage barriers at East Camano Drive Culverts #1300 and #1301 (WDFW site ID 1320092) and the removal of the culvert associated with the “beaver deceiver” (WDFW site ID 933079), 50 feet upstream of the main barriers. This will improve fish access for adult and juvenile chum, coho, cutthroat, and resident trout to the Kristoferson Creek Basin above North East Camano Drive.

    Project Contacts    
         
Project Sponsor: Island County Lead Entity: Island County Lead Entity
  Project Contact: Kyle Carlson

   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
County:   Island
Legislative District:   10
Congressional District 2022:   02
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Camano Island
HUC8:   Puget Sound (17110019)
WRIA:   Island
Sections:   31
Township:   T32NR03E
Coordinates:   48.21705943
-122.47762146

    Worksites    
Worksite NameScope of WorkProposed Planning Cost
N East Camano DR & Can Ku Rd (#1) Agency Indirect, Preliminary design (B.1.b.11.a RCO) $66,246
 Total$66,246
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
N East Camano DR & Can Ku Rd (#1)   Property 1 - Island County - N East Camano Dr Local Government
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricEstimated

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 0.1
Miles of Stream and/or Shoreline Affected (B.0.b.2) 0.04

    Project Permits    
Permit TypeApplied
Date
Received
Date
Expiration
Date
Permit Number
Hydraulics Project Approval [HPA]

    Project Milestones    
Milestone NameTarget DateDescription
Project Start
Data Gathering Started
Draft Design to RCO
Draft Plan to RCO
RFP Complete/Consultant Hired
Progress Report Due
Preliminary Design to RCO
Annual Project Billing Due
Special Conditions Met
Applied for Permits
Cultural Resources Complete Planning with no Ground Disturbance: No Further CR Required at this time. Future ground disturbing activities will likely require a survey.
Final Design to RCO
Permits Complete
Final Plan to RCO
Final Report Due
Agreement End Date
Final Billing Due
Other

NOTE: This data is subject to change.

    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Applicant Resolution/Authorizations Application/Agreement Authoriz Resolution .pdf 04/09/2018
Application Review Report Application Review Report, 18-1378P(compl 08/07/18 11:44:16).pdf 08/07/2018
Cost Estimate 18-1378 #1300 East Camano budget.xlsx.XLSX.xlsx 06/11/2018
Map: Multi-site and geographic envelope Island County_#1300 Large Scale Map.pdf.pdf 04/09/2018
Map: Multi-site and geographic envelope Island County_#1300 Area Map.pdf.pdf 04/09/2018
Map: Planning Area Island County_#1300 coordination map.pdf.pdf 06/04/2018
Map: Restoration Worksite Island County_#1300 Pond Map.pdf 04/09/2018
Photo 20180308_140610.jpg.jpg 04/09/2018
Photo Beaver deceiver pipe sm.jpg.jpg 04/09/2018
Photo 20180328_103701.jpg.jpg 04/09/2018
Project Application Report Application Report, 18-1378P (submitted 06/11/18 12:04:07).pdf 06/11/2018
Project Application Report Application Report, 18-1378R (submitted 04/09/18 20:14:59).pdf 04/09/2018
Project plan document Island County_Can Ku Rd 8_5x11 (3).pdf.pdf 04/09/2018
Salmon Project Proposal 18-1378 Salmon Planning Final East Camano #1300_06012018.doc.docx 06/11/2018
SRFB Review Panel Comment Form Final SRFB Review Panel Comment Form.pdf 12/17/2018
WDFW barrier & screening forms Island County_WDFW Barrier Eval Kristofferson #1300.doc.doc 06/04/2018
WDFW barrier & screening forms Island Conty_#1300 Appendix_E_CorrectionAnalysisForm.doc.doc 06/04/2018
WDFW barrier & screening forms Expanded Barrier Eval Kristofer #1300.doc 04/09/2018

Back to top Date of last change: 12/05/2024