Oak Harbor Marina Restoration Feasibility- SGP
|
Island County of; Oak Harbor Marina Restoration Feasibility- SGP (#18-2043)
Attachment #354490, 20160919_170213.jpg.JPG
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The goal of this project is to assess the feasibility of strategies to restore nearshore habitat and natural nearshore processes within and adjacent to the Oak Harbor Marina. This is a multi-benefit project in a highly visible area that offers a great opportunity for outreach and education to the public about the importance and benefits of habitat restoration and nearshore ecosystem processes. The project will take a comprehensive look at several elements of impact at the Marina and adjacent shoreline. The aspects to be assessed in the feasibility study include: (1) Armoring reduction: Remove approximately 1,575-2,025 linear feet of shoreline armoring and replace with soft shore protection, which may include native plants, gravel, sand, logs, and root masses (2) Stormwater improvement: Remove approximately 700 feet of storm drain flowing directly into the Bay and replace with a natural filtering system, such as bioswales, and explore options to increase the angle of the boat launch ramp to reduce pollutants from vehicles that have to be submerged to launch a vessel. (3) Shading reduction: Remove approximately 46,000 square feet of shading, including covered moorage, dock fingers, and creosote pile docks.
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Whidbey Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Island
|
Sections:
|
|
01
|
Township:
|
|
T32NR01E
|
Coordinates:
|
|
48.28587041 -122.63213147
|
|
|
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Oak Harbor Marina - Armor Reduction & Stormwater (#1)
|
|
Property 1 - City of Oak Harbor
|
Local Government
|
Oak Harbor Marina - Armor Reduction & Stormwater (#1)
|
|
Property 2 - WA Dept of Natural Resources
|
State Government
|
Oak Harbor Marina - Armor Reduction & Stormwater (#1)
|
|
Property 3 - U.S. Navy
|
Federal Government
|
Oak Harbor Marina-Shade reduction- ESRP funds only (#2)
|
|
Property 4 - City of Oak Harbor
|
Local Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
|
|
|
Area Encompassed (acres) (B.0.b.1)
|
2.0
|
|
Miles of Stream and/or Shoreline Affected (B.0.b.2)
|
0.48
|
Milestone Name | Target Date | Description |
Project Start
|
11/01/2018
|
|
Progress Report Due
|
06/30/2019
|
|
Data Gathering Started
|
07/01/2019
|
|
RFP Complete/Consultant Hired
|
07/01/2019
|
|
Annual Project Billing Due
|
07/31/2019
|
|
Progress Report Due
|
12/30/2019
|
|
Other
|
01/16/2020
|
Stakeholder engagement
|
Cultural Resources Complete
|
04/30/2020
|
Archaeological Monitor Required for all Ground Disturbance
|
Draft Design to RCO
|
05/01/2020
|
Draft Feasibility study, including alternatives analysis and preferred alternative.
|
Final Report Due
|
06/30/2020
|
|
Agreement End Date
|
06/30/2020
|
|
Other
|
06/30/2020
|
Feasibility study, including alternatives analysis and preferred alternative
|
Final Billing Due
|
07/31/2020
|
|