Hoypus Point Armor Removal
|
NW Straits Marine Cons Found; Hoypus Point Armor Removal (#20-1124)
Attachment #416093, ferry landing footing1.jpg
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The project will provide designs (preliminary through final), cost estimates, and permitting for the removal of approximately 325 linear feet of riprap and fill from the north end of Cornet Bay Day Use Area of Deception Pass State Park, recovering 0.33 acres of beach habitat area. Forage fish spawning has been identified in this area and removal of the armor would result in an increase in availability of spawning habitat. Armor removal would also result in improved nearshore habitat and refugia for juvenile salmonids out-migrating from the Skagit River. Partners: Island County Marine Resources Committee, Northwest Straits Foundation, Washington State Parks. This project will benefit, Chinook, coho, pinks, steelhead, Pacific Sand Lance, and Surf Smelt.
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Whidbey Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Island
|
Coordinates:
|
|
48.41132535 -122.60735408
|
|
|
Worksite Name | Scope of Work | Actual Planning Cost |
Hoypus Point (#1)
|
Agency Indirect, Cultural resources, Final design and permitting (B.1.b.11.a RCO)
|
$144,952
|
| Total | $144,952 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Hoypus Point (#1)
|
|
Property 1 - Deception Pass State Park
|
State Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
|
|
|
Area Encompassed (acres) (B.0.b.1)
|
1.5
|
|
Miles of Stream and/or Shoreline Affected (B.0.b.2)
|
0.30
|
Milestone Name | Target Date | Description |
Project Start
|
09/16/2020
|
|
Data Gathering Started
|
09/16/2020
|
|
RFP Complete/Consultant Hired
|
09/16/2020
|
Blue Coast Engineering completed feasibility and will be retained for design and permitting.
|
Draft Plan to RCO
|
03/31/2021
|
|
Progress Report Due
|
03/31/2021
|
|
Cultural Resources Complete
|
03/31/2021
|
Evidence of cultural resources compliance must be submitted to your grants manager, see special condition #1.
|
Preliminary Design to RCO
|
04/30/2021
|
Cite Design Level in Manual 18, App D-2
|
Annual Project Billing Due
|
09/30/2021
|
|
Progress Report Due
|
09/30/2021
|
|
Final Design to RCO
|
03/16/2022
|
Manual 18 App. D-3 requirements
|
Agreement End Date
|
04/30/2022
|
|
Final Report Due
|
05/31/2022
|
|
Final Billing Due
|
05/31/2022
|
|
Attachment Type | Attachment Title | Attach Date |
Agreement - State
|
20-1124 Agreement.pdf
|
11/24/2020
|
Amendment - State
|
20-1124 Amendment #1 - Time Extension.pdf
|
02/25/2022
|
Applicant Resolution/Authorizations
|
Applicant-Authorization-Resolution.docx.docx
|
02/03/2020
|
Application Document
|
ProjectApplicationReport_20-1124.pdf
|
03/02/2020
|
Application Document
|
FactSheet For Project 20-1124 (1).pdf
|
03/02/2020
|
Application Review Report
|
Grant Manager Comments Report, 20-1124P(compl 07/07/20 16:15.pdf
|
07/07/2020
|
Application Review Report
|
Application Review Report, 20-1124P(rtnd 04/20/20 07:51:30).pdf
|
04/20/2020
|
Application Review Report
|
Application Review Report, 20-1124P(compl 04/09/20 15:03:11).pdf
|
04/09/2020
|
Cost Estimate
|
HOYPUS_090PerDESIGN-EOC-23APR2021.pdf.pdf
|
05/03/2022
|
Cost Estimate
|
SAL-CostEstimate.xlsx.xlsx
|
02/15/2020
|
Cultural Resources: Formal Consultation
|
2020 SRFB DAHP Consultation.pdf
|
12/08/2020
|
Design document
|
Hoypus Point Final Design Report w_App April 2022.pdf.pdf
|
06/27/2022
|
Design document
|
HOYPUS_100pct Drawings Grant Deliverable Rev1.pdf
|
03/14/2022
|
Design document
|
20211221_Hoypus Point Design Report w_Appendices_reduced.pdf.pdf
|
12/22/2021
|
Design document
|
HOYPUS_90Per_DESIGN-23APR2021-Draft.pdf.pdf
|
05/10/2021
|
Design document
|
BCE_WE Conceptual Design _ Hoypus Point with Attachments 033.pdf
|
03/31/2021
|
Final project report
|
Final Report, 20-1124 (accepted 07/08/22 13:42:58).pdf
|
07/08/2022
|
Map: Planning Area
|
20-1124_Area Map.pdf.pdf
|
02/15/2020
|
Permit
|
055.22 SHE Decision 4.8.2022 (002).pdf.pdf
|
06/27/2022
|
Permit
|
HOYPUS POINT_PERMITS.pdf.pdf
|
06/27/2022
|
Permit
|
TAW_Hoypus_20220301.pdf.pdf
|
03/31/2022
|
Photo
|
ferry landing footing2.jpg.jpg
|
02/18/2020
|
Photo
|
ferry landing footing1.jpg.jpg
|
02/18/2020
|
Photo
|
IMG_20180605_135044.jpg.jpg
|
02/03/2020
|
Photo
|
IMG_20180605_134921.jpg.jpg
|
02/03/2020
|
Photo
|
IMG_20180605_134753.jpg.jpg
|
02/03/2020
|
Photo
|
IMG_20180605_134726.jpg.jpg
|
02/03/2020
|
Plans and Bid Specifications
|
Hoypus Point_Specs_100%_20220314_FINAL.pdf.pdf
|
03/31/2022
|
Progress report
|
Progress Report, 20-1124 (accepted 12/21/21 06:23:04).pdf
|
12/21/2021
|
Progress report
|
Progress Report, 20-1124 (accepted 03/31/21 15:30:59).pdf
|
03/31/2021
|
Project Application Report
|
Project Application Report, 20-1124P (sub 10/23/20 08:43:20).pdf
|
10/23/2020
|
Project Application Report
|
Project Application Report, 20-1124P (sub 06/29/20 16:44:43).pdf
|
06/29/2020
|
Project Deliverables
|
Daily Journal of Commerce 202204 Inv 3377066.pdf.pdf
|
05/03/2022
|
Project plan document
|
Design Investigation Docs_Combined.pdf.pdf
|
03/30/2021
|
Project Review Comments
|
Proj Review Comments LE, 20-1124P(compl 10/23/20 07:55).pdf
|
10/23/2020
|
Project Review Comments
|
Proj Review Comments Initial, 20-1124P(compl 10/23/20 07:55).pdf
|
10/23/2020
|
Project Review Comments
|
Project Review Comments Report, 20-1124P(accepted 07/07/20 1.pdf
|
07/07/2020
|