Polnell Point Armor Removal
|
    Funding |
  |
|
    Links |
  |
|
|
NW Straits Marine Conservation Foundation will remove approximately 1,400 linear feet of shoreline armor from the tombolo located adjacent to Polnell Point Road, Oak Harbor, Whidbey Island. Fill will be removed to decommission the road prism and restore cross shore tidal exchange and two derelict creosote treated pilings will be removed from the west side of the project area. Following armor removal, the site will be re-vegetated with dunegrass and other species commonly seen on spits and tombolos to provide sediment stabilization and habitat benefits including insect fallout and leaf litter input. The project will enhance forage fish spawning habitat for Pacific Sand Lance and surf smelt, which will in turn support Puget Sound Chinook, chum, coho, and pink salmon. The full project proposal includes all phases from feasibility and design, permitting, final design, project bidding, construction implementation, and vegetation management. The design portion of the project is contracted through RCO-project 20-1146.
|
General Area:
|
|
Polnell Point in Oak Harbor, Whidbey Island
|
County:
|
|
Island
|
Legislative District:
|
|
10
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Whidbey Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Island
|
Coordinates:
|
|
48.27853684 -122.55980844
|
|
|
Worksite Name | Scope of Work | Proposed Restoration Cost |
Polnell Point - NAS Whidbey (#1)
|
Agency Indirect, Architectural & Engineering (A&E), Beach nourishment (C.9.l.1), Cultural resources, Debris removal (C.9.n.1), Estuarine planting or native plant establishment (C.9.r.1), Obtain permits, Regrading of slope (C.9.i.1), Removal of existing fill material (C.9.g.1), Shoreline armor removal or modification (C.9.k.1)
|
$494,557
|
| Total | $494,557 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Polnell Point - NAS Whidbey (#1)
|
|
Property 1 - NAS Whidbey
|
Federal Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Estimated |
Restoration Metrics (rolled up from Worksite level) |
Estuarine / Nearshore Project |
Removal of existing fill material (C.9.g.1) |
|
Acres of Estuary Treated through fill material removal (C.9.g.2)
|
0.5
|
Regrading of slope (C.9.i.1) |
|
Acres of Estuary Treated through slope regrading (C.9.i.2)
|
0.5
|
Shoreline armor removal or modification (C.9.k.1) |
|
Miles of Shoreline Treated for armor modification/removal (C.9.k.2)
|
0.26
|
|
Acres of Shoreline Treated for armor modification/removal (C.9.k.3)
|
0.5
|
Beach nourishment (C.9.l.1) |
|
Miles of Shoreline Treated for beach nourishment (C.9.l.3)
|
0.20
|
|
Acres Treated for beach nourishment (C.9.l.4)
|
0.3
|
Debris removal (C.9.n.1) |
|
Acres Treated for debris removal (C.9.n.2)
|
0.1
|
Permits |
Obtain permits |
|
Number of permits required for implementation of project
|
3
|
Milestone Name | Target Date | Description |
Project Start
|
07/01/2021
|
|
Progress Report Due
|
01/15/2023
|
|
Cultural Resources Complete
|
06/30/2023
|
Federal Nexus: Based upon your grant application this project appears to be subject to Section 106 of the NHPA. Sponsor must provide evidence of S106 compliance (or qualifying exemption) as defined by the Lead Federal Agency. See special condition #1.
|
Progress Report Due
|
07/15/2023
|
|
Annual Project Billing Due
|
07/31/2023
|
|
Progress Report Due
|
02/14/2024
|
|
Restoration Started
|
03/01/2024
|
planting
|
Other
|
03/31/2024
|
As-built documentation attached in PRISM, if completed project differs from final design. Include an explanation if the constructed project differs significantly from the final design.
|
Landowner Agreement to RCO
|
06/30/2024
|
|
Preliminary Design to RCO
|
06/30/2024
|
FOR REVIEW PANEL REVIEW: The design plans and report need to include the elements specified in Manual 18, Appendix D-2. (see Special Condition #4)
|
Applied for Permits
|
06/30/2024
|
|
Permits Complete
|
06/30/2024
|
|
Final Design to RCO
|
06/30/2024
|
|
Progress Report Due
|
07/15/2024
|
|
Bid Awarded/Contractor Hired
|
07/30/2024
|
|
Annual Project Billing Due
|
07/31/2024
|
|
Restoration Started
|
09/30/2024
|
construction
|
Funding Acknowl Sign Posted
|
09/30/2024
|
|
Other
|
12/31/2024
|
Implemented planting plan (including depiction of planted area)
|
Progress Report Due
|
01/15/2025
|
|
RCO Final Inspection
|
05/31/2025
|
|
Restoration Complete
|
06/30/2025
|
construction
|
Restoration Complete
|
11/30/2025
|
planting and maintenance
|
Special Conditions Met
|
12/15/2025
|
ensure compliance with scope of work
|
Final Report Due
|
12/15/2025
|
|
Agreement End Date
|
12/15/2025
|
PROJECT CLOSING. All expenditures must be prior to this date.
|
Final Billing Due
|
02/15/2026
|
|
NOTE: This data is subject to change.
Attachment Type | Attachment Title | Attach Date |
Agreement - State
|
20-1559 Agreement - Polnell Point Armor Removal-signed.pdf
|
04/18/2022
|
Applicant Resolution/Authorizations
|
Applicant-Authorization-Resolution (Don Hunger).docx.docx
|
07/29/2020
|
Application Review Report
|
Grant Manager Comments, 20-1559R(compl 10/29/20 15:50).pdf
|
10/29/2020
|
Application Review Report
|
Grant Manager Comments Report, 20-1559R(rtnd 07/27/20 21:04:.pdf
|
07/27/2020
|
Budget Worksheet
|
esrp_budget_20-1559.xlsx.xlsx
|
07/24/2020
|
Cost Estimate
|
Polnell Point Restoration Updated EOC Table 4 7 2023.docx.docx
|
08/14/2023
|
Cost Estimate
|
Pre-Proposal DRAFT Cost Estimate-Polnell 20-1559.xlsx.xlsx
|
04/10/2020
|
Cultural Resource Screening Report
|
Project Cultural Resource Screening Report (04/19/22 08:49:5.pdf
|
04/19/2022
|
Cultural Resource Screening Report
|
Project Cultural Resource Screening Report (06/15/21 17:16:3.pdf
|
06/15/2021
|
Design document
|
Polnell Point FS Report BCE FINAL 12 15 2021 reduced rev1.pd.pdf
|
12/16/2022
|
Final project report
|
Final Report, 20-1559 (accepted 04/01/24 09:33:41).pdf
|
04/01/2024
|
Letters of Support
|
Island Co Lead Entity ltr of support_Polnell_ESRP.pdf.pdf
|
07/23/2020
|
Map: Area of Potential Effect (APE)
|
Project APE Report (04/19/22 08:49:58).pdf
|
04/19/2022
|
Map: Area of Potential Effect (APE)
|
Project APE Report (06/15/21 17:16:32).pdf
|
06/15/2021
|
Map: Restoration Worksite
|
Restoration Worksite_20-1559.pdf.pdf
|
07/23/2020
|
Map: Site Location
|
Map-LocationMap-Polnell.pdf.pdf
|
04/10/2020
|
Photo
|
Photo-ECY-1970.jpg
|
04/10/2020
|
Photo
|
Polnell Point6.jpg.jpg
|
04/10/2020
|
Photo
|
Polnell Point5.jpg.jpg
|
04/10/2020
|
Photo
|
Polnell Point4.jpg.jpg
|
04/10/2020
|
Photo
|
Polnell Point1.jpg.jpg
|
04/10/2020
|
Progress report
|
Progress Report, 20-1559 (accepted 03/05/24 08:41:17).pdf
|
03/05/2024
|
Progress report
|
Progress Report, 20-1559 (accepted 08/16/23 13:40:08).pdf
|
08/16/2023
|
Progress report
|
Progress Report, 20-1559 (accepted 12/23/22 08:46:53).pdf
|
12/23/2022
|
Project Application Report
|
Project Application Report, 20-1559R (sub 06/15/21 20:12:22).pdf
|
06/15/2021
|
Project Application Report
|
Project Application Report, 20-1559R (sub 06/15/21 16:12:25).pdf
|
06/15/2021
|
Project Application Report
|
Project Application Report, 20-1559R (sub 07/29/20 11:08:27).pdf
|
07/29/2020
|
Project Application Report
|
Project Application Report, 20-1559R (sub 07/24/20 10:10:40).pdf
|
07/24/2020
|
Project Review Comments
|
Proj Review Comments Eval, 20-1559R(compl 06/14/21 10:18).pdf
|
06/14/2021
|
Scope of work
|
20-1559 Statement of Work 101421.docx
|
10/14/2021
|
Visual Scope of Work
|
Visual Scope_Polnell 20-1559.pdf.pdf
|
07/23/2020
|
Visuals
|
Polnell Point_NWSF_ESRP.pptx.pptx
|