Project Snapshot
PRISM Project #22-1121 (Other)
Fletcher Bay Road Fish Passage Restoration
    Project Details    
Project Status:  Board Alternate since 07/01/2023
 
Project Type:  Planning
Project Sponsor:  Mid-Puget Sound Fisheries Enhancement Group
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon State Projects: $146,000
Total RCO Grant: $146,000 (92%)
Sponsor Match: $12,000 (8%)
Total Agreement: $158,000 (100%)
              Links
 

    Project Description    
Mid-Puget Sound Fisheries Enhancement Group proposes to complete final designs to replace the Fletcher Bay Rd NE culvert on Springbrook Creek with a bridge and restore approximately 400' of stream channel (including the section of creek that is currently confined within the culvert). The project is located on Bainbridge Island. The crossing under Fletcher Bay Road NE is a partial fish barrier that includes a series of concrete weirs and bank armoring upstream and downstream of the culvert, and an undersized (5 ft. wide x 100 ft. long) steel culvert. Restoration of fish passage and in-stream habitat conditions at this location is the highest-priority restoration project in the watershed. Conceptual designs for the culvert replacement and stream restoration were developed by Wild Fish Conservancy (WFC) as part of the Springbrook Creek Watershed Assessment (2018). Preliminary and final designs are currently being developed using SRFB funding from 21-1058, in coordination with a partner advisory team. The goal of the project is to restore fish passage and in-stream habitat conditions low in the Springbrook Creek watershed to benefit salmonid populations and improve the capacity of the stream to accommodate hydrologic changes associated with climate change. The project supports ESA threatened Puget Sound steelhead, coho, chum, and cutthroat trout, and may also benefit non-natal juvenile Chinook salmon rearing in Fletcher Bay.  This project is a cost increase to 21-1058. 

    Project Contacts    
         
Project Sponsor: Mid-Puget Sound Fisheries Enhancement Group Lead Entity: West Sound Partners for Ecosystem Recovery
  Project Contact: Christian Berg
cberg@bainbridgewa.gov
(206) 780-3784
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
County:   Kitsap
Legislative District:   23
Congressional District 2022:   06
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Bainbridge Island
HUC8:   Puget Sound (17110019)
WRIA:   Kitsap
Sections:   20
Township:   T25NR02E
Coordinates:   47.64308486
-122.56739896

    Worksites    
Worksite NameScope of WorkProposed Planning Cost
Springbrook Creek at Fletcher Bay Rd NE (#1) Cultural resources, Final design and permitting (B.1.b.11.a RCO) $158,000
 Total$158,000
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Springbrook Creek at Fletcher Bay Rd NE (#1)   Property 1 - City of Bainbridge Island ROW Local Government
Springbrook Creek at Fletcher Bay Rd NE (#1)   Property 2 - Loverich Property Private
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricEstimated

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 0.3
Miles of Stream and/or Shoreline Affected (B.0.b.2) 0.08

    Project Permits    
Permit TypeApplied
Date
Received
Date
Expiration
Date
Permit Number
Other Required Permits
Water Quality Certification [Section 401]
SEPA
Nationwide Permit
Hydraulics Project Approval [HPA]
Archaeological & Cultural Resources (EO 21-02)

    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Applicant Resolution/Authorizations 2022-MSFEG-ApplicantAuthorizationResolution signed2.pdf (5)..pdf 07/06/2022
Applicant Resolution/Authorizations COBI Applicant Authorization Executed.pdf.pdf 06/21/2022
Application Document 22-1121 Cost Increase Justification.docx.docx 07/08/2022
Application Review Report Grant Manager Comments, 22-1121P(compl 08/11/22 08:33).pdf 08/11/2022
Application Review Report Grant Manager Comments, 22-1121P(rtnd 07/21/22 17:02).pdf 07/21/2022
Application Review Report Grant Manager Comments, 22-1121P(rtnd 07/06/22 14:21).pdf 07/06/2022
Application Review Report Grant Manager Comments, 22-1121R(rtnd 04/01/22 16:27).pdf 04/01/2022
Application Review Report Grant Manager Comments, 22-1121R(rtnd 03/07/22 17:50).pdf 03/07/2022
Barrier evaluation form 21-1529 Fletcher Bay Rd FBRB-AppJ-BarrierEvalForm.PDF.pdf 03/15/2022
Correction Analysis Form Fletcher Bay Rd 21-1529 FBRB-AppI-CorrectAnalysisForm.PDF.pdf 03/15/2022
Cost Estimate 22-1121CostComparison.xlsx.xlsx 07/08/2022
Cost Estimate 22-1121CostEstimateVer2.xlsx.xlsx 06/02/2022
Cultural Resource Screening Report Project Cultural Resource Screening Report (07/27/23 12:54:0.pdf 07/27/2023
Cultural Resource Screening Report Project Cultural Resource Screening Report (04/26/23 16:32:1.pdf 04/26/2023
Cultural Resource Screening Report Project Cultural Resource Screening Report (10/04/22 08:26:5.pdf 10/04/2022
Map: Area of Potential Effect (APE) Project APE Report (07/27/23 12:54:02).pdf 07/27/2023
Map: Area of Potential Effect (APE) Project APE Report (04/26/23 16:32:15).pdf 04/26/2023
Map: Area of Potential Effect (APE) Project APE Report (10/04/22 08:31:59).pdf 10/04/2022
Map: Planning Area Map 22-1121 Aerial.pdf.pdf 06/02/2022
Map: Restoration Worksite Fletcher Bay Project Consolidated Maps.pdf.pdf 03/03/2022
Photo temporay fix October 21.jpg.jpg 03/03/2022
Photo October 2020 Low Flow photo 1.jpg.jpg 03/03/2022
Photo 1-3-21 upstream of culvert confined channel photo 3.JPEG.jpeg 03/03/2022
Photo 1-3-21 Streamflow photo 1 looking upstream.JPEG.jpeg 03/03/2022
Photo 1-3-21 looking downstream at culvert capacity Photo 2.JPEG.jpeg 03/03/2022
Preliminary design report BRIDGE Fletcher Bay Culvert and Weir Removal Project.pdf.pdf 03/03/2022
Project Application Report Project Application Report, 22-1121P (sub 07/27/23 12:54:01).pdf 07/27/2023
Project Application Report Project Application Report, 22-1121P (sub 08/08/22 15:52:37).pdf 08/08/2022
Project Application Report Project Application Report, 22-1121P (sub 07/21/22 16:57:44).pdf 07/21/2022
Project Application Report Project Application Report, 22-1121P (sub 06/28/22 00:00:34).pdf 06/28/2022
Project Application Report Project Application Report, 22-1121P (06/02/22 09:35:43).pdf 06/02/2022
Project Application Report Project Application Report, 22-1121R (sub 03/03/22 10:19:46).pdf 03/03/2022
Project plan document Springbrook-Creek-Assessment-Report-Narrative.pdf.pdf 03/03/2022
Project Review Comments Proj Review Comments Final, 22-1121P(compl 07/27/23 12:53).pdf 07/27/2023
Project Review Comments Proj Review Comments LE, 22-1121P(compl 07/27/23 12:53).pdf 07/27/2023
Project Review Comments Proj Review Comments Initial, 22-1121P(compl 07/27/23 12:53).pdf 07/27/2023
Project Review Comments Project Review Comments Report, 22-1121P (06/02/22 09:35:44).pdf 06/02/2022

Back to top Date of last change: 10/04/2023