Deer Creek Mouth Restoration
    Project Details    
Project Status:  Wastebasket since 05/30/2023
 
Project Type:  Planning
Project Sponsor:  Island County
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon State Projects: $43,000
Total RCO Grant: $43,000 (85%)
Sponsor Match: $7,600 (15%)
Total Agreement: $50,600 (100%)
              Links
 

    Project Description    
Deer Creek runs from Deer Lake to the East and into Saratoga Pass south of Clinton.  The outlet of the stream enters the marine environment from between two houses, through a concrete channel and then drops from an elevated height onto the beach. This outlet will need to be modified if fish passage is to be achieved.  This phase of project is feasibility study to investigate whether the fish barrier can be removed with the need to remove home(s), septic systems or displace families. According to page 65/94 of the Island County Fish Passage Barrier Inventory: Priority Area 2 report, Orr Creek (Deer Creek) has potential for spawning and rearing habitat for coho and searun cutthroat.

    Project Contacts    
         
Project Sponsor: Island County Lead Entity: Island County Lead Entity
  Project Contact: Lauren Burch

   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
County:   Island
Legislative District:   10
Congressional District 2022:   02
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Whidbey Island
HUC8:   Puget Sound (17110019)
WRIA:   Island
Sections:   30
Township:   T29NR04E
Coordinates:   47.96914343
-122.35059646

    Worksites    
Worksite NameScope of WorkProposed Planning Cost
Mouth of Deer Creek fish barrier removal project (#1) Agency Indirect, Conceptual Design (B.1.b.11.a RCO) $50,600
 Total$50,600
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Mouth of Deer Creek fish barrier removal project (#1)   Property 1 - 6655 COLUMBIA BEACH DR, CLINTON, WA Private
Mouth of Deer Creek fish barrier removal project (#1)   Property 2 - 6659 COLUMBIA BEACH DR, CLINTON, WA Private
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricEstimated

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 0.1
Miles of Stream and/or Shoreline Affected (B.0.b.2) 0.04

    Project Permits    
Permit TypeApplied
Date
Received
Date
Expiration
Date
Permit Number
None - No permits Required 02/13/2023 02/13/2023 02/13/2023 N/A

    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Applicant Resolution/Authorizations Applicant Resolution_Authorization_Deer-Creek-Mouth-SIGNED.p.pdf 05/09/2023
Application Review Report Grant Manager Comments, 23-1085P(rtnd 03/31/23 11:00).pdf 03/31/2023
Cost Estimate deer_creek_3508_cost_estimate_5-3-23 update.pdf.pdf 05/03/2023
Cultural Resource Screening Report Project Cultural Resource Screening Report (05/30/23 11:50:1.pdf 05/30/2023
Map: Area of Potential Effect (APE) Project APE Report (05/30/23 11:50:13).pdf 05/30/2023
Map: Multi-site and geographic envelope Deer Creek Topo and Profile.pdf.pdf 05/09/2023
Map: Multi-site and geographic envelope Deer Creek T Sheet.pdf.pdf 05/09/2023
Map: Planning Area deer_creek_3508_map_planning_area.pdf.pdf 02/15/2023
Monitoring activity Fish Removal Field Report.pdf.pdf 05/10/2023
Photo Deer Creek Outlet 2016-09-14.jpg.jpg 05/03/2023
Photo Deer Creek Outlet 2006-06-29.jpg.jpg 05/03/2023
Photo Deer Creek Outlet 2001-04-11.jpg.jpg 05/03/2023
Photo Deer Creek Outlet 1993-05-05.jpg.jpg 05/03/2023
Photo Deer Creek Outlet 1977-06-29.jpg.jpg 05/03/2023
Photo 1944 Army Corps Grid 15-24.jpg.jpg 05/03/2023
Photo Barrier at Bulkhead looking NW.JPG.jpg 02/14/2023
Photo Barrier at Bulkhead looking DS.JPG.jpg 02/14/2023
Photo Stream Columiba Bch to bulkhead.JPG.jpg 02/14/2023
Photo Top of bulkhead looking north.JPG.jpg 02/14/2023
Photo Barrier at Bulkhead looking DS 2.JPG.jpg 02/14/2023
Photo Barrier at Bulkhead looking US.JPG.jpg 02/14/2023
Photo 1952 structure on 6659 COLUMBIA BEACH DR.jpg.jpg 02/13/2023
Project Application Report Project Application Report, 23-1085P (sub 05/30/23 11:50:10).pdf 05/30/2023
Project Application Report Project Application Report, 23-1085P (sub 05/09/23 16:56:44).pdf 05/09/2023
Project Application Report Project Application Report, 23-1085P (sub 02/15/23 10:38:10).pdf 02/15/2023
Project Review Comments Proj Review Comments LE, 23-1085P(compl 05/30/23 11:49).pdf 05/30/2023
Project Review Comments Proj Review Comments Initial, 23-1085P(compl 05/30/23 11:49).pdf 05/30/2023
Visuals Deer Creek Mouth Restoration PPT.pdf.pdf 04/13/2023
Visuals Survey information of the site.pdf.pdf 02/15/2023
Visuals Deer CreekColumbia Beach Dr DS Culvert 3508 Basin Maps.pdf.pdf 02/14/2023
WDFW barrier & screening forms 1320355_Report.pdf.pdf 02/15/2023

Back to top Date of last change: 12/05/2024