Skip to main content
Save as PDF
Washington State Recreation and Conservation Office
Project Snapshot
PRISM Project #23-1175 (Other)
Barnabee Farms Springbrook Creek Restoration
    Project Details    
Bainbridge Island Land Trust; Barnabee Farms Springbrook Creek Rest. (#24-1167)

Attachment #497030, Outlet of Barnabee Culvert.jpg
Bainbridge Island Land Trust; Barnabee Farms Springbrook Creek Rest. (#24-1167) Attachment #497030, Outlet of Barnabee Culvert.jpg

Bainbridge Island Land Trust; Barnabee Farms Springbrook Creek Rest. (#24-1167)

Attachment #497030, Outlet of Barnabee Culvert.jpg Bainbridge Island Land Trust; Barnabee Farms Springbrook Creek Rest. (#24-1167)

Attachment #497026, Barnabee Armored and constrained channel downstream of culve
Project Status:  Board Alternate since 01/16/2024
 
Project Type:  Restoration
Project Sponsor:  Bainbridge Island Land Trust
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon State Projects: $200,000
Total RCO Grant: $200,000 (53%)
Sponsor Match: $175,109 (47%)
Total Agreement: $375,109 (100%)
              Links
 

    Project Description    
Bainbridge Island Land Trust and its partners will design, permit, and construct a project on Springbrook Cr to remove an undersized culvert that is only 67% passable to fish and remove over 187 linear ft of rock armor. Springbrook Cr, located on Bainbridge Island, is federally designated as critical habitat for ESA threated Puget Sound steelhead. A new bridge crossing, large wood, coir wraps and native vegetation will be installed along the banks where armor is removed. The project takes place on private land at stream mile 0.39. It was identified in the Springbrook Cr Watershed Assessment (SCWA) (Project 14-1547) as the second highest priority stream restoration project. It will provide fish access to over 3.76 miles of upstream fish habitat once a downstream barrier is corrected (final designs are in process), widen this section of channel to reflect natural stream conditions, improve connectivity between intact stream reaches adjacent to the existing undersized culvert, allow the stream to withstand anticipated higher flows anticipated in a changing climate, and allow for wood and sediment transport. Using the conceptual design developed by Wild Fish Conservancy (WFC) as part of the SCWA and updated May 2022, a final design will be developed with the landowner, WFC, and other stakeholders, permitting will be completed, a construction bid package will be developed, and construction will be implemented. Project success monitoring will take place for up to 3 years.

    Project Contacts    
         
Project Sponsor: Bainbridge Island Land Trust Lead Entity: West Sound Partners for Ecosystem Recovery
  Project Contact: Brenda Padgham
brenda@bi-landtrust.org
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
General Area:   Springbrook Creek, Kitsap County WA
County:   Kitsap
Legislative District:   23
Congressional District 2022:   06
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Bainbridge Island
HUC8:   Puget Sound (17110019)
WRIA:   Kitsap
Sections:   20
Township:   T25NR02E
Coordinates:   47.64174862
-122.56480061

    Worksites    
Worksite NameScope of WorkProposed Restoration Cost
Barnabee Farms Springbrook Creek Restoration (#1) Architectural & Engineering (A&E), Bridge installed or improved (C.2.g.1), Channel structure placement (C.4.d.1), Cultural resources, Obtain permits, Planting (C.5.c.1), Streambank stabilization (C.4.e.1) $375,109
 Total$375,109
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Barnabee Farms Springbrook Creek Restoration (#1)   Property 1 - Barnabee Farms Private
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricEstimated

Restoration Metrics (rolled up from Worksite level)

Instream Habitat Project
      Channel structure placement (C.4.d.1)
Miles of Stream Treated for channel structure placement (C.4.d.3) 0.06
Pools Created through channel structure placement (C.4.d.5) 8
Number of structures placed in channel (C.4.d.7) 12
      Streambank stabilization (C.4.e.1)
Miles of Streambank Stabilized (C.4.e.3) 0.04

Riparian Habitat Project
      Planting (C.5.c.1)
Acres Planted in riparian (C.5.c.3) 0.4

Permits
      Obtain permits
Number of permits required for implementation of project 5

Fish Passage Improvement
      Bridge installed or improved (C.2.g.1)
Number of bridges (C.2.g.2) 1

Riparian Habitat Project
      Planting (C.5.c.1)
Miles of streambank planted (C.5.c.4) 0.08

Fish Passage Improvement
      
Number of blockages / impediments / barriers impeding passage (C.2.b.4) 1

Riparian Habitat Project
      Planting (C.5.c.1)
Average Riparian Width 20

    Project Permits    
Permit TypeApplied
Date
Received
Date
Expiration
Date
Permit Number
Nationwide Permit
Other Required Permits
Water Quality Certification [Section 401]
SEPA
Hydraulics Project Approval [HPA]
Archaeological & Cultural Resources (EO 21-02)

    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Applicant Resolution/Authorizations 2023-5 BILT ApplicantAuthorizationResolutionSigned.pdf.pdf 04/05/2023
Application Review Report Grant Manager Comments, 23-1175R(compl 05/03/23 13:10).pdf 05/03/2023
Application Review Report Grant Manager Comments, 23-1175R(rtnd 05/02/23 15:35).pdf 05/02/2023
Barrier evaluation form Barnabee FBRB-AppJ-BarrierEvalForm.AJFINAL.pdf.pdf 01/13/2022
Correction Analysis Form BarnabeeFBRB-AppI-CorrectAnalysisForm.AJFINAL.pdf.pdf 01/13/2022
Correspondence 2023 updates to 2022 application.docx 05/03/2023
Cost Estimate Revised Barnabee SRFB-Cost Estimate 5-2-2023.xlsx.xlsx 05/02/2023
Cost Estimate 22-1319 Revised BarnabeeSRFB-CostEstimate 5-31-22.xlsx.xlsx 05/31/2022
Cost Estimate Original Barnabee FBRB-CostEstimate.xlsx.xlsx 03/03/2022
Cultural Resource Screening Report Project Cultural Resource Screening Report (01/16/24 08:43:0.pdf 01/16/2024
Cultural Resource Screening Report Project Cultural Resource Screening Report (10/04/22 08:28:1.pdf 10/04/2022
Design document Barnabee Farm Design Narrative Corrected 050223.pdf 05/02/2023
Design document Barnabee Farm Culvert and Armor Removal, Bridge Replacement,.pdf 05/23/2022
Design document Barnabee- 30% Revd 05-2-22.pdf.pdf 05/23/2022
Design document Conceptual Design Barnabee (Eddy) Culvert Replacement .pdf 01/13/2022
Map Barnabee Project SCWA Aerial.pdf.pdf 01/12/2022
Map: Area of Potential Effect (APE) Project APE Report (01/16/24 08:43:04).pdf 01/16/2024
Map: Area of Potential Effect (APE) Project APE Report (10/04/22 08:33:03).pdf 10/04/2022
Map: Area of Potential Effect (APE) Barnabee APE Maps 21.1542.pdf.pdf 01/12/2022
Map: Restoration Worksite Barnabee Project in Kitsap County.pdf.pdf 01/12/2022
Map: Restoration Worksite Barnabee Project Aerial.pdf.pdf 01/12/2022
Photo unnatural upstream channel.jpg.jpg 05/23/2022
Photo Road Fill illustration.jpg.jpg 05/23/2022
Photo IMG_9738.jpg.jpg 05/23/2022
Photo former picnic area fill and armor.jpg.jpg 05/23/2022
Photo former left bank bridge abutment.jpg.jpg 05/23/2022
Photo downstream of culvert.jpg.jpg 05/23/2022
Photo close up of channelized stream.jpg.jpg 05/23/2022
Photo channelized stream, fill, armor picnic.jpg.jpg 05/23/2022
Photo below culvert stream shape.jpg.jpg 05/23/2022
Photo below culvert stream config.jpg.jpg 05/23/2022
Photo Culvert looking upstream.jpg.jpg 05/23/2022
Photo upstream of culvert.jpg.jpg 05/23/2022
Photo upstream constrained channel.jpg.jpg 05/23/2022
Photo Barnabee Stairs and Footbridge to constructed bench.JPG.jpg 01/13/2022
Photo Barnabee Constructed Bench picnic area.JPG.jpg 01/13/2022
Photo Barnabee Armored and constrained channel downstream of culve.jpg 01/13/2022
Photo - downstream outlet Outlet of Barnabee Culvert.jpg.jpg 01/13/2022
Photo - upstream habitat Upstream of Barnabee Culvert Stream Conditions.jpg.jpg 01/13/2022
Project Application Report Project Application Report, 23-1175R (sub 01/16/24 08:43:02).pdf 01/16/2024
Project Application Report Project Application Report, 23-1175R (sub 05/02/23 16:43:10).pdf 05/02/2023
Project Application Report Project Application Report, 23-1175R (sub 04/05/23 20:22:16).pdf 04/05/2023
Project Review Comments Proj Review Comments LE, 23-1175R(compl 01/16/24 08:42).pdf 01/16/2024
Project Review Comments Proj Review Comments Initial, 23-1175R(compl 01/16/24 08:42).pdf 01/16/2024
Project Review Comments Project Review Comments Report, 22-1319R (02/28/22 10:36:00).pdf 02/28/2022
SRFB Review Panel Comment Form 22-1319 review panel comments.pdf.pdf 05/09/2023
Visuals Photos for May 2022 Conceptual Design NarrativeFINAL.pdf.pdf 05/23/2022
Visuals Barnabee SCWA Priorities.pdf.pdf 01/12/2022
Visuals Barnabee Project Fish Species Distributions.pdf.pdf 01/12/2022
WDFW barrier & screening forms Fish Passage Screening Report.pdf 01/12/2022

Back to top Date of last change: 10/15/2024