Barnabee Farms Springbrook Creek Rest.
|
Bainbridge Island Land Trust; Barnabee Farms Springbrook Creek Rest. (#24-1167)
Attachment #497030, Outlet of Barnabee Culvert.jpg
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The Barnabee Farm Springbrook Stream Restoration project will result in a final engineered design, permitting, removal of a 67% fish passage barrier undersized culvert and bridge installation. Springbrook Creek, is a stream federally designated as critical habitat for ESA threated Puget Sound Steelhead. The Barnabee Farm project takes place on private land at stream mile 0.39 and was identified in the Springbrook Creek Watershed Assessment (SCWA) (Project 14-1547) as the second highest priority stream restoration project to: address fish access to 0.16 miles of upstream fish habitat; widen this section of channel to reflect natural stream conditions; improve connectivity between intact stream reaches adjacent to the existing undersized culvert; allow the stream to withstand anticipated higher flows anticipated in a changing climate; and allow for wood and sediment transport. Using the conceptual design developed by Wild Fish Conservancy (WFC) as part of the SCWA, a final design will be developed in consultation with the landowner, WFC, and other stakeholders working in the watershed, permitting will be completed, a construction bid package will be developed, and construction will be implemented.
|
General Area:
|
|
Springbrook Creek, Kitsap County WA
|
County:
|
|
Kitsap
|
Legislative District:
|
|
23
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Bainbridge Island
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kitsap
|
Sections:
|
|
20
|
Township:
|
|
T25NR02E
|
Coordinates:
|
|
47.64163366 -122.56450704
|
|
|
Worksite Name | Scope of Work | Proposed Restoration Cost |
Barnabee Farms Springbrook Creek Restoration (#1)
|
Architectural & Engineering (A&E), Bridge installed or improved (C.2.g.1), Channel structure placement (C.4.d.1), Cultural resources, Fish passage blockages removed or altered (C.2.c.1), Obtain permits, Streambank stabilization (C.4.e.1)
|
$393,277
|
| Total | $393,277 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Barnabee Farms Springbrook Creek Restoration (#1)
|
|
Property 1 - Barnabee Farms
|
Private
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Estimated |
Restoration Metrics (rolled up from Worksite level) |
Fish Passage Improvement |
Fish passage blockages removed or altered (C.2.c.1) |
|
Number of Blockages/Impediments/Barriers Removed/Altered (C.2.c.2)
|
1
|
Instream Habitat Project |
Channel structure placement (C.4.d.1) |
|
Miles of Stream Treated for channel structure placement (C.4.d.3)
|
0.02
|
|
Number of structures placed in channel (C.4.d.7)
|
12
|
Streambank stabilization (C.4.e.1) |
|
Miles of Streambank Stabilized (C.4.e.3)
|
0.02
|
Permits |
Obtain permits |
|
Number of permits required for implementation of project
|
5
|
Fish Passage Improvement |
Bridge installed or improved (C.2.g.1) |
|
Miles of stream made accessible by bridge installation/repair (C.2.g.3)
|
0.16
|
|
Number of bridges (C.2.g.2)
|
1
|
|
|
Number of blockages / impediments / barriers impeding passage (C.2.b.4)
|
1
|
Permit Type | Applied Date | Received Date | Expiration Date | Permit Number |
Nationwide Permit
|
|
|
|
|
Other Required Permits
|
|
|
|
|
Water Quality Certification [Section 401]
|
|
|
|
|
SEPA
|
|
|
|
|
Hydraulics Project Approval [HPA]
|
|
|
|
|
Archaeological & Cultural Resources (EO 21-02)
|
|
|
|
|