| Category | Work Type | Actual Restoration Cost |
|
Fish Passage Improvement
|
Culvert installed or improved (C.2.f.1), Fish passage blockages removed or altered (C.2.c.1), Road-crossing removal (C.2.i.1)
|
$0
|
|
Fish Passage Improvement
|
Fish passage blockages removed or altered (C.2.c.1), Fishway chutes or pools installed (C.2.d.1)
|
$18,509
|
|
Instream Habitat Project
|
Channel structure placement (C.4.d.1)
|
$0
|
|
Instream Habitat Project
|
Channel structure placement (C.4.d.1)
|
$33,316
|
|
Riparian Habitat Project
|
Planting (C.5.c.1)
|
$14,840
|
|
General restoration activities
|
Implementation monitoring
|
$0
|
|
|
State and Local Sales Tax
|
$5,040
|
| | Total | $71,705 |
|
|